Determination 460319

Storm water damage claim initially declined on exclusions, then partially settled; resultant damage, loss of rent and claim costs disputed

FirmFinancial Firm (Unknown - Insurer)
Decided2017-10-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$104,595
Non-financial loss—
Amount claimed$177,733
SourceAFCA PDF

Summary

A company owning a rental building claimed about $177,733 for storm water damage, which the FSP initially declined on exclusions and later partly settled at $10,923.45. AFCA found the exclusions not established, ordered the FSP to pay $75,000 for property damage, $20,000 loss of rent, $5,000 claims preparation, $1,595 engineer's report and up to $3,000 for two further reports, with interest, reducing the claim for the delay caused by both parties.

The insurer must prove an exclusion on the balance of probabilities, and the defects relied on were not shown to be the proximate cause; the FSP's failure to arrange make-safe works and its delay also made it responsible for resultant damage costs.

Issues

Subjects and remedies

business interruptionhome or building damagenatural disastersmall businesspay claimpay compensationpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 460319 Determination Page 1 of 13 Case number: 460319 4 October 2017 1 Overview 1.1 Dispute The applicant is a company, represented by its officer, JW. In this determination, JW will be referred to as the applicant. On 27 January 2016, a storm caused damage to the applicant‟s property. The applicant says he inspected the property the day after the event and did not see any major damage. Upon further inspection in mid-February 2016, the applicant says he noticed more damage to the property, including mould. On 17 March 2016, the applicant lodged a claim with the financial services provider (FSP). The FSP initially declined the claim because it said the damage was not caused by the storm, but due to a combination of factors excluded under the policy. The FSP later reversed its decision and offered a partial settlement of $10,923.45, to cover the repair costs. This is because the FSP considers the applicant prejudiced it by not lodging a claim in January 2016. 1.2 Issues and key findings Has the applicant established a loss covered by the terms of the policy? There is no dispute a storm caused damage to the property. The policy provides cover for accidental damage. The applicant has therefore established a loss covered by the terms of the policy. Has the FSP established any damage is excluded? The FSP has failed to establish the damage is excluded under the policy. Did the applicant prejudice the FSP by delaying lodgement of the claim? The information suggests the FSP has suffered some prejudice as a result of delay in lodging the claim. Is the FSP required to accept the claim? The FSP is required to pay the claim for the internal damage, loss of rent and additional costs in accordance with section 1.3. Case No: 460319 Determination Page 2 of 13 1.3 Determination This determination is substantially in favour of the applicant. The FSP is to settle the applicant the following:  $75,000 (ex GST) for the damage to the property  $20,000 for loss of rent  $5,000 for claims preparation costs  $1,595 for I‟s report.  S ubject to providing invoices for C‟s and A‟s reports, the FSP is to settle the applicant for these costs, up to a maximum of $3,000 for the two reports. Interest is payable on any of the above amounts previously paid by the applicant, calculated from the date the applicant paid the above costs to the date of payment in line with section 57 of the Insurance Contracts Act 1984 (the Act). Case No: 460319 Determination Page 3 of 13 2 Reasons for determination 2.1 Has the applicant established a loss covered by the terms of the policy? Applicant has the burden to establish a claim covered by the terms of the policy It is accepted insurance law that an insured carries the initial onus to establish a claim which is covered by the terms and conditions of the policy. The applicant‟s policy provides cover for acc idental physical loss of or damage to the property. The expression “accidental damage” is not defined in the policy. Courts define “accidental damage” as damage that is unintended and unexpected (from the point of view of the insured person). If the applicant is able to establish a claim covered by the terms of the policy, the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. Circumstances of the claim The applicant says a major, one in a 100 year storm event, occurred on 27 January 2016. The applicant says he conducted an inspection of the property, a day after the storm and did not see any major damage. The applicant provided some news articles depicting the severity of the storm. He also provided an email from a previous tenant, MK, who stated:  In January 2016, the area was hit hard with 24mm of rain in just 20 minutes and the state emergency service had more than 400 calls as a result of the intense weather.  