Vessel damage claim denied under wear and tear, maintenance and unseaworthiness exclusions
Text of the determination
Determination
Case No: 465503 Determination Page 1 of 14
Case number: 465503 9 March 2018
1 Overview
1.1 Dispute
The applicant lodged a claim on her i nsurance policy with the financial services
provider (FSP) for damage to her vessel when it partially sunk on 20 October 2016.
The FSP initially denied the applicant‟s claim on the basis the damage was caused
by pre-existing poorly repaired damage together with the failure to keep the vessel in
a seaworthy condition. It later considered the damage was also caused by wear and
tear or due to a lack of repair or maintenance of the vessel, both of which are
excluded under the policy.
The applicant seeks a review of the FSP‟s decision along with compensation for the
costs incurred as a result of the delay of the repairs to the vessel.
1.2 Issues and key findings
Is the FSP entitled to deny the claim?
The FSP is not entitled to deny the claim because the information does not show the
damage was caused by wear and tear, a lack of repair or maintenance of the vessel
or that the vessel was unseaworthy.
How should this dispute be resolved?
It is fair in all the circumstances that the FSP pay the applicant the sum of
$64,994.72 in full and final settlement of her dispute. This accounts for the following:
$7,004 in hardstand fees
$3,690.72 for the salvage and initial repair costs
$4,300 in consequential financial losses and non-financial loss
$50,000 for the cost to repair the vessel.
1.3 Determination
This determination is substantially in favour of the applicant. Within 21 days of the
applicant accepting this determination, the FSP is required to pay the applicant the
sum of $64,994.72 in full and final settlement of her dispute.
Case No: 465503 Determination Page 2 of 14
2 Reasons for determination
2.1 Is the FSP entitled to deny the claim?
Policy covers all risks of physical damage subject to exclusions
There is no dispute the applicant suffered physical loss of or damage to the vessel
during the policy period and as such has established a prima facie claim, subject to
the conditions and exclusions contained in the policy. The onus, therefore is on the
FSP to establish an exclusion or any other condition on which it relies to refuse the
claim.
The FSP relies on a number of policy exclusions to deny liability. These include the
following:
any cost of repairing damage to the vessel which has been caused by the wear
and tear of a part of the vessel
loss of or damage to the vessel that is attributable to a lack of repair or
maintenance of the vessel
loss of or damage to the vessel that is attributable to unseaworthiness of the
vessel.
The FSP has to prove on the balance of probabilities that the cause of damage falls
within any of these policy exclusions.
No evidence that damage due to lack of repair or maintenance
The FSP now accepts the main cause of the water entering the vessel was the
Packless Seal System (the shaft seal) moving. However, the FSP says this moved
due to wear and tear or lack of maintenance.
No expert evidence has been provided to show the shaft seal failed due to any lack
of maintenance.
The FSP engaged marine surveyor (JS) to review the vessel. JS, in an email dated
13 December 2016, said the damage could have been caused in the following
manners:
grubscrews that hold the collar in place must have loosened somehow, either because they
were not tight enough in the first place or because of adverse vibration of the shaft
This does not attribute the damage to any lack of maintenance.
The applicant ‟s marine engineer (MG) specifically says the shaft seal does not
require servicing or maintenance.
The FSP has provided a weblink to support its position that the shaft seal requires
maintenance. However, in the absence of any expert saying the shaft seal failed due
to lack of maintenance, the Panel is not persuaded the exclusion is engaged by
reference to this weblink alone.
Case No: 465503 Determination Page 3 of 14
No evidence damage caused by wear and tear
The policy does not define the term „wear and tear‟. Case law indicates wear and tear
means damage due to ordinary usage.
The FSP submits the movement of the shaft seal (possibly due to the usual
vibrations of the shaft) is considered to be wear and tear. It states the manufacturer
advises the hose clamps need to be regularly checked to avoid this from happening.
