Determination 457951

Claim declined for foundation underpinning after building movement; crack repair offered

FirmFinancial Firm (Unknown - Insurer)
Decided2018-03-22
ProductGeneral Insurance · Strata
OutcomeFor the complainant in part
Amount awarded$4,398
Non-financial loss—
Amount claimed$277,610
SourceAFCA PDF

Summary

A body corporate sought $277,610 to underpin a strata building after foundation movement and water leaks, and the FSP declined that part. AFCA found tree-related foundation settlement was the proximate cause, and ordered the FSP to settle the west wall crack repair and loss of rent and pay $4,397.50 in professional costs.

The proximate cause must be the dominant cause, and the foundation movement from tree drying and inadequate footings was excluded, while the burst hot water unit only contributed to the initial movement.

Issues

Subjects and remedies

home or building damagepay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 457951 Determination Page 1 of 11 Case number: 457951 22 March 2018 1 Overview 1.1 Dispute The applicant is a body corporate. It held a strata insurance policy with the Financial Service Provider (FSP). In January 2015 a hot water unit burst causing inundation of the foundations. In February 2015 cracking was noticed at Unit 3 in the development. In April 2015 the applicant informed the FSP in an email of the severe cracking. In December 2015 the applicant lodged a claim with the FSP for the damage. The FSP has offered to indemnify, on a commercial basis, the cost of the repair of the cracking to the west wall but declined the claim for the remediation of the building movement caused by the movement in the foundations. The FSP says the proximate cause of the damage is tree root invasion and gradual deterioration which is excluded from cover and was not due to the burst hot water service. 1.2 Issues and key findings Is the FSP entitled to decline the claim? The panel accepts that the proximate cause of the damage is due to the normal settling, creeping, heaving, seepage, shrinkage or expansion in the foundations and footing due to the presence of trees causing a drying or shrinkage of the foundation soils. I n the circumstances the Panel finds that the FSP’s offer to settle the claim for the repair of the cracking to the west wall and loss of rent during this process, subject to the rectification of the footings is fair and reasonable. The FSP’s offer to pay the applicants professional costs of $4397.50 is fair in the circumstances 1.3 Determination This determination is in favour of the FSP. The FSP is to settle the applicant ’ s claim for the repair of the cracking of the west wall and loss of rent during this repair process subject to the applicant completing the rectification of the footings. The FSP is otherwise entitled to deny the applicant’s claim in accordance with the terms of the policy. The FSP is to pay the applicant ’ s professional costs incurred of $4397.50 Case No: 457951 Determination Page 2 of 11 2 Reasons for determination 2.1 Is the FSP entitled to decline the claim? Applicant wants the FSP to repair building movement damage Both parties accepts that a hot water service burst on or around 12 January 2015. Both parties also accepts structural settlement to western side wall had occurred. Photos provided show the cracking to the internal and external building walls. The applicant says the owner of unit 3 reported the cracking damage to her unit on 20 February 2015. The applicant says water from the burst hot water service saturated the ground soil, which in turn caused structural settlement of the building. The applicant wants the FSP to pay for the cost to repair the building movement damage. It has provided a building quotation (MA, dated 1 June 2017), which included works for: Item Cost (ex - GST) Remove concret e from side pathway to underpin foundations $ 7,653 Excavate and underpin foundations and remove excess soil. (Provisional Sum, require final engineer specification ) $ 85,750 Remove existing plumbing from external wall and wat er meters and isolate electrical wiring in cavity wall $ 9,200 Erect Scaffolding. $ 9,600 Remove external face of brickwork and relay. $ 37,500 Repair plasterwork to internal of walls after underpinning, paint, repair cracked tiles and repair to all internal areas after underpinning and paint externally windows. (Estimate only, do not know extent of repairs till underpinning completed.) $ 92,350 New concret e to side pathway after repair works $ 8,600 Remove clotheslines and re - fit $ 400 Reinstall new eaves $ 1,320 MA’s quotation totalled $277,610.30 (including GST). The applicant has the onus of proving the damage was accidental The policy covers the applicant ’s property for accidental loss or damage. ‘Accidental’ is not defined in the policy, therefore an ordinary meaning is taken; an accident is a happening which is unforeseen and unintended by the applicant. There is no dispute that the damage was unintended and unforeseen. According to the information provided Unit 3 had been fully renovated in November 2014. In this Case No: 457951 Determination Page 3 of 11 sense the damage to the property was accidental and therefore falls within the broad cover provided by the policy. The key issue in this dispute is whether the movement damage to the building was the result of a burst hot water service or due to other issues that are specifically excluded from cover under the terms of the policy. That is, what was the proximate cause of the damage? The building movement damage likely due to ongoing site condition The proximate cause of damage is the dominant or effective cause of the damage. . It is not necessarily the first or last or the sole cause of the loss. If one