Determination 459264

Scope of fire repairs to cornices, fence damage and loss of rent

FirmFinancial Firm (Unknown - Insurer)
Decided2018-04-19
ProductGeneral Insurance · Landlord
OutcomeFor the complainant in part
Amount awarded$500
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

After a fire, the landlord disputed cornice repairs, fence damage and loss of rent. AFCA declined to order cornice rectification, ordered $500 towards the fence, and ordered the remaining loss of rent up to the 12-month limit with interest.

Where an insurer authorises repairs it must return the property to its pre-loss condition, and the cornices were restored exactly as they were before the fire.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 459264 Determination Page 1 of 9 Case number: 459264 16 March 2018 1 Overview 1.1 Dispute The applicant held Landlord Insurance with the financial services provider (FSP). The applicant lodged a claim with the FSP following a fire at the insured property. The FSP accepted the claim and arranged for the property to be repaired. The applicant disputes some of the repair work. The applicant says he specifically asked the FSP to consult him throughout the rebuild of the property in regards to choice in material, internal design and fittings. The applicant says the cornices were repaired without seeking his approval. There are now two different types of cornices throughout the house and he wants the FSP to rectify them so they are all square cornices. The applicant also says the FSP is liable for further loss of rent as well as damage to his wooden fence. The applicant says it was the FSP‟s heavy vehicles which caused the damage to the fence. 1.2 Issues and key findings Is the FSP liable to rectify the cornices to square cornices? The FSP is not liable to rectify the cornices. The FSP has repaired the cornices so that they are the same as those which the applicant had prior to the fire. The FSP is not required to update or modernise the property. Is the FSP liable for damage to the applicant’s fence? It is fair in the circumstances the FSP pay to the applicant $500 to repair the damaged section of the fence. Is the FSP required to pay the applicant further for loss of rent? The FSP must pay the applicant further rent to increase the loss of rent payments to the 12 month policy limit. 1.3 Determination This determination is mainly in favour of the FSP. Should the applicant accept this determination, then within 14 days, the FSP is to pay to the applicant: Case No: 459264 Determination Page 2 of 9  $500 to repair the fence  the remainder of the loss of rent up to the 12 month policy limit plus statutory interest. Case No: 459264 Determination Page 3 of 9 2 Reasons for determination The case analyst issued a recommendation on the issues in dispute. The recommendation was in favour of the FSP and found it was not liable for any further repairs or loss of rental payments. As the applicant rejected the recommendation, the issues in dispute has been referred to me for determination. I have decided this case on the basis of what I consider fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. Submissions and material provided after the recommendation The applicant rejected the recommendation and provided exte nsive submissions and material as to why he says the FSP is liable to replace the cornices, indemnify him for the damage to the fence and pay lost rent. In relation to the cornices, the applicant says:  the house has not been rebuilt „like for like‟ on ma ny aspects and therefore the argument that the cornices were installed like for like is flawed  it is unreasonable to say he has the onus to inform the builder he wanted different cornices because it is normal building practice the owner be consulted on such things  it is not logical for the applicant to expect the builder would put two types of cornices in  he is residing in a different State and therefore consultation was essential  the issue could have been easily resolved if the FSP or builder had consulted. The applicant‟s submissions have been considered in making this determination. 2.1 Is the FSP required to rectify the cornices? The applicant requested to be consulted about material, design and fittings The applicant says his dispute is specifically about his request to be consulted in relation to the rebuild of his property. The applicant has provided correspondence between the parties which show on 24 May 2016 he requested that he be consulted in relation to any decision made such as choice of material and internal design and fittings. The FSP responded on 25 May 2016 advising the builder will ensure the applicant is contacted when any selections are required. Case No: 459264 Determination Page 4 of 9 The applicant was not consulted about the cornices The FSP‟s builder provided the applicant with a scope of works before the re -build was approved. The scope of works show the cornices were to be repaired however it does not detail what sort of cornices would be installed in what rooms or areas of the house. The applicant had made notations on the cover page of the scope of works advising he wants the opportunity to have an input for the choice of fittings. I accept the FSP‟s builder was on notice that he was to consult the applicant about choice of material, fittings and internal design. The FSP‟s builder did not consult with the applicant about his preference for the cornices. The builder repaired the cornices so that the bathroom had square cornices and the remainder of the house had curved cornices. The applicant says the