The applicant has presented information to show the part of the shaft seal which
became loose - the rotor - does not experience wear during operation. Further, there
is no evidence to show any hose clamps on the shaft seal caused it to move.
Based upon the information available, it is unclear why the shaft seal moved.
The only evidence supporting the FSP‟s position is JS‟s email dated 13 December
2016. However, this is speculative as JS did not investigate this possible cause when
ins pecting the vessel. His opinion in the email was offered in response to the FSP‟s
query as to why the shaft seal moved.
Given this, the Panel is not satisfied the FSP has shown on the balance of
probabilities that wear and tear caused the shaft seal to mo ve.
No evidence damage caused by vessel being unseaworthy
The FSP says the vessel was unseaworthy due to the following:
sterntube seal was not properly maintained
a lack of seals on the rudder stocks
the bilge pumps being inoperable due to failed float switches or disconnected
wiring
There is no evidence to show the sterntube seal was not properly maintained. It is
not mentioned in either of the expert‟s reports.
There is also no evidence of a lack of seals on the rudder stocks. JS or MG makes
no reference to these seals being missing.
JS suggested the FSP obtain an electrician‟s opinion regarding the condition of the
batteries to confirm if the bilge pumps had failed before the water inundation. The
FSP has not produced such evidence. Therefore, the evidence does not establish
these were inoperable before the inundation.
The applicant provided a survey report of 16 September 2015. This comprehensive
report showed the vessel was seaworthy.
Given all this, the Panel is not satisfied the FSP has shown the damage was caused
by the vessel being unseaworthy.
Accordingly, after careful consideration of all the evidence and arguments, the FSP
has not established any of the exclusions. Therefore, the FSP is required to
indemnify the applicant for this claim.
Case No: 465503 Determination Page 4 of 14
2.2 How should this dispute be resolved?
Applicant seeks the FSP to repair her barge
The applicant‟s claim has evolved during the dispute and includes the following:
1. $7,004 for marina hardstand fees and associated costs
2. $6,102 for marina berthing fees, increasing at $1,017 per month (this figure is
for a six month period)
3. $16,000 for travel to and from her island to the mainland (estimated from the
date of loss to 1 March 2017, increasing at $1,000 per return trip)
4. $3,690.72 for initial salvaging and repair work done by MG, paid
5. $41,245.84 for repairs initially assessed by MG (incomplete according to the
applicant and duplicates some of the repairs below)
6. $33,900.66 for diesel motors electronics, various
7. $27,307.16 for main diesel engines, repair
8. $47,462 for 240v generator (replacement and installation)
9. $4,200 for six large marine batteries
10. $40,546 for two gearboxes (replacement of port and starboard)
11. $3,300 for electric/hydraulic controllers.
There appear to be overlaps and duplications in the applicant‟s claim. For instance:
the applicant‟s email dated 24 April 2017 provides a total of $28,212 for both
the purchase of the 240v generator and installation – however, in her email
dated 21 May 2017, she included $28,212 as the installation costs alone
MG‟s scope of w orks appears to overlap with the amounts set out between 6
and 8.
FSP can cash settle the cost of repairs
The policy states with regard to claims for partial loss:
„Claims for partial loss of or damage to the vessel shall be settled on the basi s of reasonable
repair and/or replacement costs nece ssary to re -instate the vessel nearly as is reasonably
possible to its pre-incident condition where a claim is recoverable under this insurance. These
necessary costs will include the cost of transporting the vessel to the nearest appropriate repair
facility.‟ [our emphasis]
Following from this, the policy says the following regarding partial losses:
“… in the event of partial loss a deduction of 30% will be made from the claim settlement in
respect of parts or materials where the part which is repaired or replaced was, at the time of the
incident, more than 2 years old.
The deduction will not be applied to labour costs, or the repair of the basic hull and deck
structures of the vessel.”
When these provisions are considered together, it is reasonable to conclude the
policy allows the FSP to cash settle a claim when a deduction applies to parts. This is
because it would be impractical for the FSP to attempt to repair the vessel in
circumstances when the applicant would have to contribute to the costs of various
parts.