cause would have caused the harm in any case and the other would not have done so in the absence of the first then then first is the proximate cause. Both parties have provided extensive reports on the cause of the building movement damage. Having considered all the information available, the panel accepts water from the burst hot water service may have contributed to the building movement. However, the panel does not accept the leaking hot water system as the dominant and operative cause of the damage. The panel’s view is that the proximate cause of the building damage was due to the ongoing issues with the building site, which pre- existed the burst water service event on 12 January 2015. It is not in dispute the building has a history of movement damage and water leaks. This was confirmed by the applicant’s ori ginal engineer (SJ). Further water leaks were also identified by the applicant’s structural engineer (RB) and geotechnical engineer (GA). It is apparent that the building had suffered prior structural movement in 2008. The front wall was underpinned. SJ found widespread cracking in September 2009. SJ says the remedial work (jacking, lifting, wetting of soil) done in 2010 was successful, however the fundamental cause of the building movement is that the footing that support the building was not adequate to cope with the unstable foundation soil. He believes the remedial work undertaken, and any future remedial work will not address further movement damage unless the inadequacy of the footings is addressed. There is no information available that show the applicant undertook work to remedy the building’s footings. The issue with the unstable foundation soil is also confirmed by the applicant’s geotechnical engineer (GA). GA found the building was built on extremely high plasticity clay, which will undergo appreciable volumetric change with changes in moisture content. GA says the building movement damage observed is consistent with site experiencing significant volumetric change beyond what is accommodated by the building structure. GA also took soil samples and found elevated moisture content below the ground surface. He says this strongly suggest there may be other leaking pipes in the area allowing water into the reactive clay soil underneath the building structure. Case No: 457951 Determination Page 4 of 11 CEL, a consulting geotechnical and foundation engineer was engaged by the applicant. Whilst initially associating the increased movement to heave due to the leaking hot water system, CEL concluded the patterns of movement was a result of tree drying settlement rather than the water leak FSP entitled to decline the claim Having reviewed all of the exchanged material, the panel is satisfied that the proximate cause of the building movement was the movement in the foundations caused as a result of the settling, seepage or expansion of the foundations and footings. Such damage is excluded from cover under the terms of the policy. The panel accepts that there may have been some initial movement due to the leaking hot water system. The panel accepts the offer by the FSP to pay the cost to repair the cracking of the west wall and pay loss of rent during this repair subject to the applicant completing the remediation of the foundations and footings fair in the circumstances. The panel is also satisfied the FSP’s offer to settle the applicants claim for professional costs of $4397.50 fair in the circumstances. The panel is satisfied the FSP is otherwise entitled to deny the applicant’s claim. Case No: 457951 Determination Page 5 of 11 3 Supporting information 3.1 FOS approach to this determination This case has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues which are considered directly relevant to the outcome only. The applicant is a body corporate. It is represented by the body corporat e’s manager (MS) and unit owner (VC). For simplicity, this determination will refer to submissions made by them as if they had been made by the applicant. 3.2 Key records Record Key points Applicant’s engineer ( SJ ) Report 15 - 05 - 2015  The building has a history of damage and repair work . Front wall underpinned in 2008  25 Sep 2009 assessed widespread cracking and movement observed at that time, and recommended remedial action  2010 a root barrier was installed along both sides and at the rear of the property, to protect from neighbouring trees. Concret e paving on bot h sides and at the rear was re - constructed, to seal against water ingress and evaporation, and so furt her contribute to soil moisture stability.  It is reported that cracking has occurred recently along the west side (Zone 3).  On 24 April 2015, the whole of the exterior of the building was inspected, and Zone 3 was inspected inside. Zones 1 and 2 were in good condition, as inspected after the remedial works.  In Zone 3, there was signific ant cracking (Photos A to C), and the exterior wall ha d a considerable dip (Photo D). This approximated the settlement observed in 2009 before remedial works (or slightly wors e). The damage is Cat egory 3 (moderate) bordering on Category 4 (severe) in accordance with AS 2870 Residential Slabs and Footings 2011 . Figure 2 shows a profile along the west wall. Levels now are much the same as observed in 2009, before remedial works.  It is apparent that both Units 3 and 4 had been repaired and re - painted, and that there had been new settlement and cracking aft er the re - painting. The evide nce suggests that the zone under went some recovery and lifting during the re - wetting process in 2010, Case No: 457951 Determination Page 6 of 11 but recently has subsided again.  