Home / Financial Firm (Unknown - Insurer) / Determination 459264
Determination 459264
Scope of fire repairs to cornices, fence damage and loss of rent
Summary
After a fire, the landlord disputed cornice repairs, fence damage and loss of rent. AFCA declined to order cornice rectification, ordered $500 towards the fence, and ordered the remaining loss of rent up to the 12-month limit with interest.
Where an insurer authorises repairs it must return the property to its pre-loss condition, and the cornices were restored exactly as they were before the fire.
Issues
- Repairs or contractors primary · not upheld“The FSP is not liable to rectify the cornices. The cornices were repaired to the same design as before the fire.”
- Claim amount dispute secondary · upheld“The FSP must pay the applicant further rent to increase the loss of rent payments to the 12 month policy limit.”
- Claim denial secondary · upheld“It is fair in the circumstances the FSP pay to the applicant $500 to repair the damaged section of the fence.”
- Third-party or outsourcing failure secondary · upheld“The FSP's builder did not consult with the applicant about his preference for the cornices, though this caused no loss.”
Subjects and remedies
home or building damagepay claimpay compensationpay interest
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 459264 Determination Page 1 of 9
Case number: 459264 16 March 2018
1 Overview
1.1 Dispute
The applicant held Landlord Insurance with the financial services provider (FSP). The
applicant lodged a claim with the FSP following a fire at the insured property. The
FSP accepted the claim and arranged for the property to be repaired.
The applicant disputes some of the repair work. The applicant says he specifically
asked the FSP to consult him throughout the rebuild of the property in regards to
choice in material, internal design and fittings. The applicant says the cornices were
repaired without seeking his approval. There are now two different types of cornices
throughout the house and he wants the FSP to rectify them so they are all square
cornices.
The applicant also says the FSP is liable for further loss of rent as well as damage to
his wooden fence. The applicant says it was the FSP‟s heavy vehicles which caused
the damage to the fence.
1.2 Issues and key findings
Is the FSP liable to rectify the cornices to square cornices?
The FSP is not liable to rectify the cornices. The FSP has repaired the cornices so
that they are the same as those which the applicant had prior to the fire. The FSP is
not required to update or modernise the property.
Is the FSP liable for damage to the applicant’s fence?
It is fair in the circumstances the FSP pay to the applicant $500 to repair the
damaged section of the fence.
Is the FSP required to pay the applicant further for loss of rent?
The FSP must pay the applicant further rent to increase the loss of rent payments to
the 12 month policy limit.
1.3 Determination
This determination is mainly in favour of the FSP.
Should the applicant accept this determination, then within 14 days, the FSP is to pay
to the applicant:
Case No: 459264 Determination Page 2 of 9
$500 to repair the fence
the remainder of the loss of rent up to the 12 month policy limit plus statutory
interest.
Case No: 459264 Determination Page 3 of 9
2 Reasons for determination
The case analyst issued a recommendation on the issues in dispute. The
recommendation was in favour of the FSP and found it was not liable for any further
repairs or loss of rental payments. As the applicant rejected the recommendation, the
issues in dispute has been referred to me for determination.
I have decided this case on the basis of what I consider fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous FOS decisions.
I have taken into account all the material submitted by the parties, both before and
after the recommendation. I am satisfied that the documentation I have relied on has
been provided to both parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
Submissions and material provided after the recommendation
The applicant rejected the recommendation and provided exte nsive submissions and
material as to why he says the FSP is liable to replace the cornices, indemnify him
for the damage to the fence and pay lost rent.
In relation to the cornices, the applicant says:
the house has not been rebuilt „like for like‟ on ma ny aspects and therefore the
argument that the cornices were installed like for like is flawed
it is unreasonable to say he has the onus to inform the builder he wanted
different cornices because it is normal building practice the owner be consulted
on such things
it is not logical for the applicant to expect the builder would put two types of
cornices in
he is residing in a different State and therefore consultation was essential
the issue could have been easily resolved if the FSP or builder had consulted.
The applicant‟s submissions have been considered in making this determination.
2.1 Is the FSP required to rectify the cornices?
The applicant requested to be consulted about material, design and fittings
The applicant says his dispute is specifically about his request to be consulted in
relation to the rebuild of his property.
The applicant has provided correspondence between the parties which show on 24
May 2016 he requested that he be consulted in relation to any decision made such
as choice of material and internal design and fittings.
The FSP responded on 25 May 2016 advising the builder will ensure the applicant is
contacted when any selections are required.
Case No: 459264 Determination Page 4 of 9
The applicant was not consulted about the cornices
The FSP‟s builder provided the applicant with a scope of works before the re -build
was approved. The scope of works show the cornices were to be repaired however it
does not detail what sort of cornices would be installed in what rooms or areas of the
house. The applicant had made notations on the cover page of the scope of works
advising he wants the opportunity to have an input for the choice of fittings.