Case No: 465503 Determination Page 5 of 14
Panel proposes to provide a cash settlement for this dispute
Given the longstanding nature of this dispute, the applicant‟s circumstances and the
parties disagreeing about the scope of works, the Panel considers it is fair in all the
circumstances to provide a cash settlement.
This is because such an outcome would provide finality if it is accepted by the
applicant.
In contrast, if the applicant‟s preferred outcome of having the FSP repair the vessel
was undertaken, there is potential for these issues to arise:
disagreement about the scope of works when they are finalised – this is likely
given the current position of the parties and the increasing amount of the
applicant‟s claim
what parts should be subject to a deduction
concerns about the contractors the FSP wishes to authorise .
Similar issues would also likely arise if the parties were asked to assess the loss and
secure quotes for the outstanding repairs.
FSP responsible for MG’s costs for initial repairs
The applicant seeks $3,690.72 for the engineer who attended, kept the vessel afloat
and conducted the initial investigations to determine the cause of the partial sinking.
The applicant has substantiated these costs with invoices from MG.
It is fair for the FSP to pay these costs. Particularly given the evidence shows it is
likely these costs mitigated the costs of the claim.
FSP should pay for hardstand fees
The applicant seeks $7,004 in hardstand and associated fees charged by the marina
slipway. She has presented a tax invoice to show the costs incurred.
The information exchanged shows the applicant arranged for staff at the marina to lift
and place the vessel on a hardstand on 21 October 2016. The applicant says the
FSP was aware of this pursuant to their discussion on the same date.
In a letter of 4 November 2016, the FSP agreed to meet the cost for the salvage,
survey and assessments undertaken to identify the cause of the damage. However, it
denied the claim for the damage based on its exclusions.
On 7 December 2016, the FSP formally declined any liability under the policy. The
FSP also said it would not accept any liability for the hardstand costs or any other
expenses incurred.
On 20 December 2016, the FSP issued its final decision which maintained its denial.
The vessel was placed back in the water on 21 December 2016.
The applicant argues the FSP wanted her to place her vessel on the slipway
hardstand so its surveyor could inspect and assess the barge. The information shows
the FSP‟s survey or inspected the barge on 26 October 2016. It is clear such an
inspection would have been most effective if the vessel was on a hardstand.
Case No: 465503 Determination Page 6 of 14
The applicant also indicates the vessel was on the hardstand so the FSP could
complete the repairs. This is consisten t with MG‟s quote which said the vessel had to
be on a hardstand.
Given this, the Panel accepts the FSP should reimburse the hardstand fees. They
were reasonably incurred to allow the vessel to be inspected. Further, repairs could
only be effected if the vessel was on a hardstand. It would only have been apparent
to a reasonable person in the applicant‟s circumstances that the FSP would not be
paying for the cost of repairs after sending its final decision letter. The applicant
removed the vessel from the hardstand a day after this letter.
Accordingly, the FSP should pay the marina‟s invoice of $7,004.
Marina slipway fees are recoverable losses
The applicant seeks $6,102 for marina slipway casual berthing fees charged and
paid from 8 January 2017 to July 2017. She indicates the costs continue to increase
at $1,017 per month.
The FSP says these costs are consequential and excluded under the polic y.
However, the Panel does not accept the policy exclusion applies. The applicant‟s
claim for this cost is not based on a loss suffered from an insured event. Instead, it is
a financial loss she has incurred due to the FSP‟s decision to incorrectly deny th e
claim.
This does not fall within the policy exclusion.
The FSP has also argued the applicant failed to mitigate her loss as she did not
explore options to relocate the vessel to her own island‟s marina.
There is merit to the FSP‟s position.
In the Pan el‟s view, after the parties undertook an unsuccessful conciliation on 8
March 2017, it ought to have been apparent to the applicant that any possibility for
the FSP to willingly change its position would have been remote. Therefore, it was
reasonable to explore options to mitigate her losses. This would include transporting
the vessel to its usual berth whilst she continued pursuing the dispute.
