Summary

The applicant company said the FSP pre-approved two property loans, then requested excessive information and delayed settlement, causing penalty interest. AFCA found no pre-approval was given, the information requests were reasonable, and the FSP did not cause the delay.

Conflicting recollections of a phone pre-approval were weighed against contemporaneous documents, which showed no pre-approval and an incomplete application.

Issues

Subjects and remedies

small businessno remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 461288 Determination Page 1 of 2 Case number: 461288 16 June 2017 1 Overview 1.1 Dispute This dispute is about whether the FSP:  misled the Applicant by saying that the loan was pre-approved  made unreasonable requests for information from the Applicant in relation to her Applications  delayed the Settlements. The Case Analyst provided the parties with a Recommendation on the issues in dispute. The Recommendation was in favour of the FSP. A copy of the Recommendation is attached to this Determination. 1.2 Issues and key findings Were the findings of the Recommendation correct? The findings contained in the Recommendation were correct and are adopted in this Determination. The Applicant’s f urther submissions provided after the Recommendation have been considered but do not change the outcome. 1.3 Determination This Determination is in favour of the FSP. I agree with the Case Analyst ’s reasons for the Recommendation and the recommended outcome. Case No: 461288 Determination Page 2 of 2 2 Reasons for Determination 2.1 Were the findings in the Recommendation correct? Background C is the sole director of the Applicant entity. C entered into two contracts to purchase Property G (on behalf of the Applicant entity and/or nominee) and Property F (in her personal capacity and/or as nominee). She says she did so on the basis that she had pre-approval for finance from the FSP in relation to both Properties. The FSP declined the Applicant’s applications for finance in relation to both Properties. The FSP denies ever providing pre -approval for finance to the Applicant in relation to either Property. The Applicant obtained finance from another financial services provider and settlement on the purchase of both Properties has occurred (Settlements). However, both Settlements were delayed and the Applicant was required to pay penalty interest to the vendors in relation to both. The Recommendation was correct I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied the case analyst’s Recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. The Applicant did not provide any new submissions In response to the Recommendation the Appli cant’s representative said:  she had no further evidence to provide. All conversations she had held with the FSP had been verbal and were difficult to substantiate.  the Applicant ultimately obtained a loan from another lender who did not require the same information the FSP required of it. Whilst I appreciate the outcome in the Recommendation was not in the Applicant’s favour, that finding was correct and is not altered by these submissions. The available information does not support a conclusion the FSP pre-approved the Applications. The fact that another lender did not need all of the same information does not make th e FSP’s request for documents was unreasonable. Recommendation Case No: 461288 Recommendation Page 1 of 9 Case number: 461288 4 May 2017 3 Overview 3.1 Dispute C is the sole director of the Applicant entity. C entered into two contracts of sale to purchase Property G (on behalf of the Applicant entity and/or nominee) and Property F (in her personal capacity and/or as nominee). She says she did so on the basis that she had pre-approval for finance from the FSP in relation to both Properties. The FSP declined the Applica nt’s applications for finance in relation to both Properties (Applications). The FSP denies ever providing pre-approval for finance to the Applicant in relation to either Property. The Applicant obtained finance from another financial services provider and settlement on the purchase of both Properties has occurred (Settlements). However, both Settlements were delayed and the Applicant was required to pay penalty interest to the vendors in relation to both. This dispute is about whether the FSP:  misled the Applicant in relation to the Applications  made unreasonable requests for information from the Applicant in relation to her Applications  delayed the Settlements. 