As a leading civil contractor for more than 30 years, he had not experienced such torrential rain in such a short period of time. The applicant says he conducted another inspection in mid-February 2016, with the previous tenant and new tenant, as part of the handover. The applicant says he then realised the damage was more severe than originally thought. He lodged a claim in early March 2016. The applicant stated in the claim form:  due to the “sheer volume of water” and inability of t he box gutters to cope, water flooded into the building  water flooding in the road entered via the garage roller door  the building has been unoccupied since January 2016 and he was not aware of the damage until he went through the property with the new tenant. The FSP originally declined the claim. It later reversed its decision and agreed some remedial works would have likely been required on the day of loss. However, it only Case No: 460319 Determination Page 4 of 13 offered a partial settlement, as it believed this represented the fair and reasonable assessment of the costs, had the damage been notified immediately. Applicant has established a claim covered by the terms of the policy The FSP does not dispute a storm caused damage to the property. The FSP‟s loss adjuster, AG, stated in a report dated 6 April 2016, that the probable cause of damage to the property was an increasingly large volume of rainwater, inundating storm water drains and overwhelming gutters and roofs, allowing water to ingress into the office area and damage other sections of roofing material. On the basis of the information provided, the Panel is satisfied the applicant has established a claim for accidental damage under the policy. 2.2 Has the FSP established any damage is excluded? FSP says some damage excluded The FSP says not only was it prejudiced by the late notification of the claim, it says certain damage is excluded. The FSP refers to the following exclusions within the policy:  wear and tear, gradual deterioration, scratching, marring, developing flaws, normal upkeep or any gradual cause;  corrosion, rust, oxidation, any form of fungus, wet or dry rot, dampness of atmosphere, variation in temperature, evaporation, disease, shrinkage;  creeping, heaving, normal settling, shrinkage, seepage, vibration, expansion in buildings, pavements, roads, car parks and the like;  error or omission or wrong design;  faulty materials or workmanship. The FSP provided a report from an engineer, MCS, which it says refers to the poor state of the building, long term corrosion and inadequa te drainage systems. MCS stated the deficiencies to the roof and storm water drainage system have been occurring over a long period of time and are known to the insured due to the minor attempts at repair visible. MCS said roof leaks, corrosion, partial upgrade works, undersized stormwater drainage pipes, absence of overflow provisions, blockages and corrosion to downpipes are causing several leak events at the building. MCS stated:  the roof had been leaking over an extended period of time for several years  the roof had undergone partial replacement and waterproofing/patching in 2009 or 2010, but it had not sufficiently remediated the roofing leak issues  the roof shows signs of long term corrosion and substandard roofing installation/repairs  corrosion to the roof sheeting and downpipes allow storm water to leak. The FSP says this shows the damage was due to a combination of factors such as existing roof leaks, corrosion and undersized storm water drainage pipes, absence of overflow provisions, blockages and corrosion to downpipes. Case No: 460319 Determination Page 5 of 13 Applicant says damage caused by storm The applicant provided a report from A, a builder, which states the box gutters were unable to cope with the sheer volume of water due to the storm. A stated:  the „one in 100 years‟ rainfall o n 27 January 2016, caused a large portion of the damage  the damaged areas underneath the three southern-most box gutters are likely to have been caused by box gutter overflow during a freak episode of rainfall  the damage was consistent with a one off water ingress due to excessive rainfall, causing box gutter overflow  there were no signs of accumulative water damage to these areas. The applicant says A undertook a full inspection of the property, including the roof and box gutter lines and reported on resultant damage. The applicant says this is contrary to the engineer from MSC, who did not access the roof. The applicant says MCS made incorrect statements in the report and only relied on a Google map as a basis to form its opinion, rather than access the roof. The applicant says A‟s report shows the damage to the walls and skirting aligns with the box gutters on the roof, which it says supports its contention that the resultant damage is due to the box gutters being unable to cope, along with the street level water entry on the day of the storm. The applicant says there have been no issues with maintenance since it has owned the property and provided statements from previous tenants in support. The applicant provided an email dated 19 May 2016, from a previous