However, for reasons to follow, any amount payable for this loss would be subject to
FOS‟s cap of $3,300 for con sequential financial losses.
Berthing and transport costs are consequential financial losses
Consequential financial losses are losses that are indirectly caused by the FSP‟s
conduct. This would generally include losses that would not have been incurred by
most insureds. That is, it is a loss specific to the applicant‟s circumstances.
In this case, the applicant‟s claim for the marina slipway fees was due to the following
factors:
the applicant‟s residence and the vessel‟s usual berthing is on an island
the applicant does not pay for berthing fees at its usual berthing place
the vessel was damaged whilst on the mainland, which the applicant regularly
travels to for both commercial and personal reasons
Case No: 465503 Determination Page 7 of 14
the availability of repairers are on the mainland – this was one of the reasons
the vessel remained there.
Given this, the Panel does not accept the applicant‟s circumstances would be similar
to most insureds of this policy. Instead, it is clear they are specific to her situation.
Therefore, the applicant‟s cl aim for these costs are consequential financial losses
which resulted from the FSP‟s action. That is , the FSP‟s erroneous decision to refuse
the claim, but are subject to the Service‟s $3,300 cap, per its Terms of Reference.
Further, this cap would encompass her claim for travel costs to and from her island to
the mainland. This is because such a situation is specific to her circumstances.
Accordingly, the Panel proposes to award $3,300 for these aspects of her claim. This
is because the evidence shows the applicant‟s marina slipway fees alone would have
likely exceeded this cap and are substantiated.
Outstanding repair costs
As discussed, there is overlap in the amounts being sought by the applicant for the
outstanding repairs.
MG‟s quote is economical compared to the amounts quoted by C. Further, it appears
MG is appropriately qualified and capable of conducting the repairs. Particularly
given:
the applicant has referred to the contractor‟s excellent work in salvaging the
vessel
the FSP has provided no evidence to indicate MG‟s skills and experience are
insufficient.
The applicant says MG‟s quote was rushed and incomplete. There is no evidence to
support this. Further, MG‟s quote appears fairly extensive and detailed.
The FSP has submitted the cost of repairs are approximately $14,600. The Panel is
not persuaded by this. The FSP has provided no quote or expert evidence in support
of its position. The amounts allowed for parts and labour are significantly less than
those provided by both MG and C. For instance, the FSP allowed $3,500 for the
generator when MG and C quoted in excess of $18,000.
Given this, the Panel prefers to rely upon MG‟s quote in considering an appropriate
amount for the cost of repairs. However, the Panel also accepts there are aspects
within the quote that are either incomplete or could lead to additional costs. These
include:
hardstand costs that are not quoted – the FSP‟s amount estimated $2,000 for
this alone
parts and labour quoted are likely outdated and would have increased
additional damage that is likely to have been identified when items are removed
and reviewed (e.g. hydraulic switches and batteries the applicant says was
caused by the event)
Case No: 465503 Determination Page 8 of 14
Therefore, the Panel is conscious that any allowance provided should take into
account these contingencies as well as the fact the FSP can apply 30% depreciation
to parts more than two years old.
Given this and the above factors, and after careful consideration of all the available
evidence and information, the Panel proposes to award $50,000 towards the cost of
repairs.
This does not include any allowance for the replacement of the gearboxes for the
following reasons.
FSP not required to replace the gearboxes
The applicant has claimed that two gearboxes have been damaged and require
replacement. This was submitted in an email dated 4 July 2017.
The FSP has disputed liability saying they likely require replacement because the
applicant failed to mitigate her circumstances. The FSP also noted that MG only
referred to one gearbox being damaged.
The Panel is persuaded by the FSP‟s position. MG‟s quote only refers to one
gearbox being damaged. The quote did not require this gearbox to be replaced.