3.2 Issues and key findings Did the FSP mislead the Applicant in relation to the Applications? The FSP did not mislead the Applicant in relation to the Applications. There is no information to support the conclusion that it gave pre-approval to the Applicant in relation to either Property. Were the FSP’s requests for information unreasonable? The FSP’s requests for information in relation to the Applications were not unreasonable and were consistent with standard industry practice for assessing finance applications Did the FSP delay the Settlements? The FSP did not cause the Settlements to be delayed and is not required to compensate the Applicant in relation to the penalty interest for either Property. Case No: 461288 Recommendation Page 2 of 9 3.3 Recommendation This Recommendation is in favour of the FSP. The FSP did not mislead the Applicant, make unreasonable requests for information or cause the Settlements to be delayed in relation to the Properties. Case No: 461288 Recommendation Page 3 of 9 4 Reasons for Recommendation 4.1 Did the FSP mislead the Applicant in relation to her Applications? The parties provided conflicting recollections about pre-approval C says that she spoke with AT, a representative of the FSP, who granted her pre - approval for finance to purchase both Properties over the phone on 8 September 2016. Further, C says that she only bought the Properties because AT told her that the FSP would fund the purchases. However, the FSP denies ever providing verbal and/or written pre-approval to the Applicant for either Property. The FSP also says that it does not provide pre-approval in its normal course of business. FOS is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess disputes, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to contemporaneous documentary information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. The Applicant’s claim is not established A detailed timeline of events is included in section 3.1 below. Based on the information available, the FSP did not grant the Applicant pre -approval for finance to purchase either Properties or misled it in that regard. The reasons for reaching this conclusion are as follows:  The parties have provided conflicting recollections in relation to the phone call on 8 September 2016. There is no contemporaneous information to support the C’s claim that the FSP told her it had pre -approved finance to purchase the Properties.  The FSP says that it does not have a call recording or contemporaneous note of this convers ation on 8 September 2016. AT’s file note dated 25 November 2016 regarding his recollection of discussions with the Applicant does not mention any discussion regarding pre-approvals.  None of the emails between the parties say pre-approval was granted.  The available information shows that C had not given specific details about the exact Properties she or the Applicant was to purchase, the amount of finance required or the Applicant’s financial information to the FSP on or before 8 September 2016. This information would usually be required for a pre -approval to be granted. It is not reasonable to conclude that the FSP could have given pre-approval based on the very limited information the Applicant had provided.  C states in her email to AT on 14 September 2016 that she still needs to organise finance. This indicates C was aware that she did not have finance approved before she signed the contract of sale for Property G on 13 September 2016. Case No: 461288 Recommendation Page 4 of 9  Whilst C says AT’s email dated 15 September 2016 reinforces the pre - approvals provided over the phone; that is not the case. AT only congratulated C on her purchase and discussed next steps. There is no mention of pre- approvals and/or formal approvals from the FSP at any stage.  The first time C mentioned Property F to the FSP was on 24 September 2016, when she informed AT that she had purchased it. Prior to this date, C had only mentioned Property G and a different property (BB), which she was also looking to purchase, but was not successful. The Applicant cannot reasonably have obtained pre-approval from the FSP to purchase Property F on 8 September 2016 when C had not provided any information to the FSP about it. Further, her email dated 24 September 2016 says she would need to organise finance for Property F. Again, this supports the conclusion she was aware she did not yet have finance approval.  The Applicant did not submit any loan application forms to the FSP until November 2016, two months after C purchased the Properties.  On 14 November 2016, KS, a representative of the FSP, states that the loan funding remains subject to the FSP’s formal credit assessment process, indicating that the loans had not yet been approved. Based on the information available, the FSP:  did not provide pre-approvals in relation to either Property, at any stage  did not mislead the Applicant in relation to the Applications. Accordingly, it is not necessary for FOS to consider:  whether or not the Applicant relied on any misrepresentation made by the FSP; or  what loss the Applicant suffered as a result of any misrepresentation made by the FSP. 4.2 Were the FSP’s requests for information unreasonable? The FSP requested further information from the Applicant C says that the information requested by the FSP in relation to the Applications was unreasonable and that she had not been required to provide such information for previous property purchases. She also says that some of the information requested by the FSP was already available to it and also, that some of the infor mation was irrelevant. C believes that the FSP was actively trying to block the approval process by using stalling tactics. A complete list