likely that recent localised drying has occurred, causing new sinkage and settlement. A likely caus e is the row of trees in the ad joining proper ty, near the western side, suggesting that the root barrier was not effective. If so, then reconstruction of the root barrier to a greater dept h, or construction of a new root barrier along the western side, wil l be required. There is no apparent reason for the root barrier to have been ineffective.  Another possibility is poor - quality foundation soil, perhaps disturbed or loose fill. This would possibly require underpinning along the western side. In fact, the ca use is not readily apparent, and more investigation is required.  It is recommended that several test holes be excavated along the western side. They should be done so as to enable a soil investigation for diagnosis, and also to serve as re - wetting holes if appropriate. The investigation should determine the type of soil, its condition in regard to disturbance and bearing capacity, its moisture content, and the presence or absence of tree roots.  The holes should be backfilled with 5 mm screenings, and capped with a PVC pipe and cap, to facilitate their use for re - wetting if required.  Remedial works might include re - wetting, construction of a deeper root barrier , and/or underpinning. It might even be appropriate to monitor the building without any works, to se e if the structure stabilises. This will require assessment and design b y a civil engineer.  The remedial works in 2010 were in the main successful. However, the fundamental cause of the damage is that the footings supporting the building, although typical of building practice at the time, are not adequate to cope with the unstable foundation soil. The remedial works undertaken, and any future works, are in the nature of piecemeal repairs, and do not fully overcome the fundamental weakness of the building, b eing the inadequacy of the footings. It is considered that remedial works, both past and future, are well justified; and it is probable that the building will be serviceable and cracking will be manageable. However, there is no certainty of the success of remedial works, and some fut ure movement is likely. Applicant’s geotechnical engineer (CEL) Report 30 - 09 - 2015  Internally slight to moderate plaster cracking and door frame distortion was observed in the distressed area of the building. Externally there is moderate brickwork deflection.  A vertical barrier around the entire complex was installed in mid - 2010 . All pi pe work was checked and where necessary replaced and/or repaired about the same time.  Rehy dration holes were also installed and kept well watered. Over time the building showed some signs of recovery. The watering of these holes were terminated in 2012.  Fr om 2012 to early this year the building appeared to be in a stable condition. However, in January 2015 the hot water servic e to the rear of the complex burst and was not repaired for two days. Case No: 457951 Determination Page 7 of 11 Further distress began to appear in early March. It does not se em to have changed over recent months.  Given the history of the building it would appear the most recent distress is associated with heave of the soil following the hot water system leakage. This is further evidenced by the fact that the distress does not appear to have changed much over the last few months.  Given the hot water service has been repaired and all the other possible moisture change issues have been checked repaired there is no further works required at this stage. It is recommended that the cu rrent distress be regularly monit ored. In about February 2016 the site should again be inspected and further levels taken over the floor. Additional levels should then be taken at six monthly intervals until they show that the soil movements beneath the fo otings have stabilized.  Having established that the soil movements have stabilized the following remedial action is likely to be required;  Any remaining superstructure distress should be cosmetically repaired. Minor brickwork cracking should be repaint ed a s necessary, more severe brickwork distress may need to be broken out and replaced. All internal plaster cracking should be reinforced with plaster's gauze. Minor internal cracking may be hidden by the extensive us e of flexible wall papering.  Although a ve rtical barrier has been installed around the site it appears to be only 1200mm deep. The line of James Stirling Pittosporum trees to the west of the site are not causing an issue to date it will be nec essary to regularly check the west side of the building for possible tree drying settlements. If drying settlements occur then this company should be contacted to determine a course of action.  It is stressed at this point that a final assessment of the actual rectification measures required can only be made af ter the distress in this building has stabilised. FSP’s assessor (ASTA) Report 29 - 01 - 2016  there is extensive external and internal cracking to the west wall of the insured property effecting units three and four, which are located side by side along the west side of the building. FSP’s assessor (ASTA) Report 9 - 2 - 2016  there is extensive and widespread cracking up to 50mm which can be seen in the photographic schedule enclosed. At some stage the cracking will require re - patching of the plaster and redecor ating. Applicant’s geotechnical engineer ( CEL ) Letter 1 - 0 2 - 2016  Mid 2010 a vertical barrier to the west side was installed. All pipe work was checked and repaired as required and rehydration commenced. Rehydration continued with some recovery in the level of distress becoming evident. The rehydration was discontinued in 2012 with going ongoing performance until early 2015. The building began to show signs of new distress in February 2015 following a leak in the hot water servic e in late 2014.  