tenant, SH, who stated there were no issues with rain at the building. He says these tenants, due to their company profiles, would be required to report any incidences of water ingress or mould, however, both confirm there were no water entry issues . The applicant also says the building was constructed in the 1950s or 1960s and would have complied with the building codes at that time. The applicant provided a report from an engineer, I, who completed a desktop assessment of the MCS report. The report stated:  MCS did not cite any direct evidence to support his contention that the damp damage had occurred over a lengthy period of time  a greed with MCS‟s statement that the cracking and movement of the rear brick wall was long or medium term damage and not from one storm event  MCS‟s comments regarding the undersized PVC pipework would require extensive testing or detailed hydraulic analysis and there is no suggestion this was done  MCS also did not state whether the undersized pipework would have caused the damage  the anecdotal information from previous tenants and one independent report strongly suggests the damp damage was not incremental and long term  it is most likely the damp damage resulted from an old and in part faulty, roof stormwater system being overloaded by a major storm event Case No: 460319 Determination Page 6 of 13  the most likely scenario was that the damage was caused by the storm on 27 January 2016, exacerbated by a sub-standard roof stormwater system. Having reviewed all of the exchanged material, the Panel is not satisfied that the FSP has established that all of the damage at the property was caused by events excluded under the policy. Whilst it has pointed to defects at the property, the FSP‟s obligation is to establish that those defects were the proximate cause of the damage at the property. The Panel is not satisfied that the FSP has met its obligation to do so. 2.3 Did the applicant prejudice the FSP by delaying lodgement of the claim? FSP says applicant prejudiced its ability to assess claim The FSP says the applicant prejudiced its ability to assess the claim by delaying lodgement of the claim. The FSP said it had been prejudiced by the applicant‟s failure to take reasonable precautions to prevent damage. The FSP refers to an engineering report from MCS, dated 10 October 2016, which stated:  it is unlikely rain water ingress through the roof will result in surface mould if the rain water is removed in a timely manner  in its opinion, the proximate cause of the mould in the carpets and walls was the moisture being left in the building for more than 40 days prior to treatment  in its opinion, leaving rain water flooded floor coverings for more than 40 days unattended in an unventilated environment would be considered negligent maintenance and the likely proximate cause of the mould. The FSP says the claim form states the property was unoccupied after the storm. It says if the property was inspected in January 2016, then the mould may not have been visible or may not have been present at this early stage. However, it says the presence of water inside the building and wet carpet would have been clearly visible. It says this should have prompted the need for mitigating the loss, including dehumidifying the building and alerting the FSP of this damage. The FSP refers to the report of S, a restoration company, dated 5 August 2016, which states the carpets and underlay would most likely have been restorable had a restorer attended the property on 27 January 2016. The FSP says but for the delay in the initial inspection, the damage caused by long term moisture in the carpet and walls would have been avoided. It says any costs associated with carpet replacement, decontamination, hygienists and remediation works are excluded. The FSP says it would have arranged make safe repairs as soon as it was notified of the damage. It says due to the nature of the damage, it would have arranged a restorer or make safe provider to attend the premises immediately upon receipt of the claims notification. It says this is standard practice. Case No: 460319 Determination Page 7 of 13 S says an estimated restoration time to complete the works outlined in its report would be seven to ten days. It says if required to complete the works two months after with the current mould concerns, it would have taken up to four weeks to complete, depending on the level of involvement from hygienists. Applicant says actions were reasonable The applicant says it takes a week or two for mould to become visible and as soon as he became aware of the damage, he immediately notified the FSP, who took over the process. The applicant says the FSP delayed the assessment which exacerbated the costs. The applicant provided the following timeline:  27 January 2016 - storm event  28 January 2016 - inspected the property and could not see any damage  17 February 2016 - inspected the property with previous and new tenant and noticed damage  19 February 2016 - contacted his insurance broker who told the applicant to contact the FSP  22 February 