Home / Financial Firm (Unknown - Insurer) / Determination 462353

Determination 462353

Shed storm and forklift damage cash settlement and extra building standards costs disputed

FirmFinancial Firm (Unknown - Insurer)
Decided2018-01-31
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant in part
Amount awarded$53,932
Non-financial loss—
Amount claimed$90,000
SourceAFCA PDF

Summary

The applicant rejected the FSP's $53,931.59 cash settlement for shed storm and forklift damage and sought up to $90,000 for a full rebuild to current standards. AFCA found the offer fair and ordered that amount paid.

Reinstatement cover restores only the damaged parts to as-new condition, and extra costs to meet current building standards require Extra Cost of Reinstatement cover, which was not held.

Issues

Subjects and remedies

home or building damagepay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 462353 Determination Page 1 of 7 Case number: 462353 19 December 2017 1 Overview 1.1 Dispute The applicant lodged a claim with the financial services provider (FSP) under a commercial combined business insurance policy following impact damage by a forklift and a storm on 28 May 2014. The FSP accepted liability for the claim and offered to cash settle the claim in the amount of $53,931.59, to cover the repair costs to reinstate the damaged parts of the shed to the same condition when new as provided under the policy. The applicant rejected the cash settlement offer. He believes the FSP should pay full indemnity to replace the shed (up to the sum insured) in accordance with the current Australian building standards. 1.2 Issues and key findings Is the FSP entitled to cash settle the claim? As the applicant purchased reinstatement or replacement value benefit under the policy, the FSP must pay the cost of rebuilding, replacing or repairing the damaged part of the shed on the applicant’s property, to the same condition as if it was new. Since the claim was lodged the applicant has sold the property and seeks a cash settlement. I am satisfied that the FSP can cash settle the applicant’s claim. Is the FSP obliged to reinstate the shed to Australian building standards? I am satisfied that the FSP can refuse to pay for the extra reinstatement costs to rebuild the shed in accordance with current Australian building standards Is the FSP’s offer of settlement fair in the circumstances? The FSP is entitled to rely upon the scope of works in determining the extent of its liability. I am satisfied that the FSP’s offer of $53,931.59 is fair in all the circumstances. 1.3 Determination This determination is in favour of the FSP. The FSP must pay the applicant $53,931.59. Case No: 462353 Determination Page 2 of 7 2 Reasons for determination 2.1 Is the FSP entitled to cash settle the applicant’s claim? The FSP accepts the applicant purchased reinstatement cover The applicant’s policy provides (under Section 1 – Business Property Section) that the FSP has two methods of paying the applicant’s claim. These are:  Reinstatement or replacement value; and  Indemnity value. Under Section 1 – Business Property Cover, the policy provides that the claim payment method that the applicant is covered for is shown on the policy schedule. The FSP has advised that the applicant has purchased ‘reinstatement or replacement value’. Upon reviewing the cover offered under the above claim settlement methods, I am satisfied cover extended for indemnity value is limited when compared to reinstatement or replacement value. The FSP is entitled to cash settle the applicant’s claim As the applicant has purchased reinstatement or replacement value under the policy, the FSP must pay the cost of rebuilding, replacing or repairing the damaged part of the shed on the applicant’s property, to the same condition as if it was new. The FSP confirmed that because the applicant sold the property some time subsequent to the loss event and prior to June 2016, a cash settlement was considered the most appropriate basis of settlement. On this basis, the FSP has offered the applicant $53,931.59 in full and final settlement of the claim. I am satisfied that the FSP’s decision to cash settle the applicant’s claim is consistent with the terms of the policy and fair in all the circumstances. The applicant has rejected the FSP’s cash settlement offer. He considers that the FSP should provide full indemnity (up to the amount of $90,000) to replace the non- compliant shed in accordance with the current Australian building standards. 2.2 Is the FSP obliged to reinstate the shed to Australian building standards? Evidence shows shed does not meet current building standards The FSP relies on an engineering report from C to establish that the a pplicant’s shed was non-compliant with building codes, dilapidated and misaligned prior to the storm and impact of the fork lift. C ’s inspection of the shed noted dilapidation of timber rafters among the various other structural deficiencies and concluded that the shed lacked ‘suitable stability elements in the structure such as portal frames, wall bracing and roof bracing’. In particular C observed that: Case No: 462353 Determination Page 3 of 7  the timber trusses and rafters were older than the remainder of the steel framed structure  original top chord trusses strengthening members had been removed from the trusses  there had been dilapidation of timber rafters and several nails not adequately embedded. C considers that the structure of the shed prior to the storm and forklift damage did not comply with the current Australian building standards. It recommends that the non-compliant shed be removed and replaced with a compliant structure designed by a structural engineer, including provision of engineered footings. The FSP is obligated to repair or replace the damaged parts of the shed to a condition when new. It is not obligated to pay for the additional costs of rebuilding the shed to meet current Australian building standards. Under the Business Property section of the a pplicant’s policy, it states ‘What You are not covered for under this section’ as follows: 1. We will not pay for loss or damage under the Business Property cover section caused by: … d. faulty work i. Error in, omission of or wrong design ii. Faulty materials or faulty workmanship provided that this Exclusion 1(d) shall not apply to subsequent loss or damage to Your Business Property occasioned by a peril (not otherwise excluded) resulting from an event referred to in this Exclusion. There is lack of evidence to show the current damage to the shed was caused by the above factors. The shed most likely withstood several storm events in the past years and the applicant’s claim does not fall under this exclusion which was raised by the FSP. Policy does not provide cover to return shed to a compliant position The applicant’s policy schedule shows that he has not elected to take out Extra Cost of Reinstatement as an insured item under the Business Property section of his policy. Under the clause for Extra Cost of Reinstatement, it states the following: ‘Where ‘Reinstatement or replacement’ basis of settlement is shown in the Policy Schedule, this section extends to include the extra cost of reinstatement (including demolition or dismantling) of damaged