of information requested by the FSP is included in section 3.2. Th e FSP’s requests for information were reasonable The information requested by the FSP was not unreasonable. It is standard industry practice for a financial services provider to request the information that the FSP has requested in this case. Further, the FSP was entitled to make a commercial credit risk decision about the information it required to consider the Applications and whether to approve them. FOS does not review such commercial credit risk decisions. Case No: 461288 Recommendation Page 5 of 9 4.3 Did the FSP delay the Settlements? The FSP did not cause the delay in Settlements C did not have unconditional finance approved before she entered into the contracts of sale of the Properties on 13 and 24 September 2016. Both contracts were not subject to finance when C signed them. As the FSP had not granted the Applicant pre-approval for finance to purchase the Properties, or misled C in that regard when she signed the contracts, it is not responsible for the delay in Settlements. This is because the FSP had no obligation to the Applicant to provide finance in time for the original, or any later, Settlement dates. The FSP is not required to compensate the Applicant for any penalty interest and/or vendor’s legal costs in relation to the Settlements. Case No: 461288 Recommendation Page 6 of 9 5 Supporting information 5.1 Timeline of events Date Event 17 August 2016  Email from JL, a representative of the FSP, to C – discussion regarding C’s home loan 30 August 2016  Email from C to JL – C asking JL to organise pre - approval for two investment loans of about $320, 000 each. No specific details of the properties or finance required were provided 8 Sep tember 2016  C called JL – spoke to AT and informed him about the properties she was looking at. C says AT grant ed her pre - approval over the phone.  Email from JL to AT (4:08 pm) – forwarding C’s email dated 30 August 2016  Email from AT to C (4:56 pm) – ack nowledging C is making an offer for Property G. 11 September 2016  Email from C to AT – C also looking at buying another property. 12 September 2016  Emails between C and AT – regarding the second property and C’s current property. 13 September 2016  Cont ract of Sale for Property G entered into. 14 September 2016  Email from C to AT – C successful in purchasing Property G. C stated that she will need to organise financ e and settlement is in 65 days. 15 September 2016  Email from AT to C – AT acknowledg ing C’s email dated 14 September 2016 and stating that private banker (SS) will assist in transaction and amending existing facility.  C says the FSP’s pre - approval was reinforced in this email . 16 September 2016  Joint call with C, AT and SS, a representat ive of the FSP, to determine Property G would be purchased under the unit trust. 24 September 2016  Cont ract of Sale for Property F entered into.  Email from C to AT – C successful in purchasing Property F. C says she will need to organize finance for the purchase of F Property. 26 September 2016  Emails between C and AT – agreed to meet on 4 October 2016. 4 October 2016  AT met with C – C advised AT of her pers onal circumstances. AT advised C that servicing in the past was heavily based on her ex - husband’s income and that her taxable income in 2015 was approximately $15,000. AT says he provided a copy of the Privacy Consent form, Statement of Positio n and Valuation Authority to C at this meeting. However, C says she does not recall receiving paperwork from AT on this date. 17 October 2016  Email from AT to C asking for returned Statement of Position and Valuation Authority; soft copy sent as attachments. C says she was unaware of this email and then was on leave. She says she had limited Case No: 461288 Recommendation Page 7 of 9 phone contact and no IT access whilst on leave. 18 October 2016  Email from C to AT – C states she has lost her security information and believed that her email and internet banking had been compromis ed by her ex - husband.  Email from AT to C – AT advises C to contact the relev ant FSP team to access all account information and balances. 19 October 2016  C on leave. 2 November 2016  C called AT and asked about status of Applications. AT informed C that requisite forms not returned. C says no forms provided to her and asked for forms to be sent to her. C says this conversation happened on 2 November 2016, whereas FSP says it happened on 9 November 2016. 9 November 2016  Email from FSP to C – AT sent Privacy Consent Form, Statement of Position and Valuation Authority and requested details of the C’s conveyancer/solicitor, to get copies of the Contracts of Sale. 10 November 2016  Property G settlement was due to occur on this date. 11 November 2016  Email from KS, a represent ative of the FSP, to C – contains list of all information required for Applications (see section 3.2) 14 November 2016  Email from KS to C – various indicative loan options and indicative repayment calculations provided to C. KS states that the information requested in his email dated 11 November 2016 is required by the FSP in order to consider and assess loan funding for the C. KS also states that the loan funding remains subject to the FSP’s formal credit assessment process.  