September 2015 [CEL became involved again] to ascertain a Case No: 457951 Determination Page 8 of 11 possible cause of the most recent distress. Up until this date the building appeared to be in stable condition.  Late December 2015 a further leak in the hot wat er service occurred. This resulted in further movement to occur in the vicinity of unit 3 and 4 (both adjacent to the hot water system). This new distress made the diagnosis of the original cause more difficult. G eotechnical engineer ( CEL ) Letter 17 - 02 - 2016  Internally furt her moderate to sev ere cracking has appeared in unit 3 and 4. No issues with water leaks have occurred since our previous visit, however a gas leak has occurred to unit 3 .  As can be seen from Figure One no further heave has occurred to the rear of unit 4 adjacent to past lea king water pipe. However, significant settlement has occurred to the junction between unit 3 and unit 4.  The footing at this location was exposed during this investigation and revealed a conc rete footing approximately300 mm deep founded at a depth of appr oximately 700mm. The footing is founded on approximately 300 mm of fill material. Tree roots were noted in the soil beneath the footing. These roots would suggest this further movement is in fact related to tree drying settlements over the dry summer perio d. FSP’s assessor (ASTA) Claims decision letter 2 - 3 - 2016  the leaking pipe does not appear to be the caus e of the further movement, though it most likely contributed to the initial movement over the end of 2014. However, the extent of the damage to the bu ilding, whic h now appears to require underpinning, would not have occurred but for the prevailing tree root issues.  it appears that accidental damage to a water pipe has caused resultant damage to the building in the form of cracking both internally and ex ternally to Units 3 and 4.  It is considered that the underpinning would not have been required but for the tree root invasion (tree drying settlements) and on that basis, the claim for costs related to the underpinning is declined.  However, coverage is ext ended to the cost of repairing the cracks to the building on the basis that the proximate cause was due to a leaking pipe in lat e 2014. This cover is granted conditional upon the Insured first attending to the underpinning of the property. Applicant’s geo technical engineer ( CEL ) Letter 13 - 04 - 2016  The magnitude of the cracking has significantly increased over the dry summer month of late December and January, approximately three to four weeks after the repair of the second leak event. This pattern of movement would suggest that the cause of the more recent cracking is a res ult of tree drying settlement rather than as a result of the wat er leak.  If the cause of the original and most recent cracking was a result of the water leaks only, it would have been expected that once the leaks were repaired, th e soil moisture change in the soil would stabilise. Once the soil moisture content has stabilised generally no further distress occurred.  Having confirmed stabilisation any remaining distress could then be repaired. Unfortunat ely, the observed pattern of distress over Case No: 457951 Determination Page 9 of 11 the last three months does not indicate this scenario. Applicant’s geotechnical engineer ( GA ) Report 26 - 08 - 2016  Geotechnical investigation report of footing movement  The structural distress observed within the subject structure is consiste nt with movements caused by footing movements.  The subject site is underlain by extremely high plasticity clay, which undergoes appreciable volumetric change with changes in moisture content. Upon wetting the clays swell appreciably and conversely upon dry ing, the clays shrink. Under normal conditions, where there are no appreciable external wetting or drying influences, a structure, which is constructed on a standard footing arrangement, will largely accommodate the anticipated volumetric changes, which ty pically occur within the clay bet ween summer and winter. However, the volumetric changes that have occurred at the subject site have signific antly exceeded those able to be accommodated by the subject structure, resulting in the observed footing movements and associated structural distress.  In accordance with Australian Stand ard 2870 – 2011, ‘Residential Slabs and Footings’, the site is located within Climatic Zone 3, where seasonal variation of temperature, humidity and rainfall influence the moisture cond ition of the soil profile to a depth of at least 2.3 metres below the existing ground surface. External factors will influence the moisture condition to greater depths. This is demonstrated by the significant variations in the moisture content of the clay both bet ween the boreholes and with depth in individual boreholes.  Based on the observed site conditions and the results of the tes ting carried out, the following factors are likely to have significantly influenced the performance of the footings providing support to the subject structure:  The presenc e of significantly elevated moisture contents within the boreholes to dept hs in excess of 2.5 metres below the existing grounds surface strongly suggest that there may be one or more leaking pipes within the su bject area of the site that is allowing uncontrolled ingress of moisture into the reactive clay soils underlying the subject site.  As detailed in Section 3. 1 of this this report, there has been ongoing history of burst and leaking pipes at the subject site . The leak from the pipe connecting to the hot water meter unit along the west side of the building was identified to be leaking at the time of the site investigation. The pipe had been leaking for at least six months prior to th e site investigation, possi bly much longer.  