Further, MG said that the engine room should be washed down with fresh water. This
is likely to remove any residual salt water from the area.
It does not appear this mitigating action was taken despite MG‟s suggestion being set
out in a quote dated 12 November 2016.
The applicant says MG did one flush on both gearboxes. However, the only evidence
of this being done was when the vessel was salvaged. This is set out in MG‟s
invoice. There is nothing to indicate MG undertook any subsequent washing down in
line with its quote dated 12 November 2016.
Given this, the evidence shows the gearboxes require replacement due to the
applicant failing to mitigate her situation by washing them down with fresh water.
Therefore, the Panel does not accept the FSP is liable to pay for the cost of this.
FSP should pay $1,000 in non-financial loss
FOS can award up to $3,000 if the FSP causes the applicant to suffer an unusual
degree or extent of inconvenience, interference or delay. FOS awards compensation
conservatively. Applicants are expected to be moderately robust and bear the normal
degree of inconvenience experienced when a problem occurs.
The Panel does not accept the FSP acted unreasonably throughout. There were
legitimate concerns that the cause of the loss did not fall within the policy terms.
However, during the course of the dispute, it became clearer that:
the cause of loss was the shaft seal, and
the successful application of the policy exclusions being relied upon was
remote.
Case No: 465503 Determination Page 9 of 14
Further, the FSP‟s offer to settle for the cost of repairing of the vessel on a without
prejudice basis did not mitigate the situation. This is because the offer was manifestly
low given it was less than half of MG‟s quote and not based on any other quote.
Given this, the Panel accepts the applicant suffered an unusual degree of stress and
inconvenience during the course of the dispute. The Panel also accepts the impact of
these factors would have been relatively significant given how reliant the applicant
was on the vessel.
As such the Panel considers an award of $1,000 for non-financial loss to be fair in all
the circumstances.
Case No: 465503 Determination Page 10 of 14
3 Supporting information
3.1 Financial Ombudsman Service (FOS) approach to this dispute
This dispute has not been the subject of a FOS recommendation. Due to the nature
of the dispute, it has been referred directly to a Panel for determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS (or predecessor scheme)
decisions.
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered (whether or not it is expressly referenced in this determination).
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues which are
considered to be directly relevant to the outcome only.
3.2 Relevant policy sections
Subject Terms
§1. Insurance
Cover
All Risks:
This insurance covers th e insured against all risks of physical loss of or damage
to the vessel occurring during the policy Period subject to the Terms, Conditions
and Exclusions of this insuranc e.
§4. Exclusions This insurance does not cover:
…
4. Unless specified in the schedule, any cost of repairing damage to the vessel
which has been caused by the wear and tear of a part of the vessel.
If the insured selects wear and tear cover then the cost of repair of any damage
proven to have been caused by wear and tear of a part will be covered, but not
the cost of the part which has sustained wear and tear.
6. Loss of use, Loss of Charter Inc ome (unless otherwise specified in the
schedule), loss of mark et value, diminution of racing performanc e, diminution in
aesthetic appearanc e , loss of any manufacturer‟s or supplier‟s warranty or any
other form of non physical loss or damage;
7. Loss of or damage to the vessel that is attributable to:
7.1 recklessness of the insured;
7.2 unseaworthiness of the vessel
7.3. a lack of repair or ma intenance of the vessel; or
7.4 failure to comply with statutory requirements.
§3. Agreed 3. Partial Loss:
Case No: 465503 Determination Page 11 of 14
Subject Terms
Fixed Value,
Total and
Partial Loss
and
Deductible(s)
Claims for partial loss of or damage to the vessel shall be settled on the basis of
reasonable repair and/or replacement costs necessary to re - instate the vessel
nearly as is reasonably possible to its pre - incident condition where a claim is
recoverable under this insuranc e. These necessary costs will include the cost of
transporting the vessel to the nearest appropriate repair facility. This clause will
also apply to the insurance of any other property insured with specified limits
under Section A §2 of this insurance.