I accept the FSP‟s builder was on notice that he was to consult the applicant about
choice of material, fittings and internal design.
The FSP‟s builder did not consult with the applicant about his preference for the
cornices. The builder repaired the cornices so that the bathroom had square cornices
and the remainder of the house had curved cornices.
The applicant says the builder did consult him on many things and he is happy with
most of the repairs. However he was not consulted about the cornices and it was not
logical for him to expect the builder to put two types of cornices in.
The cornices have been repaired to how they were before the fire
The difference in cornices in the house was not because of a mistake of the builder
or FSP but because that is how the cornices were installed before the fire. The
cornices were repaired to the same design as the applicant previously had them.
Therefore I do not agree with the applicant‟s comment that it was not logical for the
builder to install two types of cornices.
The purpose and objective of insurance is to place the insured in the position they
were in before an insured event caused damage. The policy allows the FSP to cash
settle or authorise repairs to the damaged property. Where the FSP authorises
repairs it has an obligation to return the property to the condition it was in before the
insured event occurred. However the law accepts that it might not always be possible
to do so.
In this instance, the cornices have been installed in exactly the same way they were
before the fire. It was entirely reaso nable for the builder to repair them this way. In
fact it is the FSP‟s obligation to do so.
The applicant argues that it is usual building practice for the owner of a property to be
consulted on such things. I agree this would be the case if the applicant had engaged
the builder himself. However in these instances the builder is engaged by and
responds to the FSP. The FSP can exercise its own discretion in deciding whether it
will authorise the builder to repair things differently or modernise fittings at t he
applicant‟s request. If it chooses not to, but still repairs the cornices to how they were
pre-fire, the FSP has discharged its obligations in regard to the repair of the cornice.
There has been no loss to the applicant
Moreover, the FSP‟s failure to co nsult the applicant about the cornices has not
resulted in a loss to the applicant.
The FSP has provided information to establish the square cornices are a higher cost
in material and labour. This means if the FSP had installed them throughout the
Case No: 459264 Determination Page 5 of 9
house the applicant would have been required to meet the additional cost at his own
expense. I accept that the applicant may have agreed to meet the cost of installing
the square cornices throughout the property. However if the fire had never occurred
the applicant would have had to outlay the same cost, if not more, to have the
cornices re-installed throughout the house if he was concerned about the two
different types of cornices.
It cannot even be said that the applicant has missed an opportunity to have the
cornices re-installed as one cornice type throughout the property. This is because the
FSP has offered to re-install all cornices as curved cornices. The applicant rejected
this offer.
The applicant has been placed in exactly the same position he was in, i n regards to
the cornices, prior to the insured event. The FSP has not made an error in the
circumstances and is not required to take any further action in relation to the
cornices.
2.2 Is the FSP liable for damage to the applicant’s fence?
The applicant’s ne ighbour says the repair work damaged the fence
The applicant‟s neighbour provided a photograph of the shared fence which shows it
has been pushed out of shape near the front of the driveway and was encroaching
on his property. The applicant‟s neighbour say s the damage was caused during the
rebuild of the applicant‟s property when the FSP‟s builder used heavy vehicles on the
driveway causing earth subsidence and movement of the fence.
The applicant‟s neighbour also says prior to construction, this segment o f the fence
was “quite plumb and in good condition.” He says he first noticed the fence had
moved slightly at the end of July and, later in the year, the movement became more
substantial at which time he raised his concerns with the applicant. I note the FSP
advised repairs were completed in December 2016.
The FSP reviewed photographs taken of the property when the builder first attended
to complete assessment of the property. It says the photographs show the condition
of the fence prior to the works been completed. It says the fence was deteriorated.
The FSP suggests the neighbour‟s “large enclosure” may have been holding the
fence up. It submits the neighbour‟s yard is lower than the applicant‟s yard and as
there is no retaining wall or bracing to account for the level of land it submits the
fence is going to lean in on the lower side of the land. It submits if the fence was in
good condition it would have withstood heavy vehicles using the driveway.
It relies on the policy terms which say that it does not cover damage caused by
gradual deterioration or failure to keep the property in good repair and condition.
The applicant accepts his fence was not new at the time however maintains the FSP
is liable for the damage to that particular section of his fence.
Case No: 459264 Determination Page 6 of 9
Fair in all the circumstances the FSP pay $500 to the applicant
When it first denied the claim, the FSP relied on photographs taken of the property
when the builder first attended to complete assessment of the property. It says these
photographs show the condition of the fence which was deteriorated already. The
photographs are date stamped 3 March 2016. I accept the fence is deteriorated but
the photographs do not clearly show the area where there is a bow in the fence seen
in the applicant‟s neighbour‟s photograph.
