Storm damage to boat shed and boat slip declined under actions of the sea exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2018-02-14
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The FSP declined the applicant's claim for storm damage to her boat shed and boat slip as caused by excluded actions of the sea. AFCA found the storm was the dominant cause, ordered the FSP to meet the storm repair claim on policy terms, and ordered statutory interest, excluding pre-existing timber decay.

Under the proximate cause test the dominant cause was the storm and its surge, which is covered, so the actions of the sea exclusion did not apply.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 464190 Determination Page 1 of 6 Case number: 464190 25 January 2018 1 Overview 1.1 Dispute The applicant is represented by her broker in this dispute. For the sake of brevity, the applicant and her broker will be referred to as the applicant in this determination. The applicant holds a home building and contents insurance policy with the financial services provider (FSP). The applicant lodged a claim with the FSP for damage sustained to the boat shed and boat slip as result of a storm. The FSP declined the claim on the basis the damage was caused by actions of the sea which is excluded under the policy. 1.2 Issues and key findings Is the FSP entitled to decline the claim? The available information shows the FSP is not entitled to decline the claim because:  the actions of the sea were caused by severe storms  storm is covered under the policy. 1.3 Determination This determination is in favour of the applicant. The FSP is to meet the applicant’s claim for the storm damage repairs under the terms and conditions of the policy. The FSP is required to pay interest, in accordance with the Insurance Contracts Act 1984 (the Act) from the date the applicant paid the repair cost to the date of settlement. Case No: 464190 Determination Page 2 of 6 2 Reasons for determination I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied the documentation I have relied on has been provided to both parties. 2.1 Is the FSP entitled to decline the claim? Applicant is required to establish a valid claim under the policy It is accepted insurance law that the applicant has the onus to establish the loss arose from an event covered under the policy. This is known as a prima facie claim. If the applicant is able to do so, the onus shifts to the FSP to show the policy does not respond to the loss. The policy provides cover for accidental damage. The term ‘accidental’ is not defined within the policy. However, the courts have defined ‘accidental’ in an insurance context as something that is ‘unintended and unexpected’ . The applicant submits the storm caused the damage. There is no dispute there was a storm. On this basis, I am satisfied the applicant has established a prima facie claim. Information provided by engineer supports storm as the cause of the damage The FSP appointed structural engineer (E) to inspect the property and provide a report. E concluded the damage to the boat shed and boat slip was caused by unprecedented ocean swell activity. However, it is noted E reported severe storms contributed to the unprecedented ocean swell activity. E stated large swell activity, with waves of up to six metres, was observed during the period of Monday 6 June 2016 to Wednesday 8 June 2016 in the vicinity of G Island, which is approximately 40km away from the site. E commented the swell activity had the energy to cause large scale damage and erosion to coastlines and structures located within tidal and shore lines. E further noted the large swell activity was broug ht on by a storm front which crossed the state, and which resulted in flooding to parts of Tasmania. E concluded the swell activity is the likely cause of the damage to the boat slip and boat shed. While it is noted E advised there was unprecedented ocea n activity, E confirmed the storm resulted in the unprecedented ocean swell activity. On this basis, I accept the unprecedented ocean activity was caused by the storm. Hydrologist confirmed the storm as a contributing factor to the damage The FSP appointed hydrologists (H) to provide a report as to the cause of damage. H concluded the damage was due to prolonged wave action from the sea. However, H further noted the severe storm contributed to the wave action. Case No: 464190 Determination Page 3 of 6 H noted up to 100mm of rain was recorded across parts of northern Tasmania in June 2016. On Monday 6 June 2016, up to 300mm of rain was recorded. H commented the storm wave heights exceeding 5m (significant) developed over a distance of approximately 2000km, producing waves with a north easterly direction. Similarly to the findings of E, I note H concluded the damage was caused by wa ve action. However, H confirmed the storm contributed to the prolonged wave actions and noted:  The storm wave heights exceeding 5m (significant) developed over a fetch of approximately 2000km, producing waves with a north easterly direction.  The June 2016 east coast low system in the Tasman Sea generated extreme ocean water level and wave conditions in the Tasman Sea and in particular along the north-east coast of Tasmania.  The concurrent water level and wave conditions developed on Monday 6 June and persisted over Tuesday 7 June and Wednesday 8 June. Water levels elevated as a result of storm surge process, including the effect of lower atmospheric pressure (inverse barometric effect) and intense wind from offshore storm (wind setter).  The mean sea level pressure at the nearby aerodrome dropped from 1025.2 at 9am Saturday 4 June 2016 to a low of 990.8 at 3pm Tuesday 7 June 2016.  Storm surges can interact with ocean processes, such as tides and waves, to further increase coastal sea levels and flooding. Significant wave heights exceeding 7m were predicted along the north-east Tasmanian coastline on Monday 6 June at 22:00.  Spring tide conditions plus persistent storm surge resulted in extremely elevated ocean water levels occurring nightly from Monday 6 June to Wednesday 8 June.  Storm wave conditions persisted on Tuesday/Wednesday and coincided with extremely elevated water levels, particularly during the evening high tides.  The observed damage to the boat shed and ramp is consistent with this wave action.  