Storm water damage claim initially declined on exclusions, then partially settled; resultant damage, loss of rent and claim costs disputed
Text of the determination
Determination
Case No: 460319 Determination Page 1 of 13
Case number: 460319 4 October 2017
1 Overview
1.1 Dispute
The applicant is a company, represented by its officer, JW. In this determination, JW
will be referred to as the applicant.
On 27 January 2016, a storm caused damage to the applicant‟s property.
The applicant says he inspected the property the day after the event and did not see
any major damage. Upon further inspection in mid-February 2016, the applicant says
he noticed more damage to the property, including mould.
On 17 March 2016, the applicant lodged a claim with the financial services provider
(FSP).
The FSP initially declined the claim because it said the damage was not caused by
the storm, but due to a combination of factors excluded under the policy.
The FSP later reversed its decision and offered a partial settlement of $10,923.45, to
cover the repair costs. This is because the FSP considers the applicant prejudiced it
by not lodging a claim in January 2016.
1.2 Issues and key findings
Has the applicant established a loss covered by the terms of the policy?
There is no dispute a storm caused damage to the property. The policy provides
cover for accidental damage. The applicant has therefore established a loss covered
by the terms of the policy.
Has the FSP established any damage is excluded?
The FSP has failed to establish the damage is excluded under the policy.
Did the applicant prejudice the FSP by delaying lodgement of the claim?
The information suggests the FSP has suffered some prejudice as a result of delay in
lodging the claim.
Is the FSP required to accept the claim?
The FSP is required to pay the claim for the internal damage, loss of rent and
additional costs in accordance with section 1.3.
Case No: 460319 Determination Page 2 of 13
1.3 Determination
This determination is substantially in favour of the applicant.
The FSP is to settle the applicant the following:
$75,000 (ex GST) for the damage to the property
$20,000 for loss of rent
$5,000 for claims preparation costs
$1,595 for I‟s report.
S ubject to providing invoices for C‟s and A‟s reports, the FSP is to settle the
applicant for these costs, up to a maximum of $3,000 for the two reports.
Interest is payable on any of the above amounts previously paid by the applicant,
calculated from the date the applicant paid the above costs to the date of payment in
line with section 57 of the Insurance Contracts Act 1984 (the Act).
Case No: 460319 Determination Page 3 of 13
2 Reasons for determination
2.1 Has the applicant established a loss covered by the terms of the
policy?
Applicant has the burden to establish a claim covered by the terms of the
policy
It is accepted insurance law that an insured carries the initial onus to establish a
claim which is covered by the terms and conditions of the policy.
The applicant‟s policy provides cover for acc idental physical loss of or damage to the
property.
The expression “accidental damage” is not defined in the policy. Courts define
“accidental damage” as damage that is unintended and unexpected (from the point of
view of the insured person).
If the applicant is able to establish a claim covered by the terms of the policy, the
onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to
rely on an exclusion under the policy or is otherwise entitled to deny the claim.
Circumstances of the claim
The applicant says a major, one in a 100 year storm event, occurred on 27 January
2016. The applicant says he conducted an inspection of the property, a day after the
storm and did not see any major damage.
The applicant provided some news articles depicting the severity of the storm. He
also provided an email from a previous tenant, MK, who stated:
In January 2016, the area was hit hard with 24mm of rain in just 20 minutes and
the state emergency service had more than 400 calls as a result of the intense
weather.
As a leading civil contractor for more than 30 years, he had not experienced
such torrential rain in such a short period of time.
The applicant says he conducted another inspection in mid-February 2016, with the
previous tenant and new tenant, as part of the handover. The applicant says he then
realised the damage was more severe than originally thought. He lodged a claim in
early March 2016.
The applicant stated in the claim form:
due to the “sheer volume of water” and inability of t he box gutters to cope, water
flooded into the building
water flooding in the road entered via the garage roller door
the building has been unoccupied since January 2016 and he was not aware of
the damage until he went through the property with the new tenant.
The FSP originally declined the claim. It later reversed its decision and agreed some
remedial works would have likely been required on the day of loss. However, it only
Case No: 460319 Determination Page 4 of 13
offered a partial settlement, as it believed this represented the fair and reasonable
assessment of the costs, had the damage been notified immediately.
