Text of the determination
Determination
Case No: 463688 Determination Page 1 of 5
Case number: 463688 19 September 2017
1 Overview
1.1 Dispute
The Applicants (Mr and Mrs P) had a loan with the financial services provider (FSP),
secured by a mortgage over their property. The loan was paid out, but the Applicants
lost the original certificate of title to the property. In 2016, the Applicants decided to
sell the property, and so needed to obtain a replacement certificate of title without the
FSP’s security showing as an encumbra nce.
The Applicants say that:
In September 2016, they went to a FSP branch to request a Discharge of
Mortgage (Discharge). They were told by FSP staff that they did not need to fill
out a form, because a Discharge had already been completed
They found out that a Discharge had not been completed and
The conveyancer therefore requested the FSP provide a Discharge on 16
November 2016, but due to FSP delays it was not provided until 12 December
2016.
The Applicants say they incurred losses totalling $67,182.09 because of the
misrepresentation and delays caused by the FSP in providing the Discharge.
The Case Manager provided the parties with a recommendation dated 21 June 2017
on the issues in dispute. The recommendation was partially in favour of the
Applicants. The Applicants rejected the recommendation. A copy of the
recommendation is attached to this determination.
1.2 Issues and key findings
Were the findings of the recommendation correct?
The findings contained in the recommendation were correct and are adopted in this
determination. Further submissions provided after the recommendation have been
considered.
Do the Applicants ’ further submissions change the outcome?
The further submissions do not change the outcome as it has not been established
that the Applicants were misled in September 2016. In addition, e ven if FOS was
satisfied that the Applicants were given the wrong information at a FSP branch on 29
September 2016, the information does not support a finding that the FSP should
have provided the Discharge earlier than 29 November 2016. Finally, the Applicants
did not provide any submissions to establish the loss claimed.
Case No: 463688 Determination Page 2 of 5
Based on all the available information the recommendation ’s non -financial loss award
was appropriate.
1.3 Determination
This determination is partially in favour of the Applicants.
If the Applicants accept this determination, then within seven days of the FSP being
notified of the acceptance, the FSP should pay the Applicants $1,000 non-financial
loss compensation to an account they nominate.
Case No: 463688 Determination Page 3 of 5
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
The recommendation was accurate
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties.
I am satisfied that the case manager’s recommendation contains an accurate
summary of the dispute, the issues to be determined, any applicable paragraphs of
the Terms of Reference and any relevant law.
Further submissions provided by the Applicants in response to the recommendation
have been considered below.
2.2 Do the Applicants ’ further submissions change the outcome?
The Applicants’ submissions about the September 2016 branch visit do not
change the outcome
In the recommendation, the Case Manager concluded the following in relation to the
claims:
The weight of information did not support a finding that the Applicants attended
a FSP branch in September 2016 or that they were misled that they did not
need to fill out a discharge form
Nevertheless, the Applicants’ conveyancer’s request to the FSP for a discharge
by email dated 16 November 2016, should have been actioned by around 29
November 2016. Therefore the FSP unreasonably delayed providing the
Discharge
The Applicants had not demonstrated they incurred a financial loss as a result
of the delay.
In response to the recommendation, the Applicants provided further information they
say supports their claim that they went to a FSP branch in September 2016 and were
misled about completing a discharge of mortgage. I do not consider that these
submiss ions assist the Applicants’ claim .
For the reasons set out in the recommendation, I am not satisfied that the Applicants
have established they were misled by the FSP on 29 September 2016.
The Applicants say that after they went to the branch on 29 September 2016, they
told their conveyancer (on the basis of what they were told by the FSP) that the
mortgage had already been discharged and “… that everything would be ready for
when we requested a new replacement title…in order to sell the property”. Th e
conveyancer did not write to the FSP to request a discharge until 16 November 2016.
Case No: 463688 Determination Page 4 of 5
Despite what they say they were told on 29 September 2016, the Applicants did not
seek a new replacement title or to sell the property until November 2016 in any
event. Even if I was satisfied that the misrepresentation occurred on 29 September
2016, it does not appear that this contributed to any further delay in the sale or
settlement of the property.
Based on the available information, there is no basis for saying that the FSP ought to
have provided the Discharge earlier than 29 November 2016.