4. New For Old:
For Partial Loss claims, the insured has the option to select co ver either with or
without a deduction due to the age of the part repaired or replaced.
If the insured selects cover without a deduction, then no deductions will be made
for any claim for New for Old under this §3.4.
If the insured selects cover on terms w hich include a deduction due to the age of
the part repaired or replaced and unless otherwise specified in the schedule, in
the event of partial loss a deduction of 30% will be made from the claim
settlement in respect of parts or materials where the part which is repaired or
replaced was, at the time of the incident, more than 2 years old.
The deduction will not be applied to labour costs, or to the repair of the basic hull
and deck structures of the vessel.
5. Deductibles:
The deductibles specified in the schedule will apply to each claim except that in
no circumstances shall a deductible apply in respect of:
5.1 a total loss of the entire vessel under Section A §3.2;
5.2 any payments made under Section A §2.1 - 7;
5.3 any claim under Section A §2. 11 for Lo ss of Charter Income, but the
first 7 days of Loss of Charter Income are not rec overable; and
5.4 any claim for loss or damage arising whilst the vessel is moored at its
usual berth, pontoon or private jetty or when the vessel is ashore within a
commercial marina providing the vessel is not moored on a swing mooring
or is at anchor.
3.3 Reports
Record Key points
Applicant’s consultant
(JL)
Survey i nspection report
16.09. 2015
Surveyed on 15 September 2015 for insurance.
Barge launched in 1992 and custom built.
JL was able to inspect and evaluate the s tern b earing ( PSS Water
Sealed ) and after visually observing the item, it appeared to be
functioning as intended allowing for normal wear and tear.
JL was able to inspect and evaluate the twin inboard engine (with
PSS gland on starboard shaft w ater cooled) and after visually
observing the component, it appeared to be functioning as intended
allowing for normal wear and tear.
JL was able to inspect and evaluate the four bilge pumps and after
visually observing them, they appeared to be functioning as
Case No: 465503 Determination Page 12 of 14
Record Key points
intended allowing for normal wear and tear.
JL was able to inspect and evaluate the generator and after visually
observing the unit, it appeared to be functioning as intended
allowing for normal wear and tear.
JL wa s able to inspect and evaluate the vessel‟s electrical system
and after visually observing the unit, all parts appeared to be
functioning as intended allowing for normal wear and tear.
JL commented the vessel was seawort hy and well found.
JL valued the mar ket value of the vessel and associated equipment
to be approximately $160,000.
FSP’s surveyor (JS)
Survey report
31.10. 2016
Inspected vessel on 26 October 2016 following a partial sinking .
Observed uncoated aluminium and crack in bottom of starboard
skeg indicated cont act with the seabed.
Sighted crack below welded portside skeg to hull join was possibly
caused by shock of repeated seabed contact.
Concluded slow ingress of seawater via crack in port skeg and
failure of automatic bilge pump operation would have caused the
vessel to gradually take on water and sink.
Once internal water level had reached the port rudder stock PSS
seal, water ingress would have rapidly increas ed via the 8mm gap
between ceramic seal faces.
Applicant’s marine
engineer (MG)
Repair quote
1 2 .11. 2016
$41 , 245.84 total for parts and repairs, including:
Labour to attend vessel at marina berth.
Assist in removal of ingressing water.
Pump out remaining water once on hardstand.
Wash down engine room with fresh water
Drain genset oil and both gear box oil.
Refill with diesel oil combination.
Run up port motor, starboard motor would not start due to ECM unit
malfunction due to being submerged in salt water.
Remove and refit new starter motors.
Remove starboard gear box to overhaul and r efit.
Replace ECM unit on starboard motor, clean all connections,
replace wiring where needed, changed all pumps, fit overhauled
hydraulic pump, remove and reinstall genset, check over all 240V
wiring, relaunch vessel to conduct seatrials.
