Determination 463950

Storm damage rectification cost and apportionment

FirmFinancial Firm (Unknown - Insurer)
Decided2018-02-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$50,215
Non-financial loss$1,500
Amount claimed—
SourceAFCA PDF

Summary

After a storm damaged the applicants' home, the insurer disputed the rectification cost and the apportionment for pre-existing damage. AFCA ordered payment of $50,215 with interest and $1,500 non-financial loss compensation.

The policy requires reinstatement to substantially the 'when new' condition, and the applicants' specialist quotation best reflects the reasonable cost of that work.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 463950 Determination Page 1 of 4 Case number: 463950 16 February 2018 1 Overview 1.1 Dispute This matter involves a claim by the applicants under a Home Insurance Policy, held with the financial services provider (FSP), following damage to the insured property in a storm. The FSP has accepted the applicants ’ claim and made payments, but a dispute continues as to the full extent of the FSP’s o bligations to the applicants under the terms and conditions of the policy. 1.2 Issues and key findings What is the extent of the FSP’s obligations to the applicant s under the terms and conditions of the policy? The FSP is required to pay the additional amount of $50,215, to meet its obligations under the terms and conditions of the policy. 1.3 Determination This determination is in favour of the applicants. The FSP upon acceptance of the determination by the applicants, is required to pay the applicants the additional amount of $50,215, to finalise its obligations under the terms and conditions of the policy. The FSP is required to pay interest on this amount, in accordance with the Insurance Contracts Act 1984 (the Act), from 15 June 2017, until the date the payment is made. The FSP is required to pay the applicants an additional amount for non-financial loss compensation of $1,500, if it has not already done so. Case No: 463950 Determination Page 2 of 4 2 Reasons for determination This dispute has been the subject of a recommendation issued by the Service on 31 July 2017. It was the Case Manager’s recommendation that the FSP was required to pay the applicants the additional amount of $50,215, plus $1,500 for non-financial loss compensation. The FSP rejected the recommendation insofar as it related to the payment of $50,215, but accepted the recommendation insofar as it related to the non-financial loss compensation of $1,500. Both parties have provided further submissions in respect to this matter, subsequent to the recommendation. I have carefully considered all of the material provided both before and after the recommendation in the preparation of this determination. Whilst all of the information exchanged has been considered, only that information relevant to the final outcome will be referred to in this determination. This determination follows consideration of all of the information exchanged and is based on what is fair in the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice and where applicable, prior determinations. 2.1 What is the extent of the FSP’s obligations under the terms and conditions of the policy? Coverage of the policy The coverage provided by the applicants ’ Home Insurance Policy, is detailed within the Product Disclosure Statement (PDS). The PDS details: . . . Case No: 463950 Determination Page 3 of 4 Given what follows within this determination, I am satisfied that the use of the words ‘…when new…’ in sub paragraphs b. and c. of paragraph 1, above, is significant. Circumstances of the claim and dispute As stated, the applicants ’ home suffered damage in a storm and the FSP accepted the claim. However, a dispute continues as to the extent of the FSP’s obligations under the terms and conditions of the policy. The FSP has made payment in respect to a number of items but a dispute continues as to the rectification work required as a result of replacement of the pool. I agree with the Case Manager’s recommendation to the effect that the policy provision above requires the FSP to reinstate the property to substantially the same condition it was in ‘when new’ and not to the condition it may have been in immediately before the storm event that caused the damage. The FSP says that there was pre-existing damage and maintenance issues which should not be included as part of the rectification works. Further, the FSP says that its representative inspected the property on 8 March 2017 and provided a report which broke down the items in dispute and quantified the proportions which ought to be covered by the policy. The FSP says that the report specified the percentage to which the policy responds and the percentage to which the policy does not respond (due to pre -existing damage and maintenance issues) in respect to the rectification works. Significantly, the FSP says that the applicants agreed to the proposed apportionment and agreed to assess the claim on the basis of the FSP’s representative’s calculations. The applicants say that at no stage did they agree to the apportionment and that they raised their concerns r egarding the FSP’s representative’s report immediately it was received. Having reviewed all of the exchanged material, I am not satisfied that the FSP has established that the applicants did agree to the apportionment and the applicants have not bound themselves to the calculations made by the FSP’s represen tative. I have reviewed the material presented by the FSP and I agree with the Case Manager that the quotations provided do not appear to take into account a number of items relevant to the claim. Further, I agree with the Case Manager to the effect that the additional quotations provided by the applicants do adequately reflect the Scope of Works and the reasonable cost to restore the applicants ’ property to a condition substantially the same as ‘when new’. As a result, I prefer the quotations provided by the applicants. The applicants provided a quotation from a specialist (UE) in the amount of $45,650. Case No: 463950 Determination Page 4 of 4 The quotation does not include GST and when GST is added, this totals an amount of $50,215. This quotation is for a lower amount than the other quotation and it is fair that any resolution be based on this quotation. The quotation from UE is dated 8 June 2017 and lists an expiry date of 15 June 2017. Given the quotation is out of date, I consider it fair in all the circumstances that the FSP be required to pay interest, in accordance with the Act, on the amount of $50,215, from 15 June 2017, until the date the payment is made. In addition, noting that the FSP agreed to pay the applicants non-financial loss compensation, the FSP should pay the applicants $1,500, if it has not already done so.