The Applicants did not provide any information supporting the claims for loss
The recommendation specified the information that had not been provided by the
Applicants to demonstrate how the timing of the sale of the property would have been
any different if the Discharge had been provided earlier. This included:
A copy of any contract of sale for the Applicants’ property to show that a specific
sale or settlement date was missed or deferred because of any delay, or any
penalty imposed, especially in the light of the fact the sale of the property did
not settle until April 2017
Any information to document that the Applicants had a buyer that was ready to
exchange contracts or settle the sale of the property upon earlier receipt of the
Discharge
An explanation as to when the Applicants requested and obtained a
replacement title from the land titles office after they received the Discharge,
especially in the light of information showing the Applicants had not obtained a
replacement title by 24 January 2017.
In responding to the recommendation, the Applicants did not make any further
submissions in response to the delay or losses claimed. Specifically, the Case
Manager found that over the course of the dispute the Applicants had not
demonstrated how their claimed losses (of which there are many) would have been
avoided if the FSP provided the Discharge earlier than 12 December 2016.
The Applicants had claimed significant losses associated with vacating a business
premises not related to the Discharge. However, it has not been established that
those losses were reasonably foreseeable by the FSP in November or December
2016, even if the FSP had delayed settlement. Accordingly those losses would be too
remote to form part of a claim for loss in relation to the FSP’s actions.
FOS’s processes require Applicants to provide information to establish and support
their claims for loss. Based on all the available information, I agree with the findings
in the recommendation that the Applicants have not established their claim for
financial loss. In the absence of any new information from the Applicants in response
to the recommendation, there is no basis on which to award financial loss
compensation.
Non-financial loss award was appropriate
In the recommendation, the Case Manager found it was appropriate that the FSP
compensate the Applicants $1,000 for the stress and inconvenience they would have
experienced while waiting the extra couple of weeks for the FSP to provide the
Discharge.
Case No: 463688 Determination Page 5 of 5
I agree with the reasoning in this regard in the recommendation, and note that the
FSP did not provide any submissions in rejection of this finding.
The FSP should pay the Applicants $1,000 compensation to account for the non-
financial losses they incurred because of the unreasonable delay by the FSP in
providing the Discharge after 16 November 2016.
Recommendation
Case No: 463688 Recommendation Page 1 of 4
Case number: 463688 21 June 2017
3 Overview
3.1 Dispute
The Applicants (Mr and Mrs P) held a loan with the FSP, secured by a mortgage over
their property. The loan was paid out, but the Applicants subsequently lost the
original title to the property. In 2016, the Applicants decided to sell the property, and
so needed to obtain a replacement title. They say that:
In September 2016, they went to an FSP branch to request a Discharge of
Mortgage (Discharge). They were told by FSP s taff that they did not need to fill
out a form, because a Discharge had already been completed.
When the Applicants’ conveyancer applied for a new title, the titles office could
not provide it because no Discharge had been submitted.
The conveyancer requested the FSP provide a Discharge on 16 November
2016, but it was not provided until 12 December 2016.
The Applicants say they incurred losses totalling $67,182.09 because of the delays
caused by the FSP in providing the Discharge.
3.2 Issues and key findings
Did the FSP cause a delay in providing the Discharge?
The available information does not support a finding that the Applicants went to the
FSP branch in September 2016. It therefore cannot be concluded that the FSP
caused a delay between September 2016 and 16 November 2016, when their
conveyancer requested a Discharge. However, in view of the conveyancer’s request
on 16 November 2016, the FSP should have provided the Discharge earlier than it
did on12 December 2016.
Did the FSP’s delay cause the Applicants to suffer loss?
The Applicants have not established that their claimed losses would have been
avoided if the FSP had provided the Discharge before 12 December 2016. The
FSP’s delay would, however, have caused stress and inconvenience. The FSP
should compensate the Applicants $1,000 for the non-financial losses they incurred.
3.3 Recommendation
This recommendation is partially in favour of the Applicants. If the FSP and the
Applicants accept this recommendation, the FSP should pay the Applicants $1,000.
Case No: 463688 Recommendation Page 2 of 4
4 Reasons for recommendation
4.1 Did the FSP cause a delay in providing the Discharge?
Information does not establish that the Applicants requested the Discharge at
the branch
The Applicants say they went to the FSP branch in September 2016 to request the
Discharge. The Applicants say they started filling out the form requesting the
Discharge, but were then told by an FSP branch staff member that the Discharge had
already been completed. The Applicants say they then left the branch under the
assumption that they could obtain a replacement title without the need for a
Discharge. The Applicants say the later delays could have been avoided if they were
given the correct information in September 2016.
When FOS assess disputes, we consider available documents, and then decide what
is most likely to have occurred based on the information provided to us. The weight
of information does not establish, on the balance of probabilities, that the Applicants
first requested the Discharge at the FSP branch in September 2016.