builder did consult him on many things and he is happy with most of the repairs. However he was not consulted about the cornices and it was not logical for him to expect the builder to put two types of cornices in. The cornices have been repaired to how they were before the fire The difference in cornices in the house was not because of a mistake of the builder or FSP but because that is how the cornices were installed before the fire. The cornices were repaired to the same design as the applicant previously had them. Therefore I do not agree with the applicant‟s comment that it was not logical for the builder to install two types of cornices. The purpose and objective of insurance is to place the insured in the position they were in before an insured event caused damage. The policy allows the FSP to cash settle or authorise repairs to the damaged property. Where the FSP authorises repairs it has an obligation to return the property to the condition it was in before the insured event occurred. However the law accepts that it might not always be possible to do so. In this instance, the cornices have been installed in exactly the same way they were before the fire. It was entirely reaso nable for the builder to repair them this way. In fact it is the FSP‟s obligation to do so. The applicant argues that it is usual building practice for the owner of a property to be consulted on such things. I agree this would be the case if the applicant had engaged the builder himself. However in these instances the builder is engaged by and responds to the FSP. The FSP can exercise its own discretion in deciding whether it will authorise the builder to repair things differently or modernise fittings at t he applicant‟s request. If it chooses not to, but still repairs the cornices to how they were pre-fire, the FSP has discharged its obligations in regard to the repair of the cornice. There has been no loss to the applicant Moreover, the FSP‟s failure to co nsult the applicant about the cornices has not resulted in a loss to the applicant. The FSP has provided information to establish the square cornices are a higher cost in material and labour. This means if the FSP had installed them throughout the Case No: 459264 Determination Page 5 of 9 house the applicant would have been required to meet the additional cost at his own expense. I accept that the applicant may have agreed to meet the cost of installing the square cornices throughout the property. However if the fire had never occurred the applicant would have had to outlay the same cost, if not more, to have the cornices re-installed throughout the house if he was concerned about the two different types of cornices. It cannot even be said that the applicant has missed an opportunity to have the cornices re-installed as one cornice type throughout the property. This is because the FSP has offered to re-install all cornices as curved cornices. The applicant rejected this offer. The applicant has been placed in exactly the same position he was in, i n regards to the cornices, prior to the insured event. The FSP has not made an error in the circumstances and is not required to take any further action in relation to the cornices. 2.2 Is the FSP liable for damage to the applicant’s fence? The applicant’s ne ighbour says the repair work damaged the fence The applicant‟s neighbour provided a photograph of the shared fence which shows it has been pushed out of shape near the front of the driveway and was encroaching on his property. The applicant‟s neighbour say s the damage was caused during the rebuild of the applicant‟s property when the FSP‟s builder used heavy vehicles on the driveway causing earth subsidence and movement of the fence. The applicant‟s neighbour also says prior to construction, this segment o f the fence was “quite plumb and in good condition.” He says he first noticed the fence had moved slightly at the end of July and, later in the year, the movement became more substantial at which time he raised his concerns with the applicant. I note the FSP advised repairs were completed in December 2016. The FSP reviewed photographs taken of the property when the builder first attended to complete assessment of the property. It says the photographs show the condition of the fence prior to the works been completed. It says the fence was deteriorated. The FSP suggests the neighbour‟s “large enclosure” may have been holding the fence up. It submits the neighbour‟s yard is lower than the applicant‟s yard and as there is no retaining wall or bracing to account for the level of land it submits the fence is going to lean in on the lower side of the land. It submits if the fence was in good condition it would have withstood heavy vehicles using the driveway. It relies on the policy terms which say that it does not cover damage caused by gradual deterioration or failure to keep the property in good repair and condition. The applicant accepts his fence was not new at the time however maintains the FSP is liable for the damage to that particular section of his fence. Case No: 459264 Determination Page 6 of 9 Fair in all the circumstances the FSP pay $500 to the applicant When it first denied the claim, the FSP relied on photographs taken of the property when the builder first attended to complete assessment of the property. It says these photographs show the condition of the fence which was deteriorated already. The photographs are date stamped 3 March 2016. I accept the fence is deteriorated but the photographs do not clearly show the area where there is a bow in the fence seen in the