Determination 464408

Cash settlement amount for storm damage repairs

FirmFinancial Firm (Unknown - Insurer)
Decided2017-10-18
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$195,000
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's home was damaged in a storm and the insurer offered $162,152.05 cash settlement for repairs, while the applicant's builder quoted a much higher figure. AFCA accepted the insurer's scope of works but required a $195,000 cash settlement that includes an allowance for transferred repair risk.

An insurer exercising its cash settlement discretion must do so fairly, including an allowance for the risk it transfers to the insured.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 464408 Determination Page 1 of 4 Case number: 464408 11 September 2017 1 Overview 1.1 Dispute This matter involves a claim by the applicant under her Home Insurance Policy, held with the financial service provider (FSP), following damage to the home. Whilst the FSP has accepted the applicant’s claim, a dispute continues as to the extent of the FSP’s obligations under the terms and conditions of the policy. 1.2 Issues and key findings What is the extent of the FSP’s obligations under the terms and conditions of the policy? Upon acceptance of this determination by the applicant, the FSP is to pay the applicant the total amount of $195,000 to meet its obligations in respect of repairs to the home under the terms and conditions of the policy. 1.3 Determination This determination is partially in favour of the applicant. Upon acceptance of the determination by the applicant, the FSP is to pay the applicant the total amount of $195,000 in settlement of the applicant’s claim in respect of repairs under the terms and conditions of the policy. The amount of $195,000 includes the previous cash settlement offer of $162,152.05. The FSP is not required to pay interest on this amount. The FSP is not required to pay non-financial loss compensation. The FSP has met its obligations under the policy in respect to temporary accommodation and is not required to make any further payment with regard to temporary accommodation. Case No: 464408 Determination Page 2 of 4 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the material exchanged. This determination follows consideration of all of the information exchanged and is based on what is fair in the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice and where applicable, prior determinations. This determination is made by a panel consisting of the Panel Chair Ombudsman together with a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. 2.1 What is the extent of the FSP’s obligations under the terms and conditions of the policy? Circumstances of the loss There is no dispute that the applicant’s home and contents suffered damage in a significant weather event on or about 16 December 2015. The FSP accepted the applicant’s claim for contents and has made payment under the policy provisions. The FSP also accepted t he applicant’s claim in respect to damage to the home and has made a cash settlement offer in the amount of $162,152.05 for repairs to the building. The offer from the FSP is based upon a report from a building consultant (IT) and a scope of works also prepared by the building consultant. The applicant has provided a report from a builder which refers to a much higher settlement figure in respect of the repairs to the home. However, IT identified a number of issues with the home, unrelated to the significant weather event which caused damage to the home. The scope of works provided by IT relates to the damage to the home as a result of the significant weather event. The applicant’s builder’s scope of works and quotation for a significantly greater amount, does not confine itself to the weather related damage but provides for coverage of all remediation issues at the home. In response to the report and scope of works from the applicant’s builder, IT provided an additional response. IT confirmed that they inspected the property on three occasions, 21 December 2015, 27 January 2016 and 30 April 2016, over which time they took some 190 photographs. IT identified a number of issues with the property, including:  deterioration Case No: 464408 Determination Page 3 of 4  incomplete and non-professional renovations  non-compliant and non-approved building works  non-compliant electrical wiring  building materials stored on site for an extended period of time that had vegetation growing through them. Significantly, IT was of the view that the quotation provided by t he applicant’s builder, grossly overstated the rectification works required to repair the storm damage to the residence. Further, the applicant’s builder’s quote does not separate storm damage from the maintenance issues or pre-existing building defects that required rectification; furthermore the quote is not reflective of an objective view of the necessary repairs to the home as a result of the significant weather event. On the other hand, IT did concede that there may be some degree of additional damage to the front area of the house but IT did not consider that this would grossly alter the detail contained within its scope of works, as previously provided. Having reviewed all of the exchanged material, the panel is satisfied that the scope of works provided by IT is an accurate assessment of the repairs required at the property as a result of the significant weather event on or about 16 December 2015. The panel is satisfied that the FSP’s final offer of $162,152.05 is inclusive of a number of unrevealed issues which may need to be added to the work to be done, including mould remediation. The result is that the panel is satisfied that the FSP is entitled to rely upon this scope of works to establish its obligation in respect to repairs, arising solely from the significant weather event, under the terms and conditions of the policy. However, whilst the panel accepts that the FSP has a discretion under the terms of the policy to cash settle the repairs to the property, rather than carry out the repairs, the FSP must exercise this discretion fairly. In determining whether to exercise the discretion to cash settle the claim, the FSP must take into account all reasonable factors, including the nature of the repairs required and whether a cash settlement adequately ensures the applicant is able to properly complete all repairs. Significantly, by cash settling for the repairs, the FSP transfers the risks associated with repairs and unidentified areas of damage, from itself to the applicant. In those circumstances, the panel is satisfied that it is fair in all the circumstances that there be an allowance on top of IT’s quoted scope of works, that covers the transfer of this risk. The result is that upon acceptance of this determination by the applicant, the FSP is to pay the applicant the total amount of $195,000 representing the cost of repairs to the home. The amount of $195,000 includes the FSP’s cash settlement offer of $162,152.05. Payment of this amount will finalise the FSP’s obligations to the applicant in respect of repairs to the home as a result of the significant weather event. Case No: 464408 Determination Page 4 of 4 Given the amount to be paid includes an allowance for the transfer of risk, the panel is satisfied that the FSP is not required to pay additional amounts for either interest or non-financial loss compensation. Temporary accommodation The FSP has confirmed that it has made payments to the applicant in respect of temporary accommodation, based upon accommodation found by the applicant and representing the policy limit of 52 weeks. Further, in making allowance for the risk assumed by the applicant as a result of the cash settlement by the FSP, the panel has also included an amount, within the quantum of $195,000, for temporary accommodation during the period of repair. Having reviewed all of the exchanged material and in light of the risk transference allowance being made by the panel, the FSP is not required to make any further payment with regard to temporary accommodation.