Applicant has established a claim covered by the terms of the policy
The FSP does not dispute a storm caused damage to the property. The FSP‟s loss
adjuster, AG, stated in a report dated 6 April 2016, that the probable cause of
damage to the property was an increasingly large volume of rainwater, inundating
storm water drains and overwhelming gutters and roofs, allowing water to ingress
into the office area and damage other sections of roofing material.
On the basis of the information provided, the Panel is satisfied the applicant has
established a claim for accidental damage under the policy.
2.2 Has the FSP established any damage is excluded?
FSP says some damage excluded
The FSP says not only was it prejudiced by the late notification of the claim, it says
certain damage is excluded.
The FSP refers to the following exclusions within the policy:
wear and tear, gradual deterioration, scratching, marring, developing flaws,
normal upkeep or any gradual cause;
corrosion, rust, oxidation, any form of fungus, wet or dry rot, dampness of
atmosphere, variation in temperature, evaporation, disease, shrinkage;
creeping, heaving, normal settling, shrinkage, seepage, vibration, expansion in
buildings, pavements, roads, car parks and the like;
error or omission or wrong design;
faulty materials or workmanship.
The FSP provided a report from an engineer, MCS, which it says refers to the poor
state of the building, long term corrosion and inadequa te drainage systems.
MCS stated the deficiencies to the roof and storm water drainage system have been
occurring over a long period of time and are known to the insured due to the minor
attempts at repair visible. MCS said roof leaks, corrosion, partial upgrade works,
undersized stormwater drainage pipes, absence of overflow provisions, blockages
and corrosion to downpipes are causing several leak events at the building.
MCS stated:
the roof had been leaking over an extended period of time for several years
the roof had undergone partial replacement and waterproofing/patching in 2009
or 2010, but it had not sufficiently remediated the roofing leak issues
the roof shows signs of long term corrosion and substandard roofing
installation/repairs
corrosion to the roof sheeting and downpipes allow storm water to leak.
The FSP says this shows the damage was due to a combination of factors such as
existing roof leaks, corrosion and undersized storm water drainage pipes, absence of
overflow provisions, blockages and corrosion to downpipes.
Case No: 460319 Determination Page 5 of 13
Applicant says damage caused by storm
The applicant provided a report from A, a builder, which states the box gutters were
unable to cope with the sheer volume of water due to the storm.
A stated:
the „one in 100 years‟ rainfall o n 27 January 2016, caused a large portion of the
damage
the damaged areas underneath the three southern-most box gutters are likely to
have been caused by box gutter overflow during a freak episode of rainfall
the damage was consistent with a one off water ingress due to excessive
rainfall, causing box gutter overflow
there were no signs of accumulative water damage to these areas.
The applicant says A undertook a full inspection of the property, including the roof
and box gutter lines and reported on resultant damage. The applicant says this is
contrary to the engineer from MSC, who did not access the roof. The applicant says
MCS made incorrect statements in the report and only relied on a Google map as a
basis to form its opinion, rather than access the roof.
The applicant says A‟s report shows the damage to the walls and skirting aligns with
the box gutters on the roof, which it says supports its contention that the resultant
damage is due to the box gutters being unable to cope, along with the street level
water entry on the day of the storm.
The applicant says there have been no issues with maintenance since it has owned
the property and provided statements from previous tenants in support. The applicant
provided an email dated 19 May 2016, from a previous tenant, SH, who stated there
were no issues with rain at the building. He says these tenants, due to their company
profiles, would be required to report any incidences of water ingress or mould,
however, both confirm there were no water entry issues .
The applicant also says the building was constructed in the 1950s or 1960s and
would have complied with the building codes at that time.