C says she returned all information required to KS by email on this date. There is a sign ed and completed Statement of Position and Application for Business Financ e dated 14 November 2016, but no email to show what other information was provided to the FSP by C. 18 November 2016  Phone call between C and KS – C says it became clear to her that FSP would not provide her with the loans.  Email from KS to C – KS says that he has contacted the real estate agent to obtain copy of rec eipt confirming deposit has been paid and mentions the loan amounts sought and related fees. 20 November 2016  Email from C to KS – C mentions that she previously had pre - approval from AT prior to paying deposit on bot h Properties. She says her understanding and experience is that the loan application proc ess is then standard following this pre - approval. She also says th at all previously requested information has already been provided, but questions how certain bits of information are relevant and why they were required. 21 November 2016  Email from KS to C – FSP declines the Applications. KS also says that pre - approval w as not previously provided, explains why certain information previously requested is required for the approval process and notes that this information has not been provided to date. 24 November 2016  Property F settlement was due to occur on this date. Case No: 461288 Recommendation Page 8 of 9 25 November 2016  Face to face meeting between C, FG and IS (representatives of the FSP) – C maint ains that she had pre - approval and only bought the Properties because AT told her that the FSP would fund the purchases. IS stated that the FSP does not undertak e pre - approvals in the normal course of business. IS asked C for written evidence of pre - approval; C said it was all verbal. IS and FG explained to C that the available information does not show sufficient income to service the loan amounts sought, as the FSP did not know how much C is going to contribute to the purchases. C stated that the information was incorrect and that she did have the ability to service. C discussed AT’s behaviour towards her and said that she felt bullied by the FSP. The meeting end ed with C saying that she would be going to A Current Affair about this. 6 January 2017  Applicant obt ained conditional approval through another financial services provider. 31 January 2017  Two letters from vendor’s solicitor to C – Applicant liable to pay penalty interest ($7,751.15 for Property F and $6,039.86 for Property G) and vendor’s legal costs ($330 for Property F and $660 for Property G) due to delay in Settlements. 3 February 2017  Both Property settlements were due to occur on this date. 5.2 List of information requested by the FSP The following information was requested by the FSP in KS’s email to C on 11 November 2016:  Confirmation of loan facility/amount sought for Property G  Confirmation of loan facility/amount sought for Property F  Confirmation that the Applicant will pay all legal, stamp duties, fees together with related costs for both Property G and Property G  Purchases from Applicant’s cash holdings  Signed Business Loan Application Form  Signed Privacy Consent Form  Signed Statement of Position  Signed Valuation Authority  Signed Contract of Sale for Property G  Signed Contract of Sale for Property F  Draft Transfer of Land for Property G  Draft Transfer of Land for Property F  Contact details for the Applicant’s conveyancer  The Applicant’s quarterly BAS statements  Confirmation of anticipated rent that the Applicant will pay to operate/practice her business going forward given that the current premises she operates from is being sold  Details of anticipated rental income expected from Property G in the event the Applicant is going to rent out the property.  Details of anticipated rental income expected from Property F in the event the Applicant is going to rent out the property. Case No: 461288 Recommendation Page 9 of 9  ATO taxation portals statements for the Applicant and her related company /trust  Evidence of deposit(s) paid in relation to the Property G and Property F  Evidence of the Applicant’s funds to complete the settlement for Property G  Evidence of the Applicant’s funds to complete the settlement for Property F  Contact details for the Applicant’s accountant  Confirmation that the relevant trust deed has not been varied since last presented to the bank  Insurance Certificate of Currency for Property G noting FSP as an interested party, acceptable replacement cover and public liability for minimum $10 million.  Insurance Certificate of Currency for Property F noting FSP as an interested party, acceptable replacement cover and public liability for minimum $10 million.  Insurance Certificate of Currency for another one of the Appli cant’s properties, noting FSP as an interest party, acceptable replacement cover and public liability for minimum $10 million

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.