2016 - contacted the FSP who asked the applicant to download and fill out a claims form  13 March 2016 - lodged the claim  23 March 2016 - the FSP‟s loss adjuster, AG, inspects the property  26 April 2016 - the FSP denied the claim  May – June 2016 - applicant engages engineer, I, to provide report  5 July 2016 - applicant engages LMI to assist in claim  27 July 2016 - the FSP reverses its decision  July – August 2016 - the applicant engages C and A to prepare reports on damage  26 August 2016 - the FSP issues an internal dispute resolution response denying the claim  25 October 2016 - the FSP reverses decision and offers $10,923.45. The applicant provided an additional email from the previous tenant, MK, dated 22 January 2017. MK stated:  he was in a part-time caretakers role on behalf of the applicant, utilizing some space in the property as storage unti l a new tenant was involved  after the 27 January 2016 storm, MK inspected the property and apart from some water at the rear of the property in the back shed, it was MK‟s opinion at this time that he was very lucky to escape  it was not until the applicant, MK and the new tenant IB met at the property on 17 February 2016, that conditions had dramatically changed  he was only a part-time caretaker and there was no payment agreement at the time. The applicant says his actions fully align with his obligations under the policy and it was the FSP‟s delay in assessing the claim and failure to provide a make safe at the property that exacerbated the costs incurred. Case No: 460319 Determination Page 8 of 13 Some delay Having reviewed all of the exchanged material, the Panel is satisfied that there has been delay on the part of both parties to the dispute. In particular, the Panel is concerned by the delay that occurred after the first report from the FSP‟s assessor that confirmed make safe repairs were required. On the other hand, the Panel has difficulty accepting that MK would not have noticed any damage and in particular would not have noticed wet carpets. The Panel is satisfied that the delay in claim lodgement has contributed to a small degree, to the extent of the loss. The FSP should be entitled to reduce its obligations under the policy to the extent that the loss was worsened by that delay. 2.4 Is the FSP required to increase its offer? Applicant seeks cover for all resultant damage The applicant is claiming for only resultant damage and all costs associated with the resultant damage, including:  expert reports  remediation works, including concrete slab treatment and hygienist  carpet replacement  reinstatement of resultant damage to structure, walls and ceiling  loss of rent  claims preparation. The applicant claims the following: Loss Amount I‟s Report $1,595 C‟s Report $5,000 C‟s Budget Estimate for Decontamination $39,319 C‟s Budget Estimate for Carpet Replacement $27,600 Recommended Hygienist $10,000 (estimate) A‟s Report $5,000 (estimate) A‟s Budget Estimate for Remediation Works $16,905 Loss of Rent (June to February 2017 ) $ 30,006 Outgoings expenses $8,000 Claim Preparation Expenses (Initial Fee Only) $ 19,308 Basic repair works expenses incurred to date $15,000 TOTAL $ 177,733 ex GST ( approx) Case No: 460319 Determination Page 9 of 13 FSP made a limited offer for remedial works The FSP says some remedial works would have likely been required on the day of the loss. It referred to a report by S, a restoration company, dated 5 August 2016. S prepared a scope of works based on works required if it had attended the premises on 27 January 2016. The FSP says S‟s report was based on the measurements of the office area and its drying calculations detailed in its report. S stated based on the available reports and documentation provided by the FSP, that had it attended on 27 January 2016, the following damage from a box gutter overflow from storm would be present:  given water entered via the roof space only, believe it to be a category 2, and class 3 water loss  carpets and underlay affected but would have most likely been restorable  northern wall has some staining which requires cleaning. S stated the following mitigation and restoration works would have been completed:  extract excess water from affected areas  remove and dispose of underlay from carpet  application of anti-microbial treatment  installation and hire of drying equipment  supply new underlay for areas removed  prepare floor for installation of new underlay and re -stretching of carpet  drill, plug and supply new trims  clean and deodorise carpet  clean northern wall. The FSP said claims preparation costs would be considered and offered $5,000 to meet these costs. The FSP offered $10,923.45, which includes the following:  $6,423.45 contribution towards carpet replacement (in line with S‟s report)  $5,000 claims preparation costs  Less $500 excess. The FSP says had a full and thorough inspection occurred the day after the storm, the damage observed in February would have been identified then. It says this would have allowed the applicant to take all reasonable precautions to prevent further