The applicant provided a report from an engineer, I, who completed a desktop
assessment of the MCS report. The report stated:
MCS did not cite any direct evidence to support his contention that the damp
damage had occurred over a lengthy period of time
a greed with MCS‟s statement that the cracking and movement of the rear brick
wall was long or medium term damage and not from one storm event
MCS‟s comments regarding the undersized PVC pipework would require
extensive testing or detailed hydraulic analysis and there is no suggestion this
was done
MCS also did not state whether the undersized pipework would have caused
the damage
the anecdotal information from previous tenants and one independent report
strongly suggests the damp damage was not incremental and long term
it is most likely the damp damage resulted from an old and in part faulty, roof
stormwater system being overloaded by a major storm event
Case No: 460319 Determination Page 6 of 13
the most likely scenario was that the damage was caused by the storm on 27
January 2016, exacerbated by a sub-standard roof stormwater system.
Having reviewed all of the exchanged material, the Panel is not satisfied that the FSP
has established that all of the damage at the property was caused by events
excluded under the policy.
Whilst it has pointed to defects at the property, the FSP‟s obligation is to establish
that those defects were the proximate cause of the damage at the property.
The Panel is not satisfied that the FSP has met its obligation to do so.
2.3 Did the applicant prejudice the FSP by delaying lodgement of the
claim?
FSP says applicant prejudiced its ability to assess claim
The FSP says the applicant prejudiced its ability to assess the claim by delaying
lodgement of the claim.
The FSP said it had been prejudiced by the applicant‟s failure to take reasonable
precautions to prevent damage. The FSP refers to an engineering report from MCS,
dated 10 October 2016, which stated:
it is unlikely rain water ingress through the roof will result in surface mould if the
rain water is removed in a timely manner
in its opinion, the proximate cause of the mould in the carpets and walls was the
moisture being left in the building for more than 40 days prior to treatment
in its opinion, leaving rain water flooded floor coverings for more than 40 days
unattended in an unventilated environment would be considered negligent
maintenance and the likely proximate cause of the mould.
The FSP says the claim form states the property was unoccupied after the storm. It
says if the property was inspected in January 2016, then the mould may not have
been visible or may not have been present at this early stage. However, it says the
presence of water inside the building and wet carpet would have been clearly visible.
It says this should have prompted the need for mitigating the loss, including
dehumidifying the building and alerting the FSP of this damage.
The FSP refers to the report of S, a restoration company, dated 5 August 2016,
which states the carpets and underlay would most likely have been restorable had a
restorer attended the property on 27 January 2016.
The FSP says but for the delay in the initial inspection, the damage caused by long
term moisture in the carpet and walls would have been avoided. It says any costs
associated with carpet replacement, decontamination, hygienists and remediation
works are excluded.
The FSP says it would have arranged make safe repairs as soon as it was notified of
the damage. It says due to the nature of the damage, it would have arranged a
restorer or make safe provider to attend the premises immediately upon receipt of the
claims notification. It says this is standard practice.
Case No: 460319 Determination Page 7 of 13
S says an estimated restoration time to complete the works outlined in its report
would be seven to ten days. It says if required to complete the works two months
after with the current mould concerns, it would have taken up to four weeks to
complete, depending on the level of involvement from hygienists.
Applicant says actions were reasonable
The applicant says it takes a week or two for mould to become visible and as soon as
he became aware of the damage, he immediately notified the FSP, who took over the
process. The applicant says the FSP delayed the assessment which exacerbated the
costs.
The applicant provided the following timeline:
27 January 2016 - storm event
28 January 2016 - inspected the property and could not see any damage
17 February 2016 - inspected the property with previous and new tenant and
noticed damage
19 February 2016 - contacted his insurance broker who told the applicant to
contact the FSP
22 February 2016 - contacted the FSP who asked the applicant to download
and fill out a claims form
13 March 2016 - lodged the claim
23 March 2016 - the FSP‟s loss adjuster, AG, inspects the property
26 April 2016 - the FSP denied the claim
May – June 2016 - applicant engages engineer, I, to provide report
5 July 2016 - applicant engages LMI to assist in claim
27 July 2016 - the FSP reverses its decision
July – August 2016 - the applicant engages C and A to prepare reports on
damage
26 August 2016 - the FSP issues an internal dispute resolution response
denying the claim
25 October 2016 - the FSP reverses decision and offers $10,923.45.
The applicant provided an additional email from the previous tenant, MK, dated 22
January 2017. MK stated:
he was in a part-time caretakers role on behalf of the applicant, utilizing some
space in the property as storage unti l a new tenant was involved
after the 27 January 2016 storm, MK inspected the property and apart from
some water at the rear of the property in the back shed, it was MK‟s opinion at
this time that he was very lucky to escape
it was not until the applicant, MK and the new tenant IB met at the property on
17 February 2016, that conditions had dramatically changed
he was only a part-time caretaker and there was no payment agreement at the
time.