The exact effects of the burst hot water unit on the subject building are difficult to quantify without the benefit of having to be able to measure/obs erve the site conditions both before and after the hot water unit burst in January 2015. However, the water from the burst hot water unit at the south west corner of the building it is likely to have resulted in additional uncontrolled ingress of moisture into the clay founding stratum along the west side of the subject building. Such ingress of moisture would have contributed to the foundation related movements within the subject building. Case No: 457951 Determination Page 10 of 11  Given the age of the building and the amount of foundation related movement that has taken place, there are likely to be additional pipes at the subject si te that are leaking and allowing uncontrolled ingress of moisture into the clay founding strat um. It is also quite possible that pipes connecting to the dwellings on the adjacent properties are leaking and cont ributing to the elevated moisture content of the clay founding stratum underlying the subject site.  The numerous trees on the adjacent properties and particularly along the west side are likely to have contributed to additional ground moisture varianc e after the pipe burst.  The 1.2 met re deep root ba rrier that was installed along the west side of the building in 2010 is not of sufficient dept h to eliminate the drying effects of the row of trees on the neighbouring property to the west of the site.  The resultant damage to a building that is founded on a high plasticity clay founding strat um, from a moisture source that is that is intermittent or temporary (e.g. stormwater related, burst pipes etc.) is typically more severe than for a source of moisture ingress that is consistent, particularly when combi ned with the drying effects of nearby trees. For example, a leaking pipe that is repaired in late winter or early spring after it has been leaking for several months will allow appreciable ingress of moisture into the clay founding stratum during a period when the moisture demands from the adjac ent trees are minimal. The moisture demands of the nearby trees during the following summer period when rainfall levels are typically low and evaporation levels are high, will significantly contribute to the drying a nd shrinkage of the clay founding stratum, resulting in appreciable settlement of footings. Cyclical wetting and drying of clay is notoriously problematic in that footing settlement and cracking of the superstructure typically increase upon each drying cyc le. Applicant’s structural engineer ( RB ) Letter 26 - 08 - 2016  RB undertook a structural inspection of the perimeter of the building 16th March 2016 and also inspected the internal structure of unit 3 and the rear south western corner services room. Please re fer to attached photos dat ed 16th March 2016.  Following our ins pection RB briefed a geotechnical engineer (GA Geotechnical Engineers ) to undertake a soil report and soil moisture tests as per attached report from G A dated 26th  August 2016. These field work s were undertaken on 25th May 2016. Our review of this report confirms highly elevated moisture levels in the ground were still present along the western boundary which was the likely result of the burst water service several months earlier and potentially some ongoing less significant water service leaks. Our understanding is that even though the burst pipes were repaired, the saturation levels had reached a point where the drying process would take a signific ant amount of time to occur within these highly reactive clays. As a r esult settlement issues have clearly occurred as is evident from the substantial cracking of the building which had occurred shortly after thes e pipe burst events taking plac e. Refer to attached photos that clearly Case No: 457951 Determination Page 11 of 11 indicate a severe level of damage to the load bearing structure.  Based on the information available to R B for this review and opinion, we believe this damage has resulted from the extreme variance to moisture levels along this boundary within these highly reactive clays and it is our professional opinion this cracking was initiated by the burst water service saturating the reactive clay. We also recommend that all servic es should be re - checked for any ongoing lea ks and repaired as soon as possible in an attempt to help stabi lise the moisture regime along the western boundary as soon as possible.  Some repair guidanc e is provided in the soil report by G A and will comprise of a combination of continuous underpinning with the necessity for some sections of brickwork and footings to be completely removed and reconstructed. The structural design, specification and certification for building permit of the remediation measures proposed, would need to be undertaken following a more detailed structural analysis of the building and footi ng loads subject to the attached geotechnical rec ommendations. We suggest this is the next stage of the design process. Applicant’s arborist (AT) Letter 19 - 12 - 2016  James Sterling pittosporum tennuifolium [insured address]  This species characteristically has a small root system for the size of t he tree. They are a tall upright growing tree but the root systems are usually shallow and compact. This often leads to the tree becoming lose in the ground and toppling over.  the roots are non - invasive and lack the potential to do damage to buildings and pathways. Applicant’s builder ( MG ) Quotation 1 - 6 - 2017  Quotation for $277,610. 30 including GST.