On the available information it is impossible to show the damage was caused by the
FSP‟s vehicles. The applicant has provided a photograph of his fence when it was
not damaged but it is not date stamped.
Taking into account all the available information and in particular the material from
the applicant‟s neighbour, I am persuaded on the balance of probabilities, while the
fence was not in good condition before repairs commenced, nonetheless, it was
plumb as described by the applicant‟s n eighbour.
I also accept had the fence not been deteriorated, it is unlikely it would have been
damaged in the course of repairs. Nonetheless, taking all matters into account, I
consider is fair in the circumstances the FSP make some contribution to repair the
segment of the fence at the front of the property which is bowed. I have taken into
account the fence was already deteriorated. I have also taken into account the
neighbour‟s applicant is responsible for 50% of the cost of repairs of this segment of
the fence.
I am satisfied it is fair in the circumstances the FSP pay $500 to the applicant to
repair this segment of the fence.
2.3 Is the FSP required to pay the applicant further for loss of rent?
The policy provides for loss of rent
The applicant describes a number of issues which are still to be completed in relation
to the rebuild and repairs. Due to the present condition of the property, he says he
cannot advertise or lease the house. He says the FSP should continue to pay for loss
of rent until repairs are complete.
The policy covers the rent lost during the reasonable time it would take to repair or
rebuild the property. However, there is a limit to the amount of lost rent that will be
paid. The policy states the FSP will only pay the benefit up to 12 months from when
the listed event, the fire, took place.
The FSP says it has paid loss of rent up to 31 January 2017 despite the repairs being
completed in December 2016 and therefore it has met its policy obligations.
The repairs are not finished
I do not agree the rebuild and repairs have been completed. The FSP has cash
settled the applicant for outstanding repairs which confirms repairs are not complete.
Additionally, the applicant has provided photographs of the property showing repairs
are not completed and it is not ready to lease.
Case No: 459264 Determination Page 7 of 9
The FSP says it could not complete repairs because of the dispute about the
cornices. I accept this may have been the case for painting and plastering. However
the material provided establishes there are a number of other things outstanding
which could have been completed while the dispute was ongoing.
The FSP should pay loss of rent up to 12 months
Considering the rebuild and repairs are not finalised it is fair in the circumstances the
FSP provide the applicant further loss of rent pursuant to the policy terms.
The FSP says it has paid approximately $18,000 in loss of rent in accordance with
rent being $1,781 monthly. This works out to be just over 10 months‟ rent.
The repairs have taken well over 12 months and it is fair in the circumstances the
FSP should pay loss of rent up to the 12 month policy limit.
If the applicant accepts this determination the FSP is to pay the applicant the
remainder of loss of rent benefits under the policy up to the 12 month limit within 14
days of acceptance of the determination.
The FSP is also required to apply interest to the balance of loss of rent from 26
February 2017 until payment in accordance with the Insurance Contracts Act 1984 .
Case No: 459264 Determination Page 8 of 9
3 Supporting information
3.1 FOS Approach
It is an accepted principle of general insurance law that an insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss
3.2 Relevant policy extracts
Product disclosure statement (PDS)
Section and page Extr act
What we pay for –
Buildings Insurance
Page 41
How we settle your buildings claim
We will choose to settle your claim for loss or damage to your
rental property or „other cover‟ in one of the following ways:
1. Arrange for repairers, builders and suppliers to repair or
rebuild your rental property.
If you agree, we can arrange for our preferred repairers,
suppliers or builders to repair or rebuild your rental property.
2. Pay you the reasonable cost to repair or rebuild your
rental property.
We can choose to:
pay you
pay your nominated repairer, supplier or builder, or
provide you with store credits from one of our nominat ed
suppliers.
3. Pay you the buildings sum insured
We may do this when we consider your rental property to be a
total loss or wh en we choose to do so.
Other Cover –
Buildings Insurance
Page 27
Loss of rent during repairs
If a listed event causes loss or damage to your rental property
and we agree your tenants can't live in it and need to move out
so it can be repaired or rebuilt.
Covered under Buildings Insurance
the rent you lose during the reasonable time it should take to
repair or rebuild your rental property.
We pay the rent you los e for the reasonable time we agree it
should take to repair or rebuild your rental property for up to 12
months from when the listed event took place .
Case No: 459264 Determination Page 9 of 9
3.3 Other relevant material considered and relied on
Parties‟ submissions and all attachments to all submissions both before and
after the recommendation including reports and emails.
Correspondence between the parties.
Photographs from the parties.
The applicant‟s reasons for rejecting the recommendation.