The applicant says his actions fully align with his obligations under the policy and it
was the FSP‟s delay in assessing the claim and failure to provide a make safe at the
property that exacerbated the costs incurred.
Case No: 460319 Determination Page 8 of 13
Some delay
Having reviewed all of the exchanged material, the Panel is satisfied that there has
been delay on the part of both parties to the dispute.
In particular, the Panel is concerned by the delay that occurred after the first report
from the FSP‟s assessor that confirmed make safe repairs were required.
On the other hand, the Panel has difficulty accepting that MK would not have noticed
any damage and in particular would not have noticed wet carpets.
The Panel is satisfied that the delay in claim lodgement has contributed to a small
degree, to the extent of the loss. The FSP should be entitled to reduce its obligations
under the policy to the extent that the loss was worsened by that delay.
2.4 Is the FSP required to increase its offer?
Applicant seeks cover for all resultant damage
The applicant is claiming for only resultant damage and all costs associated with the
resultant damage, including:
expert reports
remediation works, including concrete slab treatment and hygienist
carpet replacement
reinstatement of resultant damage to structure, walls and ceiling
loss of rent
claims preparation.
The applicant claims the following:
Loss Amount
I‟s Report $1,595
C‟s Report $5,000
C‟s Budget Estimate for Decontamination $39,319
C‟s Budget Estimate for Carpet Replacement $27,600
Recommended Hygienist $10,000 (estimate)
A‟s Report $5,000 (estimate)
A‟s Budget Estimate for Remediation Works $16,905
Loss of Rent (June to February 2017 ) $ 30,006
Outgoings expenses $8,000
Claim Preparation Expenses (Initial Fee Only) $ 19,308
Basic repair works expenses incurred to date $15,000
TOTAL $ 177,733 ex GST ( approx)
Case No: 460319 Determination Page 9 of 13
FSP made a limited offer for remedial works
The FSP says some remedial works would have likely been required on the day of
the loss. It referred to a report by S, a restoration company, dated 5 August 2016. S
prepared a scope of works based on works required if it had attended the premises
on 27 January 2016.
The FSP says S‟s report was based on the measurements of the office area and its
drying calculations detailed in its report.
S stated based on the available reports and documentation provided by the FSP, that
had it attended on 27 January 2016, the following damage from a box gutter overflow
from storm would be present:
given water entered via the roof space only, believe it to be a category 2, and
class 3 water loss
carpets and underlay affected but would have most likely been restorable
northern wall has some staining which requires cleaning.
S stated the following mitigation and restoration works would have been completed:
extract excess water from affected areas
remove and dispose of underlay from carpet
application of anti-microbial treatment
installation and hire of drying equipment
supply new underlay for areas removed
prepare floor for installation of new underlay and re -stretching of carpet
drill, plug and supply new trims
clean and deodorise carpet
clean northern wall.
The FSP said claims preparation costs would be considered and offered $5,000 to
meet these costs.
The FSP offered $10,923.45, which includes the following:
$6,423.45 contribution towards carpet replacement (in line with S‟s report)
$5,000 claims preparation costs
Less $500 excess.
The FSP says had a full and thorough inspection occurred the day after the storm,
the damage observed in February would have been identified then. It says this would
have allowed the applicant to take all reasonable precautions to prevent further loss.
Applicant says offer is insufficient to cover costs
The applicant provided a report from C, a restoration company, which recommends
extensive remediation works to rectify the water damage and mould growth as a
result of overflowing box gutters from the storm.
C recommended:
urgent and safe removal and disposal of carpet, including underlay
slab treatment
removal and disposal of mould-affected ceiling tiles, skirting and plaster
Case No: 460319 Determination Page 10 of 13
appointment of a hygienist to undertake post-remediation works.