Applicant’s marine
engineer (MG)
Statement
13.11. 2016
The marina contacted him to urgently attend to sinking vessel.
Found engine room flooded.
Three auxiliary 240 volt submersion pumps were engaged to pump
out water.
MG turned off all through hull seacocks.
After 45 minutes of pumping it was evident that we were not
overcoming water int rusion.
Travel lift was engaged to hold vessel in slings to avoid vessel
sinking.
On close inspection with aid of diving goggles, MG found that the
starboard [Packless Seal System] PSS shaft seal rotor had moved
from the seated position with a gap of more than 12mm.
Case No: 465503 Determination Page 13 of 14
Record Key points
MG obtained a ball peen hammer from adjacent vessel and knocked
rotor up to seated position. Onc e this was completed, bilge pumps
overcame the water intrusion rate.
Vessel was lifted out of the wat er and plac ed on hardstand and had
considerable amount of wat er remaining in bilge.
No noticeable leaks from vessel hull any where.
Concluded that the water int rusion had come from starboard side
PSS seal assembly.
FSP’s surveyor (JS)
Comments
2 2 .11. 2016 (or 23.11.2016 )
Photographs provided by MG of starboard and port PSS seals
indicate that the seal on the starboard shaft has moved up the shaft,
covered the corrosion stain and releas ed the seal pressure letting
water in.
FSP’s surveyor (JS)
Comments
2 4 .11. 2016
Water would not have got in through the rudder stock as the seal is
60mm above the waterline.
After speaking to MG the day before, together with his photographs
of the propeller shaft seals , JS believe d that the bulk of the water
came in through the starboard propshaft seal.
If the bilge pumps had been working they would have kept up with
the water ingress until the batteries went flat, however, the forward
pump did work when JS switched it to manual set ting, but that
doesn‟t mean the batteries were charged enough to run the pumps
at full capacity.
No pumps functioned via float switches during the survey even after
he switched them to automatic on the electrical panel but, they may
have failed during the immersion.
FSP’s surveyor (JS)
Comments
13 .1 2 . 2016
T he grubscrews that hold shaft seal collar in place must have
somehow loosened (either because they were not tight enough or
due to adverse vibration of the shaft ).
It is also possible the threadlock was not used on the screws, but JS
was not sure if this was common practice.
FSP may require an electrician to inspect the condition of the
batteries and confirm why the bilge pumps were not working.
Applicant’s marine
engineer (MG)
Tax invoice #81
01.02. 2017
$ 1 , 590.82 for repairs to barge
parts (machine long and short bearings and fasteners) and labour
Applicant’s marine
engineer (MG)
Tax invoice #82
01.02. 2017
$ 2 , 099.9 0 for repairs to barge
Once out of water, engine room compartment was drained of
remaining water, engine compartment was degreased and cleaned
out with fresh water. Gear boxes were drained of ingressed sea
water, diesel and oil additives was then int roduced int o gear boxes.
All submersed electric items were sprayed with a dewatering fl uid,
port motor was started, starboard motor could not be started due to
ECM unit having been submers ed.
Applicant’s marine The PSS or Packless Seal System fitted to the barge is not an item
Case No: 465503 Determination Page 14 of 14
Record Key points
engineer (MG)
Statement
27.02. 2017
that would require maintenanc e or servicing.
It is designed to be maintenance free once installed to
manufacturer‟s specifications.
3.4 Key references
JSM Management Pty Ltd v QBE Insurance (Australia) Ltd [2011] VSC 339.
Policy schedule and product disclosure statement.
Applicant‟s submissions, photographs, reports and quotes.
FSP‟s submissions, reports and photographs.
Correspondence between the parties.
Word Definition
Wear and tear (Oxford English dictionary) d amage or deterioration sustained from continuous
use
Wear and tear (Macquarie dictionary) diminution, decay, damage, or injury sustained by
ordinary use
Wear (Macquarie dictionary) to impair, det eriorate or consume gradually by use
or any continued process
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.