loss. Applicant says offer is insufficient to cover costs The applicant provided a report from C, a restoration company, which recommends extensive remediation works to rectify the water damage and mould growth as a result of overflowing box gutters from the storm. C recommended:  urgent and safe removal and disposal of carpet, including underlay  slab treatment  removal and disposal of mould-affected ceiling tiles, skirting and plaster Case No: 460319 Determination Page 10 of 13  appointment of a hygienist to undertake post-remediation works. C provided an estimate as follows:  $39,319 for decontamination of organic growth  $27,600 for carpet replacement. C provided an estimate timeframe of 20 days to complete the works. The applicant provided a report from A, a building company, dated 16 August 2016. A outlined the internal damage to the building, which it says was caused by the storm. The estimate for works including painting, plaster, tiling and carpentry, amounted to $16,905. The applicant also seeks an estimate of $10,000 for a hygienist. The applicant provided an invoice from L, dated 21 October 2016, for $16,500 for minimum works required to the property for L to commence its tenancy at the property. These works included removal of the carpet, box gutters, flashing, microbial treatment to mould affected areas, connecting the stormwater pipes and repairs to roof. The applicant sought the FSP to commence these repairs, to allow the tenant to occupy the property and loss of rent would not be incurred. FSP to increase offer for resultant damage Due to the FSP failing to attend to any make safe repairs, the panel considers the FSP is responsible for the costs associated with the repairs of the resultant damage. The FSP is therefore liable to cash settle the applicant for the following: C‟s Budget Estimate for Decontamination $39,319 C‟s Budget Estimate for Carpet Replacement $27,600 A‟s Budget Estimate for Remediation Works $16,905 Basic repair works expenses incurred to date $15,000 TOTAL $ 98,824 ex GST This amount is to be reduced to allow for the prejudice suffered by the FSP as a result of delay. In addition, the accounts submitted by the applicant include an allowance for repairs to damage that pre dated the storm. It is clear that the FSP is only responsible for storm caused damage. It is fair that the FSP pay $75,000 in respect to this aspect of the applicant‟s claim. The applicant has quoted a hygienist for $10,000, however, no quote was provided. In the circumstances and in the absence of any information to support this aspect of the claim, the panel does not consider the FSP is liable for this sum. Case No: 460319 Determination Page 11 of 13 Loss of rent The applicant seeks loss of rent of $30,006 for the period June 2016 to February 2017. The FSP says if not for the delay in notification of the claim, the applicant would not have suffered any loss of rent. The applicant says it made arrangements for a new tenant to commence in February 2016. Due to the water ingress, it offered a rent free period from February 2016 to May 2 016. The applicant says due to the FSP‟s delays and ongoing denials, it has incurred losses of $13,336 for the period June 2016 to September 2016. The applicant provided a copy of the lease dated 10 February 2016, specifying a rental period of two years commencing 26 February 2016. The lease detailed the rent-free period of February 2016 to May 2016, then $3,334 per month for rent. The PDS provides cover for business interruption, which includes the following: „ Item 5 – Loss of Rent Receivable This item is limited to loss of Rent Receivable and additional expenditure. The amount payable will be: (a) in respect of loss of Rent Receivable the amount by which the Rent Receivable during the Indemnity Period falls short of the Standard Rent Receivable, in consequence of the Damage; and (b) in respect of additional expenditure the additional expenditure necessarily and reasonably incurred for the sole purpose of avoiding or diminishing the loss of Rent Receivable which, but for that expenditure, would have taken place during the Indemnity Period in consequence of the Damage, but not exceeding the amount of the reduction in Rent Receivable thereby avoided, Less any sum saved during the Indemnity Period in respect of such of the expenses and charges payable out of the Rent Receivable as may cease or be reduced in consequence of the Damage.‟ Rent receivable is defined as: „ Rent Receivable means the amount of the rent received or receivable (including base rental, Turnover rental and contributions to outgoings) from the letting of property at the Situation.