When the Applicants first lodged their dispute with FOS on 8 December 2016, their
visit to the branch was not raised. The branch visit was not raised as an issue with
FOS until 10 January 2017, when it was described in a phone call. If the branch visit
had occurred as described, it was the key starting point in the chronology of the
claimed delay. One would therefore reasonably have expected the Applicants to
have raised the issue of the branch visit as early as possible.
The FSP has provided records of all interactions between the FSP and the
Applicants from August 2016 to January 2017. The records show in-branch and
telephone or internet interactions between the Applicants and the FSP. The notes
record other interactions between the Applicants and the branc h in December 2016,
but the interaction described by the Applicant as occurring in September 2016 is not
recorded. One would expect this interaction to have been recorded in the FSP’s
notes if it occurred. Branch staff would have accessed the Applicant’s b anking history
in order to determine that the Discharge had already been completed, and one would
expect the branch staff’s review of this information to be entered into the FSP’s
system notes.
The Discharge should have been provided earlier
The Applican ts’ conveyancer emailed the FSP on 16 November 2016, requesting the
FSP prepare the Discharge. The parties accept that the Applicant did not receive the
Discharge until 12 December 2016.
The FSP says its standard turnaround time for a Discharge request is ten business
days. The FSP says in the normal course of events, customers also need to
complete a Discharge Authority form before a Discharge can be prepared. The
information on file establishes that the Applicants did not need to complete a new
Discharge Authority in order for the Discharge to be completed.
Case No: 463688 Recommendation Page 3 of 4
In the circumstances, the Applicants should have received the Discharge earlier than
12 December 2016. Given the FSP’s stated standard turnaround time for Discharge
requests, the Applicants should have received the Discharge on or around 29
November 2016.
4.2 Did the FSP’s delay cause the Applicants to suffer loss?
It has not been shown that loss would have been avoided
When it is established than a financial services provider has caused a delay, the
question then becomes what loss could have been avoided if there was no delay.
In response to FOS requests, the Applicants provided information about the loss they
say was caused by the delay in actioning the discharge request. The Applicants’ loss
claim totals $67,182.09, and includes:
bank charges applied to FSP and other financial institution accounts that could
have been paid down sooner if the property sale was settled earlier
legal and rental costs incurred because the Applicants had to extend the lease
over a rental property as a result of delays
other solicitor’s fees
moving costs that would not have been incurred if the property sale settled in
December, because in December the Applicants were able to rely on friends
and family to assist them with the move
lost wages, and non-financial loss.
Although the Applicants have quantified their loss claim with reference to statements
and other invoices, they have not demonstrated how this loss would have been
avoided if the FSP provided the Discharge earlier than 12 December 2016.
No information has been provided to demonstrate the chronology of the sale of the
property, and how that chronology was affected by the FSP’s delay. The Applicants
have not provided a copy of any contract of sale for the property to show that a
specific sale or settlement date was missed because of the delay. The Applicants
have not explained when they obtained the replacement title after they received the
Discharge. The Applicants have also not explained when they lodged their
application with the titles office before and after receiving the Discharge, and the
length of time it took for the titles office to process that request. No information has
been provided to show that the Applicants had a buyer that was ready to exchange
contracts or settle upon receipt of the Discharge.
The information instead indicates that the Applicants had not obtained a replacement
title by 24 January 2017, and that the sale of the property did not settle until April
2017. Although the Applicants are claiming various expenses incurred between
December 2016 and April 2017, it has not been shown that these costs would not
have been incurred if the FSP did not cause the delay.
Case No: 463688 Recommendation Page 4 of 4
The delay caused non-financial loss
The Applicants say the delay in providing the Discharge caused them stress and
inconvenience. There is information on file to support this. FSP system notes record
Mr P spoke to the FSP to express his frustration with the delay as follows:
On 5 December 2016, Mr P expressed his “frustration with the t ime it is taking
for this process”, and was then told he did not need to complete a Discharge
Authority form, even though he received an email the same day advising that he
need to complete a form.
On 8 December 2016, Mr P advised the FSP he was “upset” with the continued
delay.
The Applicants subsequently lodged this dispute with FOS on 8 December 2016
because of the inconvenience being caused.
The FSP should compensate the Applicants for the non-financial loss they incurred
during the period of delay between 29 November 2016 and 12 December 2016. FOS
can award a maximum of $3,000 compensation for non-financial loss, although our
approach to such compensation is conservative. In this dispute, the FSP should pay
$1,000 to the Applicants for non-financial loss incurred because of the delay.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.