Determination 464408
Cash settlement amount for storm damage repairs
Summary
The applicant's home was damaged in a storm and the insurer offered $162,152.05 cash settlement for repairs, while the applicant's builder quoted a much higher figure. AFCA accepted the insurer's scope of works but required a $195,000 cash settlement that includes an allowance for transferred repair risk.
An insurer exercising its cash settlement discretion must do so fairly, including an allowance for the risk it transfers to the insured.
Issues
- Claim amount dispute primary · upheld
“the FSP is to pay the applicant the total amount of $195,000 representing the cost of repairs to the home”
- Repairs or contractors secondary · not upheld
“the panel is satisfied that the scope of works provided by IT is an accurate assessment of the repairs required”
Subjects and remedies
home or building damagenatural disasterpay claim
Text of the determination
Determination
Case No: 464408 Determination Page 1 of 4
Case number: 464408 11 September 2017
1 Overview
1.1 Dispute
This matter involves a claim by the applicant under her Home Insurance Policy, held
with the financial service provider (FSP), following damage to the home.
Whilst the FSP has accepted the applicant’s claim, a dispute continues as to the
extent of the FSP’s obligations under the terms and conditions of the policy.
1.2 Issues and key findings
What is the extent of the FSP’s obligations under the terms and conditions of
the policy?
Upon acceptance of this determination by the applicant, the FSP is to pay the
applicant the total amount of $195,000 to meet its obligations in respect of repairs to
the home under the terms and conditions of the policy.
1.3 Determination
This determination is partially in favour of the applicant.
Upon acceptance of the determination by the applicant, the FSP is to pay the
applicant the total amount of $195,000 in settlement of the applicant’s claim in
respect of repairs under the terms and conditions of the policy.
The amount of $195,000 includes the previous cash settlement offer of $162,152.05.
The FSP is not required to pay interest on this amount.
The FSP is not required to pay non-financial loss compensation.
The FSP has met its obligations under the policy in respect to temporary
accommodation and is not required to make any further payment with regard to
temporary accommodation.
Case No: 464408 Determination Page 2 of 4
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the material exchanged.
This determination follows consideration of all of the information exchanged and is
based on what is fair in the circumstances, having regard to the relevant legal
principles, terms of the policy, good industry practice and where applicable, prior
determinations.
This determination is made by a panel consisting of the Panel Chair Ombudsman
together with a representative with extensive experience in the insurance industry
and a representative with extensive experience in consumer claims.
2.1 What is the extent of the FSP’s obligations under the terms and
conditions of the policy?
Circumstances of the loss
There is no dispute that the applicant’s home and contents suffered damage in a
significant weather event on or about 16 December 2015.
The FSP accepted the applicant’s claim for contents and has made payment under
the policy provisions.
The FSP also accepted t he applicant’s claim in respect to damage to the home and
has made a cash settlement offer in the amount of $162,152.05 for repairs to the
building.
The offer from the FSP is based upon a report from a building consultant (IT) and a
scope of works also prepared by the building consultant.
The applicant has provided a report from a builder which refers to a much higher
settlement figure in respect of the repairs to the home.
However, IT identified a number of issues with the home, unrelated to the significant
weather event which caused damage to the home.
The scope of works provided by IT relates to the damage to the home as a result of
the significant weather event.
The applicant’s builder’s scope of works and quotation for a significantly greater
amount, does not confine itself to the weather related damage but provides for
coverage of all remediation issues at the home.
In response to the report and scope of works from the applicant’s builder, IT provided
an additional response.
IT confirmed that they inspected the property on three occasions, 21 December
2015, 27 January 2016 and 30 April 2016, over which time they took some 190
photographs.
IT identified a number of issues with the property, including:
deterioration
Case No: 464408 Determination Page 3 of 4
incomplete and non-professional renovations
non-compliant and non-approved building works
non-compliant electrical wiring
building materials stored on site for an extended period of time that had
vegetation growing through them.
Significantly, IT was of the view that the quotation provided by t he applicant’s builder,
grossly overstated the rectification works required to repair the storm damage to the
residence. Further, the applicant’s builder’s quote does not separate storm damage
from the maintenance issues or pre-existing building defects that required
rectification; furthermore the quote is not reflective of an objective view of the
necessary repairs to the home as a result of the significant weather event.
On the other hand, IT did concede that there may be some degree of additional
damage to the front area of the house but IT did not consider that this would grossly
alter the detail contained within its scope of works, as previously provided.
Having reviewed all of the exchanged material, the panel is satisfied that the scope of
works provided by IT is an accurate assessment of the repairs required at the
property as a result of the significant weather event on or about 16 December 2015.
The panel is satisfied that the FSP’s final offer of $162,152.05 is inclusive of a
number of unrevealed issues which may need to be added to the work to be done,
including mould remediation.
The result is that the panel is satisfied that the FSP is entitled to rely upon this scope
of works to establish its obligation in respect to repairs, arising solely from the
significant weather event, under the terms and conditions of the policy.
However, whilst the panel accepts that the FSP has a discretion under the terms of
the policy to cash settle the repairs to the property, rather than carry out the repairs,
the FSP must exercise this discretion fairly.
In determining whether to exercise the discretion to cash settle the claim, the FSP
must take into account all reasonable factors, including the nature of the repairs
required and whether a cash settlement adequately ensures the applicant is able to
properly complete all repairs.
Significantly, by cash settling for the repairs, the FSP transfers the risks associated
with repairs and unidentified areas of damage, from itself to the applicant.
In those circumstances, the panel is satisfied that it is fair in all the circumstances
that there be an allowance on top of IT’s quoted scope of works, that covers the
transfer of this risk.
The result is that upon acceptance of this determination by the applicant, the FSP is
to pay the applicant the total amount of $195,000 representing the cost of repairs to
the home.
The amount of $195,000 includes the FSP’s cash settlement offer of $162,152.05.
Payment of this amount will finalise the FSP’s obligations to the applicant in respect
of repairs to the home as a result of the significant weather event.
Case No: 464408 Determination Page 4 of 4
Given the amount to be paid includes an allowance for the transfer of risk, the panel
is satisfied that the FSP is not required to pay additional amounts for either interest or
non-financial loss compensation.
Temporary accommodation
The FSP has confirmed that it has made payments to the applicant in respect of
temporary accommodation, based upon accommodation found by the applicant and
representing the policy limit of 52 weeks.
Further, in making allowance for the risk assumed by the applicant as a result of the
cash settlement by the FSP, the panel has also included an amount, within the
quantum of $195,000, for temporary accommodation during the period of repair.
Having reviewed all of the exchanged material and in light of the risk transference
allowance being made by the panel, the FSP is not required to make any further
payment with regard to temporary accommodation.