applicant‟s neighbour‟s photograph. On the available information it is impossible to show the damage was caused by the FSP‟s vehicles. The applicant has provided a photograph of his fence when it was not damaged but it is not date stamped. Taking into account all the available information and in particular the material from the applicant‟s neighbour, I am persuaded on the balance of probabilities, while the fence was not in good condition before repairs commenced, nonetheless, it was plumb as described by the applicant‟s n eighbour. I also accept had the fence not been deteriorated, it is unlikely it would have been damaged in the course of repairs. Nonetheless, taking all matters into account, I consider is fair in the circumstances the FSP make some contribution to repair the segment of the fence at the front of the property which is bowed. I have taken into account the fence was already deteriorated. I have also taken into account the neighbour‟s applicant is responsible for 50% of the cost of repairs of this segment of the fence. I am satisfied it is fair in the circumstances the FSP pay $500 to the applicant to repair this segment of the fence. 2.3 Is the FSP required to pay the applicant further for loss of rent? The policy provides for loss of rent The applicant describes a number of issues which are still to be completed in relation to the rebuild and repairs. Due to the present condition of the property, he says he cannot advertise or lease the house. He says the FSP should continue to pay for loss of rent until repairs are complete. The policy covers the rent lost during the reasonable time it would take to repair or rebuild the property. However, there is a limit to the amount of lost rent that will be paid. The policy states the FSP will only pay the benefit up to 12 months from when the listed event, the fire, took place. The FSP says it has paid loss of rent up to 31 January 2017 despite the repairs being completed in December 2016 and therefore it has met its policy obligations. The repairs are not finished I do not agree the rebuild and repairs have been completed. The FSP has cash settled the applicant for outstanding repairs which confirms repairs are not complete. Additionally, the applicant has provided photographs of the property showing repairs are not completed and it is not ready to lease. Case No: 459264 Determination Page 7 of 9 The FSP says it could not complete repairs because of the dispute about the cornices. I accept this may have been the case for painting and plastering. However the material provided establishes there are a number of other things outstanding which could have been completed while the dispute was ongoing. The FSP should pay loss of rent up to 12 months Considering the rebuild and repairs are not finalised it is fair in the circumstances the FSP provide the applicant further loss of rent pursuant to the policy terms. The FSP says it has paid approximately $18,000 in loss of rent in accordance with rent being $1,781 monthly. This works out to be just over 10 months‟ rent. The repairs have taken well over 12 months and it is fair in the circumstances the FSP should pay loss of rent up to the 12 month policy limit. If the applicant accepts this determination the FSP is to pay the applicant the remainder of loss of rent benefits under the policy up to the 12 month limit within 14 days of acceptance of the determination. The FSP is also required to apply interest to the balance of loss of rent from 26 February 2017 until payment in accordance with the Insurance Contracts Act 1984 . Case No: 459264 Determination Page 8 of 9 3 Supporting information 3.1 FOS Approach It is an accepted principle of general insurance law that an insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss 3.2 Relevant policy extracts Product disclosure statement (PDS) Section and page Extr act What we pay for – Buildings Insurance Page 41 How we settle your buildings claim We will choose to settle your claim for loss or damage to your rental property or „other cover‟ in one of the following ways: 1. Arrange for repairers, builders and suppliers to repair or rebuild your rental property. If you agree, we can arrange for our preferred repairers, suppliers or builders to repair or rebuild your rental property. 2. Pay you the reasonable cost to repair or rebuild your rental property. We can choose to:  pay you  pay your nominated repairer, supplier or builder, or  provide you with store credits from one of our nominat ed suppliers. 3. Pay you the buildings sum insured We may do this when we consider your rental property to be a total loss or wh en we choose to do so. Other Cover – Buildings Insurance Page 27 Loss of rent during repairs If a listed event causes loss or damage to your rental property and we agree your tenants can't live in it and need to move out so it can be repaired or rebuilt. Covered under Buildings Insurance  the rent you lose during the reasonable time it should take to repair or rebuild your rental property. We pay the rent you los e for the reasonable time we agree it should take to repair or rebuild your rental property for up to 12 months from when the listed event took place . Case No: 459264 Determination Page 9 of 9 3.3 Other relevant material considered and relied on  Parties‟ submissions and all attachments to all submissions both before and after the recommendation including reports and emails.  Correspondence between the parties.  Photographs from the parties.  The applicant‟s reasons for rejecting the recommendation.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.