C provided an estimate as follows:
$39,319 for decontamination of organic growth
$27,600 for carpet replacement.
C provided an estimate timeframe of 20 days to complete the works.
The applicant provided a report from A, a building company, dated 16 August 2016.
A outlined the internal damage to the building, which it says was caused by the
storm. The estimate for works including painting, plaster, tiling and carpentry,
amounted to $16,905.
The applicant also seeks an estimate of $10,000 for a hygienist.
The applicant provided an invoice from L, dated 21 October 2016, for $16,500 for
minimum works required to the property for L to commence its tenancy at the
property. These works included removal of the carpet, box gutters, flashing, microbial
treatment to mould affected areas, connecting the stormwater pipes and repairs to
roof.
The applicant sought the FSP to commence these repairs, to allow the tenant to
occupy the property and loss of rent would not be incurred.
FSP to increase offer for resultant damage
Due to the FSP failing to attend to any make safe repairs, the panel considers the
FSP is responsible for the costs associated with the repairs of the resultant damage.
The FSP is therefore liable to cash settle the applicant for the following:
C‟s Budget Estimate for Decontamination $39,319
C‟s Budget Estimate for Carpet Replacement $27,600
A‟s Budget Estimate for Remediation Works $16,905
Basic repair works expenses incurred to date $15,000
TOTAL $ 98,824 ex GST
This amount is to be reduced to allow for the prejudice suffered by the FSP as a
result of delay.
In addition, the accounts submitted by the applicant include an allowance for repairs
to damage that pre dated the storm. It is clear that the FSP is only responsible for
storm caused damage.
It is fair that the FSP pay $75,000 in respect to this aspect of the applicant‟s claim.
The applicant has quoted a hygienist for $10,000, however, no quote was provided.
In the circumstances and in the absence of any information to support this aspect of
the claim, the panel does not consider the FSP is liable for this sum.
Case No: 460319 Determination Page 11 of 13
Loss of rent
The applicant seeks loss of rent of $30,006 for the period June 2016 to February
2017.
The FSP says if not for the delay in notification of the claim, the applicant would not
have suffered any loss of rent.
The applicant says it made arrangements for a new tenant to commence in February
2016. Due to the water ingress, it offered a rent free period from February 2016 to
May 2 016. The applicant says due to the FSP‟s delays and ongoing denials, it has
incurred losses of $13,336 for the period June 2016 to September 2016.
The applicant provided a copy of the lease dated 10 February 2016, specifying a
rental period of two years commencing 26 February 2016. The lease detailed the
rent-free period of February 2016 to May 2016, then $3,334 per month for rent.
The PDS provides cover for business interruption, which includes the following:
„ Item 5 – Loss of Rent Receivable
This item is limited to loss of Rent Receivable and additional expenditure.
The amount payable will be:
(a) in respect of loss of Rent Receivable the amount by which the Rent Receivable
during the Indemnity Period falls short of the Standard Rent Receivable, in
consequence of the Damage; and
(b) in respect of additional expenditure the additional expenditure necessarily and
reasonably incurred for the sole purpose of avoiding or diminishing the loss of Rent
Receivable which, but for that expenditure, would have taken place during the
Indemnity Period in consequence of the Damage, but not exceeding the amount of the
reduction in Rent Receivable thereby avoided,
Less any sum saved during the Indemnity Period in respect of such of the expenses
and charges payable out of the Rent Receivable as may cease or be reduced in
consequence of the Damage.‟
Rent receivable is defined as:
„ Rent Receivable means the amount of the rent received or receivable (including base
rental, Turnover rental and contributions to outgoings) from the letting of property at the
Situation.‟
Had the FSP completed the repairs in a timely manner, the delays and further
exacerbation of the damage would not have occurred. S estimated if required to
complete the works two months after with the current mould co ncerns, it would have
taken up to four weeks to complete, depending on the level of involvement from
hygienists. Given the applicant‟s effort to maintain a tenant, with free rent for a three
month period during the period repairs could have been completed, the FSP is liable
for the additional costs incurred by the applicant due to the FSP‟s failure to complete
the repairs.