‟ Had the FSP completed the repairs in a timely manner, the delays and further exacerbation of the damage would not have occurred. S estimated if required to complete the works two months after with the current mould co ncerns, it would have taken up to four weeks to complete, depending on the level of involvement from hygienists. Given the applicant‟s effort to maintain a tenant, with free rent for a three month period during the period repairs could have been completed, the FSP is liable for the additional costs incurred by the applicant due to the FSP‟s failure to complete the repairs. On the other hand, the information with regard to loss of rent is not complete. The applicant has not provided full details of property tenancy. Given the information it has, the Panel is satisfied that it is fair that the FSP should pay the applicant $20,000 with regard to the question of loss of rent. Case No: 460319 Determination Page 12 of 13 Claims preparation expenses The applicant seeks in excess of $20,000 for claims prepara tion costs due to a company assisting in resolving the claim. The applicant says its services were necessary to enable the FSP to reverse its decline. The applicant says it believes there was an agreement between him and the FSP that should it be able to show a valid claim exists, it would be indemnified for the claims preparation benefit. The FSP offered $5,000 for these costs. It says this was based on the fact these expenses were incurred for items that are not covered under the policy or declined due to the late notification of the claim. The FSP calculated its share of the claims preparation costs by basing it on two full days at $300 per hour, being $4,500, plus $500 for administration and other incidental costs. The applicant provided an invoice from LMI dated 6 December 2016, amounting to $11,000, plus a timesheet for works amounting to $19,308.81. The PDS provides: „ Claim preparation expenses Subject to our written approval (which approval will not be reasonably withheld), we will pay for costs necessarily and reasonably incurred for the preparation and negotiation of a claim for which we agree to indemnify You under this Policy. The most we will pay is $25,000 in total for any one claim, unless a higher amount is included in the particular section of the Policy. This benefit is in addition to any Insured Amount or Limit of Liability. ‟ The Certificate of Insurance lists the maximum amount for claims preparation costs under business interruption is $50,000. Under business interruption, the PDS defines it as: „ Item 4 – Claim preparation expenses In addition to the amount payable under General Policy Benefit „Claim preparation expenses‟ of this Policy we will pay You up to the amount shown in the current Policy Schedule for the costs of such reasonable professional fees as may be payable by You and other such reasonable expenses necessarily incurred by You and not otherwise recoverable, for preparation and negotiatio n of claims under this section.‟ The PDS requires the FSP‟s written approval prior to incur ring claim preparation expenses. The applicant did not obtain the FSP‟s prior written consent, therefore it is not entitled to payment for this additional benefit. Whilst the applicant believed there was an agreement in place, no such evidence has been pro vided to establish this belief. However, under paragraph 9.4 of the FOS Terms of Reference (TOR), the Service can consider whether the FSP should contribute to legal or other professional costs incurred by an applicant. An FSP will generally not be required to contribute more than $3,000, unless exceptional circumstances apply. Given the FSP‟s initial denial of the claim, the applicant says the appointment of a firm, LMI, was necessary to assist in the handling of the claim. Case No: 460319 Determination Page 13 of 13 The Panel considers the applicant‟s reasoning for appointing LMI to be reasonable in the circumstances. However, the Panel considers the offer of $5,000 to be reasonable for this service. Consequential losses The applicant also claims $1,595 (e x GST) for I‟s engineering report. H e provided an invoice in support. The applicant also claims $5,000 for an estimate of C‟s report, $5,000 as an estimate for A‟s report and $8,000 for outgoing expenses in relation to the lease. The Panel accepts it was reasonably necessary for the applicant to obtain the reports referred to above. It was reasonable for the applicant to appoint I, to discuss the FSP‟s engineering report, as he had concerns regarding MCS‟s report. It was also reasonable for the applicant to appoint A and C, to consider the da mage required to be repaired at the property. Given the range of issues the applicant was required to address in the dispute, and owing to the FSP‟s original denial of the claim, the Panel considers the FSP is required to reimburse the applicant for these costs. The FSP is to settle the applicant $1,595 for I‟s report. In addition, s ubject to providing invoices for C‟s and A‟s reports, the FSP is to settle the applicant for these costs, up to a maximum in total of $3,000 for the two reports. However, the applicant has failed to support his claim for outgoing expenses in the sum of $8,000. In these circumstances, the FSP is not required to settle the applicant for this sum. The FSP is liable to pay interest calculated from the date the applicant paid the above costs to the date of payment in line with section 57 of the Act.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.