The opinion of H that ‘the damage to boat shed and ramp at the insured’s site…was due to prolonged wave action from the sea’ . Information shows the proximate cause of the damage is storm The FSP submits the cause of the damage is the actions of the sea. As actions of sea are excluded under the policy, the FSP declined the claim. The applicant submits the damage was caused by the severe storm. As there is conflicting opinions as to the proximate cause, it is necessary to determine the proximate cause of the damage. The proximate cause of the loss is the dominant or effective or operative cause of the loss, whether or not that be the last in time or the sole cause. This means that even if the actions of sea was the last event to cause the damage to the boat shed and boat slip, this does not mean it is necessarily the proximate cause of the loss. To determine the dominant cause, each cause (be it storm or actions of the sea) must be examined for the qualities of reality, predominance and efficiency as the active, efficient cause. If one cause (such as actions of the sea or storm) would have Case No: 464190 Determination Page 4 of 6 caused the harm in any case, and the other would not have done so in the absence of the first, the first is the proximate cause. It is noted in the reports of the E and H that severe storms contributed to the unprecedented ocean swells and prolonged wave actions. Therefore, I am satisfied, on the balance of probabilities, the proximate cause of the loss was the storm. I am not satisfied the damage to the property would have occurred, if not for the storm which caused the actions of the sea. As the policy provides cover for storm, the FSP is not entitled to decline the claim. The FSP considered the principles of Wayne Tank & Pump Co Ltd v Employers Liability Assurance Corporation Ltd [1974] 1 QB 57 ( ‘ Wayne Tank ’ ) applying that being when two or more proximate causes give rise to a claim, one of which is excluded, the member was entitled to apply the exclusio n, and therefore had no liability for the applicant’s loss. On the balance, the FSP says the damage was caused by ‘…the action of the sea, high water…’ T he FSP further says that ‘any of the damage that was caused by the storm is excluded by Wayne Tank ’. I have noted the reference to Wayne Tank and the approach taken by the FSP, however courts in considering proximate cause had clearly stated that a proximate cause is not the first, or the last or the sole cause of the loss, it is the effective o r dominant or operative cause ( State Government Insurance Commission v Sinfein Pty Ltd ) [1996] 15 WAR 434 and ( Laser Max Engineering Pty Ltd v QBE Insurance Australia Limited) [2005] 13 ANZ insurance cases (205) NSWCA 66. The storm was the dominant cause of the chain of events. The sea and/or high water on its own is unlikely to have caused the damage to the boat shed and boat slip. It was the extreme storm event and storm surge that was the dominant or operative cause in this instance that resulted in the storm surge and high water. I note that there is not an exclusion for storm surge under the policy. FSP liability only extends to the damage as a result of the storm It is noted in E’s report some of the damage to the boat shed was pre -existing. The damage E states is pre-existing is to the floor structure, wall and roof framing. E observed decay in the timbers in these areas. Therefore, the FSP is not liable for the reimbursement of repairs completed to these areas, as the damage is not a result of the storm. The applicant is required to provide the FSP with a copy of the invoice and itemised scope of works completed on the repaired boat shed and boat slip within 21 days of acceptance of this determination. The FSP is entitled to assess the scope of works and provide settlement for the storm related works completed, within 14 days of receiving the invoice and itemised scope of works. The FSP is entitled to deduct any applicable excess from the settlement amount. The FSP should pay interest on the settlement at the statutory rate from the date the applicant paid the invoice until the date of payment. Case No: 464190 Determination Page 5 of 6 3 Supporting information What you are insured again, and what you are not You are insured against, accidental loss or damage (including the Specified Events listed below) t o your buildings, contents belonging to you, your family or for which you are they are legally responsible or bot h at the situation during the period of insurance. Specified events ….. q) storm, flood, tempest, rainwater, wind, hail, tornado, cyclone or hurricane, freeze or weight of snow ….. General exclusions The following General exclusions apply to all sections of this policy …. the action of sea, high water, tidal wave …. 3.1 Reports Record Key points FSP’s expert (E ) Report 01 - 07 - 2016  L arge swell activity, with waves of up to six metres, was observed during the period of Monday 6 June to Wednesday 8 June 2016 in the vicinity of G Island, which is approximately 40km away from the site.  This swell activity had the energy to cause large s cale damage and erosion to coastlines and structures located within tidal and shore lines.  Unprecedented ocean swell activity was likely the cause of structural damage to the boat slip and cosmetic damage to the boat shed.  The large swell activity was b rought on by a storm front which crossed the state, and which resulted in flooding to parts of Tasmania.  The swell activity was reported as being extra - large and that it had been described as the largest swell activity experienced in decades. FSP’s expert ( H ) Report 07 - 07 - 2016  In the 24 hours to 9am on Sunday 5 June 2016, up to 100mm of rain was recorded across parts of northern Tasmania.  In the subsequent 24 hours to 9am on Monday 6 June 2016, parts of Northern Tasmania recorde d up to 300mm.  The wave system continued to develop on Sunday 5 June Case No: 464190 Determination Page 6 of 6 2016 the trough moved offshore into the Tasman Sea.  S torm wave heights exceeding 5m (significant) developed over a fetch of approximately 2000km, producing waves with a nort h easterly direction.  A stor m surge residual developed from Saturday 4 June 2016 and peaked at approximately 0.4 metres on Tuesday 7 June 2016 .