property insured necessarily incurred to comply with the requir ements of any Act of Parliament or Regulation…’ The applicant accepts he did not take out Extra Cost of Reinstatement cover. It is not disputed by the parties that effecting repairs to only the damaged parts of the shed, to return it to a condition when new, would result in a shed not meeting current Australian building standards. However subject to the conditions and exclusions of the policy, the FSP will not be liable for any additional expenses required to return it to a compliant position due to the applicant’s failure to take out additional cover for extra reinstatement costs. The applicant has raised concerns that it is unfair to apply modern design knowledge and standards to a shed constructed 40 years ago. He says that the shed has stood Case No: 462353 Determination Page 4 of 7 in the elements for 40 years with no reported issues and on this basis, he is not satisfied that its design can only now be considered faulty and non-compliant with current Australian building standards. I acknowledge and have considered these comments . The fact that remains the construction of the shed, according to current building standards is considered faulty and non-compliant. The shed may have been compliant with current Australian building standards at the time of construction 40 years ago and I agree it should be rebuilt according to current standards. The FSP is however not liable for these additional costs as the applicant did not take out the additional cover as explained above. The applicant is therefore expected to contribute towards such additional costs of reinstatement. 2.3 Is the FSP’s offer of settlement fair in the circumstances? The FSP’s scope of cover is adequate Following the loss, the FSP engaged C to assess the shed and provide an engineering report outlining the loss and providing its recommendations. In this report, C confirmed that the shed did not meet current Australian building standards due to its age and design. It recommended that necessary structural building upgrades be undertaken to ensure its compliance with these standards. C did not provide evidence to show the shed did not meet the design and construction standards expected at the time it was constructed. There is no dispute between the parties that physical loss or damage was caused to some parts of the a pplicant’s shed as a result of the forklift and subsequent windstorm. It is possible the other issues identified by C may have contributed to the damage. The FSP has obtained a scope of work from C and a quotation from L to repair and replace the damaged shed. The quotation obtained from L outlines the specific repairs required to the storm damaged shed and the cost of these repairs. The total quote for the repairs (inclusive of GST) is $52,181.25. I have considered the quote from L in light of the scope of works provided by C and am satisfied that the quote includes all the necessary repair works to the shed. Since receipt of this material, the applicant has not raised any concerns with how repair works to the shed have been assessed. There have been no comparative quotes provided nor any suggestion from the applicant that the $53,931.59 quoted to repair the shed is missing any items or has been wrongly priced. I am satisfied that the scope of works provided and the quotation are fair in the circumstances. Case No: 462353 Determination Page 5 of 7 3 Supporting information 3.1 FOS Approach As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this Determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this Determination, commentary has been restricted to those issues considered directly relevant to the outcome only. 3.2 Policy terms How we will pay Your claim There are two methods of paying Your claims. They are ‘reinstatement or replacement value’ and ‘indemnity value’. The claim payment method You are covered for is shown on the current Policy Schedule. Method of settlement – reinstatement or replacement value We will pay the cost of rebuilding, replacing or repairing any damaged part of Your Business Property to the same condition as when they were new or, where appropriate, in accordanc e with the ‘Output replacement’ clause set out below. …………….. ……………… Extra cost of reinstatement (Applicable to Buildings, machinery and plant). Where ‘Reinstatement or replacement’ basis of settlement is shown in the Policy Schedule, this section extends to include the extra cost of reinstatement (including demolition or dismantling) of damaged property insured necessarily incurred to comply with the requirements of any Act of Parliament or Regulation made under an Act or By law or the Regulation of any Municipal or Statutory Authority, subject to the Case No: 462353 Determination Page 6 of 7 following provisions and subject also to the terms, conditions and sums insured of this section. Provided that: a. ……………... b. ……………… c. ………………. d. the amount recoverable shall not include the additional costs incurred with complying with any such Act, Regulation or By-law or requirement with which You have been required to comply prior to the happening of the damage. What you are not covered for under this section 1. We will not pay for loss or damage under the Business Property cover section caused by: d) Faulty work i. Error in, omission of or wrong design ii. Faulty materials or faulty workmanship Provided that this Exclusion 1(d) shall not apply to subsequent loss or damage to Your Business Property occasioned by a peril (not otherwise excluded) resulting from any event referred to in this Exclusion. 3.3 Expert Reports Record Key points C Engineering Report 04 - 08 - 14  The lack of suitable engineering design has resulted in excessive deflection o f the roof trusses and a lack of stability elements and that accordingly the integrity of the structure is compromised  The removal of truss strengthening elements prior to the storm and impact Events has also cont ribu ted to the lack of structural integrity  It is in their opinion that the primary cause of damage is inadequate structural design and the secondary cause of damage are storm and impact Events in May 2014  It is in their opinion that the impact and storm Ev ents have exacerbated the deterioration of a structure that was non - compliant, dilapidat ed and misaligned prior to the storm and impact Events.  They recommend that the non - compliant work shed structure is removed and replaced with a compliant structure de signed by a suitably qualified structural engineer, including provision of engineered footings CN Second Report  C ha s concluded it is their opinion that the premises were not engineer designed which, according to C , has res ulted in excess Case No: 462353 Determination Page 7 of 7 Commercial - Impact deflection of the roof trusses and a lack of stability elements, which compromises the integrity of the structure of the premises  C is of the opinion that the storm and impact events have exacerbated initial alignments of the roof trusses and loosen ing of the roof’s joint  It is the opinion of C that the primary cause of the damage is inadequate structure design and the second cause of damage the storm and impact events of May 2014

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.