Home / Financial Firm (Unknown - Insurer) / Determination 465290

Determination 465290

Storm water damage cash settlement amount and claim delay

FirmFinancial Firm (Unknown - Insurer)
Decided2017-09-15
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$2,331
Non-financial loss$500
Amount claimed$7,800
SourceAFCA PDF

Summary

After a storm, the FSP accepted a water damage claim and offered a $2,331.49 cash settlement, which the applicant disputed as too low. AFCA found the FSP's quote fair, excluded balcony maintenance work, and ordered the cash settlement with statutory interest plus $500 for delay-related inconvenience.

The FSP's quotation was the only reliable costing, as the applicant's invoice did not break down the covered repairs, and the policy excludes maintenance work.

Issues

Subjects and remedies

pay claimpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 465290 Determination Page 1 of 3 Case number: 465290 14 September 2017 1 Overview 1.1 Dispute The applicant holds a home insurance policy (Policy) issued by the financial services provider (FSP). The Policy started on 17 June 2015 and renews annually. The Policy covers loss or damage caused by insured events only, subject to exclusions. Following a storm, the applicant lodged a claim for water damage to the insured property. The applicant says that:  the FSP has unreasonably delayed the assessment of the claim, and  the cash settlement offer made by the FSP is inadequate. The applicant is seeking a review of the amount offered to cash settle the claim and compensation for stress and inconvenience caused by the delay. 1.2 Issues and key findings Is the cash settlement amount fair and reasonable? Based on the information provided, the cash settlement amount based on the FSP’s quotation fairly represents the cost to the FSP to repair the damage that is cove red under the Policy. Is the applicant entitled to compensation? The FSP has acknowledged that the handling of the claim fell below the expected standard. The applicant has established that the delays caused him stress and inconvenience. The applicant is entitled to $500 compensation for non-financial loss. 1.3 Determination This determination is substantially in favour of the FSP. Within 14 days of the applicant’s acceptance of this determination the FSP must :  cash settle the applicant in the amount of $2,331.49 plus interest at the statutory rate, and  pay the applicant $500 in compensation. Case No: 465290 Determination Page 2 of 3 2 Reasons for determination 2.1 Is the cash settlement amount fair and reasonable? The Policy provides cover for insured events including storm damage The Product Disclosure Statement (PDS) set out the terms and conditions of the Policy. It says: We cover loss or damage to the building caused by a storm. There is no dispute that a storm caused damage to the insured property on or around 4 June 2016. The applicant lodged a claim for the damage on 20 June 2016. Cover for storm damage is subject to general exclusions The Policy also contains exclusions. The onus rests with the FSP to establish on the balance of probabilities that an exclusion applies in order to deny a claim. The PDS says: You are not covered under any section of your policy for damage, loss, cost or legal liability that is caused by, arises from or involves: Wear, tear and gradual deterioration Wear, tear, rust, fading, rising damp, mould, mildew, corrosion, rot, action of light, atmospheric or climatic conditions or gradual deterioration such as but not limited to:  tiles and their adhesive or grouting breaking down;  weat hering of roof tiles or roof ridge capping;  gradual weathering and breakdown of bricks, mortar or concrete. On 27 July 2016 the FSP’s assessor inspected the property. He said: During our roof inspection we found that the roof has not been damaged due to the recent storm event however we have found maintenance issues to the roof. Roof plumber to attend and raise and repair lead flashing at front bay window as there is underlying issues but not storm related, roof plumber to also investigate cause of leak at rear balcony area. I do believe this is maintenance as there is no visible damage but think it is to do with the drainage pipe as seen in the photos. Policy holder will need to have these fixed before internal are to proceed. On 12 October the property was reinspected and the assessor reported that: The customer acknowledged maintenance required to the roof area to prevent further water ingress during heavy rain periods…The customer is happy with today’s outcome and ready to proceed with external repairs as per original SOW only (no additional work required). On this basis the FSP has accepted the claim for the resulting damage, but required the applicant to undertake the following maintenance repairs first:  raise and repair roof lead flashing at the front bay window, and  investigate and fix leak at rear balcony. The FSP has offered to cash settle the claim for the resulting damage Based on the claim notes there was some confusion about whether the maintenance work as required had been completed. In order to try and resolve the dispute the FSP offered to cash settle for the damage that is covered under the Policy in the amount of $2,331.49. The applicant has not accepted this offer. He says that the cost of repairing exceeds the amount offered. The applicant provided an invoice for repairs for $7,800. The invoice does not identify the areas of damage that were repaired. It says: Case No: 465290 Determination Page 3 of 3 Investigat e balcony leaking into eaves lining Repair waste pipe on balcony Remove rotting timber caus ed by leak and repair timber frame Replace eave lining sheet Set eaves Paint eave lining to match existing eaves I am satisfied that the work to the balcony was not covered under the policy as it was identified as a maintenance issue at the first inspection. The FSP’s quotation does include the cost of repairing the eaves. The applicant was unable to provide any further information about the breakdown of costs. In the absence of the breakdown of the cost, the applicant has not been able to establish what it actually cost him to repair the damage covered by the Policy. The FSP has based the cash settlement of the quotation provided by its assessor. In the absence of any other information, I am satisfied that the amount of $2,331.49 is fair and reasonable. An award of interest on the cash settlement amount in accordance with section 57 of the Insurance Contracts Act should be applied from the date the applicant paid for the repairs until the date on which the FSP satisfies this determination. The applicant must supply the FSP with proof of payment and the date on which payment was made for the repairs in order for the award of interest to be paid. 2.2 Is the applicant entitled to compensation? The FSP has acknowledged that its builder caused delays and inconvenience In its Notice of Response the FSP has accepted that the service delivered by its appointed builder (HR) fell short of the standards that the applicant was entitled to expect. The FSP has apologised for the inconvenience caused. The applicant did notify the FSP that the time taken was causing him inconvenience as he is required to travel for work and had to attend the property for inspections on numerous occasions. It is fair in all of the circumstances that an award of $500 for non-financial loss be awarded to the applicant.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.