On the other hand, the information with regard to loss of rent is not complete. The
applicant has not provided full details of property tenancy. Given the information it
has, the Panel is satisfied that it is fair that the FSP should pay the applicant $20,000
with regard to the question of loss of rent.
Case No: 460319 Determination Page 12 of 13
Claims preparation expenses
The applicant seeks in excess of $20,000 for claims prepara tion costs due to a
company assisting in resolving the claim. The applicant says its services were
necessary to enable the FSP to reverse its decline.
The applicant says it believes there was an agreement between him and the FSP
that should it be able to show a valid claim exists, it would be indemnified for the
claims preparation benefit.
The FSP offered $5,000 for these costs. It says this was based on the fact these
expenses were incurred for items that are not covered under the policy or declined
due to the late notification of the claim.
The FSP calculated its share of the claims preparation costs by basing it on two full
days at $300 per hour, being $4,500, plus $500 for administration and other
incidental costs.
The applicant provided an invoice from LMI dated 6 December 2016, amounting to
$11,000, plus a timesheet for works amounting to $19,308.81.
The PDS provides:
„ Claim preparation expenses
Subject to our written approval (which approval will not be reasonably withheld), we will
pay for costs necessarily and reasonably incurred for the preparation and negotiation
of a claim for which we agree to indemnify You under this Policy. The most we will pay
is $25,000 in total for any one claim, unless a higher amount is included in the
particular section of the Policy.
This benefit is in addition to any Insured Amount or Limit of Liability. ‟
The Certificate of Insurance lists the maximum amount for claims preparation costs
under business interruption is $50,000.
Under business interruption, the PDS defines it as:
„ Item 4 – Claim preparation expenses
In addition to the amount payable under General Policy Benefit „Claim preparation
expenses‟ of this Policy we will pay You up to the amount shown in the current Policy
Schedule for the costs of such reasonable professional fees as may be payable by You
and other such reasonable expenses necessarily incurred by You and not otherwise
recoverable, for preparation and negotiatio n of claims under this section.‟
The PDS requires the FSP‟s written approval prior to incur ring claim preparation
expenses. The applicant did not obtain the FSP‟s prior written consent, therefore it is
not entitled to payment for this additional benefit. Whilst the applicant believed there
was an agreement in place, no such evidence has been pro vided to establish this
belief.
However, under paragraph 9.4 of the FOS Terms of Reference (TOR), the Service
can consider whether the FSP should contribute to legal or other professional costs
incurred by an applicant. An FSP will generally not be required to contribute more
than $3,000, unless exceptional circumstances apply.
Given the FSP‟s initial denial of the claim, the applicant says the appointment of a
firm, LMI, was necessary to assist in the handling of the claim.
Case No: 460319 Determination Page 13 of 13
The Panel considers the applicant‟s reasoning for appointing LMI to be reasonable in
the circumstances. However, the Panel considers the offer of $5,000 to be
reasonable for this service.
Consequential losses
The applicant also claims $1,595 (e x GST) for I‟s engineering report. H e provided an
invoice in support.
The applicant also claims $5,000 for an estimate of C‟s report, $5,000 as an estimate
for A‟s report and $8,000 for outgoing expenses in relation to the lease.
The Panel accepts it was reasonably necessary for the applicant to obtain the reports
referred to above.
It was reasonable for the applicant to appoint I, to discuss the FSP‟s engineering
report, as he had concerns regarding MCS‟s report. It was also reasonable for the
applicant to appoint A and C, to consider the da mage required to be repaired at the
property.
Given the range of issues the applicant was required to address in the dispute, and
owing to the FSP‟s original denial of the claim, the Panel considers the FSP is
required to reimburse the applicant for these costs.
The FSP is to settle the applicant $1,595 for I‟s report. In addition, s ubject to
providing invoices for C‟s and A‟s reports, the FSP is to settle the applicant for these
costs, up to a maximum in total of $3,000 for the two reports.
However, the applicant has failed to support his claim for outgoing expenses in the
sum of $8,000. In these circumstances, the FSP is not required to settle the applicant
for this sum.
The FSP is liable to pay interest calculated from the date the applicant paid the
above costs to the date of payment in line with section 57 of the Act.