Home / Financial Firm (Unknown - Insurer) / Determination 464366
Determination 464366
Scope of water damage repairs and delays in claim handling
Summary
The applicant sought replacement of her kitchen benchtop and cabinets after water damage and complained about claim handling. AFCA ordered the claim-related repairs and temporary accommodation to continue, rejected replacing the benchtop and cabinets, and ordered $3,000 for non-financial loss.
Expert evidence showed the cabinets could be reinstated and the benchtop damage was not claim-related, but the FSP's unreasonable delays warranted the maximum non-financial loss award.
Issues
- Repairs or contractors primary · not upheld
“The available evidence does not show the benchtop and cabinets need to be replaced.”
- Poor claim handling secondary · upheld
“I accept the claim has been unreasonably handled”
- Delay secondary · upheld
“mould remediation works did not appear to begin until 2 May 2016”
Subjects and remedies
home or building damagepay claimpay non financial lossrepair or rectify
Text of the determination
Determination
Case No: 464366 Determination Page 1 of 3
Case number: 464366 21 December 2017
1 Overview
1.1 Dispute
The financial services provider (FSP) accepted the applicant’s claim for water
damage and authorised repairs.
The applicant complained about the FSP’s handling of the claim and is seeking
compensation. The applicant also disputes the extent of outstanding repairs. The
applicant says the kitchen benchtop and cabinets should be replaced.
The FSP, whilst now agreeing to repair the damage, does not accept this extends to
replacing the cabinets or benchtop. The FSP offered $1,000 in compensation for the
applicant’s claim experience. The applicant has rejected this.
1.1 Issues and key findings
Should the FSP replace the benchtop and cabinets?
The available evidence does not show the benchtop and cabinets need to be
replaced.
Should the FSP pay compensation?
The FSP should pay $3,000 in non-financial loss due to the unreasonable handling of
the claim.
1.2 Determination
This determination is partially in favour of the applicant.
The FSP is required to repair the claim related damage and pay for the applicant’s
temporary accommodation until this is complete. These works do not include
replacing the benchtop or cabinets.
These repairs are to begin within 14 days of the FSP receiving notification that the
applicant accepts this Determination.
The FSP is also to pay $3,000 in non-financial loss.
Case No: 464366 Determination Page 2 of 3
2 Reasons for determination
2.1 Should the FSP replace the benchtops and cabinets?
Evidence does not show benchtop and cabinets need to be replaced
These relevant facts are not in dispute:
the FSP did elect to repair the damage and began this course of action
the applicant and her husband have been in temporary accommodation for a
long period of time
repairs stopped, following which the parties considered a cash settlement
outcome – the parties could not agree to an amount
the FSP has now agreed to complete the claim related repairs
The applicant says the benchtop was damaged as part of the claim . She has
provided photographs of the benchtop in question to support her position.
It is not apparent from the photographs that the benchtop is damaged. Further, there
was no reference throughout the claim that the benchtop was damaged from either
the cl aimed event or the repairs undertaken. Instead, the FSP’s claim notes say the
benchtop was to be replaced as part of private works being sought by the applicant.
The applicant is also seeking for the cabinets to be replaced. However, the available
expert evidence shows they can be reinstated and do not need to be replaced. There
is also no expert evidence saying the cabinets cannot be reinstated.
Given all this, I do not accept the evidence shows the FSP is liable to replace the
benchtop or cabinets as part of the claim related repairs.
FSP is to complete the claim related repairs
The FSP is required to continue with the claim related repairs. This does not extend
to replacing the benchtop or cabinets.
Further, the FSP is to repair the claim related damages as soon as practicable to
ensure the property is restored as close as possible to the pre-incident condition. The
FSP is also to continue paying temporary accommodation until the works have been
completed. This is not subject to the policy limit given, for reasons to follow, I accept
the claim has been unreasonably delayed.
2.2 Should the FSP pay compensation?
FSP should pay $3,000 in non-financial loss
FOS can award up to $3,000 for non-financial loss if the FSP caused the applicant to
suffer an unusual degree or extent of inconvenience, delay or interference.
I accept the claim has been unreasonably handled given the following:
mould remediation works did not appear to begin until 2 May 2016 – this was
almost five months after the claim was lodged
Case No: 464366 Determination Page 3 of 3
whilst the FSP said these works would take seven days, they were not
completed until about two months later
the FSP took almost three months to clean the mould on the cabinet doors after
the applicant raised a concern about their use
the FSP sought to cash settle the claim when a dispute arose about the
benchtop – this was about one year after the claim was lodged and repairs had
started
the applicant has been housed in temporary accommodation that is not of a
comparable size to her home
These delays and experiences are significant. It has contributed to the applicant’s
claim related damage remaining unrepaired almost two years after the claim was
lodged. I accept this would have substantively interfered with the applicant’s peace of
mind.
Given this, the maximum amount of $3,000 for non-financial loss should be awarded.
Applicant has not shown a financial loss due to claims experience
The applicant has also sought compensation for being housed in a small bedroom
hotel, driving to her home to pick up her mail and utility costs at the temporary
accommodation.
There is no evidence these inconveniences resulted in financial losses. For instance
regarding the utility costs, the applicant would have incurred these had she occupied
her home during this period. There is no evidence to show she incurred a financial
cost regarding the temporary accommodation or picking up the mail.
Accordingly, these factors were taken into consideration when awarding the
maximum amount of non-financial loss.