Debt recovery action while customer in financial difficulty and construction funding delays
Text of the determination
Determination
Case No: 456073 Determination Page 1 of 8
Case number: 456073 3 March 2017
1 Overview
1.1 Dispute
The Applicant has a construction loan with the Financial Services Provider (FSP) to
purchase and build an investment property. The Applicant says that the builder
caused delays in finalising the construction and he has commenced legal
proceedings against the builder to recover his losses.
The Applicant also says the FSP:
reduced funds available in the construction loan
unreasonably delayed the final progress payments to the builder and
did not meet its obligations to him as a customer experiencing financial difficulty
and caused the deterioration of his financial position.
For this reason, the Applicant says it is unconscionable for the FSP to pursue debt
recovery action before his legal action against the builder concludes.
1.2 Issues and key findings
Did the FSP unreasonably delay the final payment to the builder?
The FSP applied interest to the construction loan account in accordance with the
loan contract. As the Applicant was not making repayments, the increasing loan
balance reduced the funds available to complete construction.
The FSP‟s initial decision to decline further funding was a credit risk assessment
decision about lending that FOS does not have the jurisdiction to review under its
Terms of Reference.
The FSP eventually provided the requisite funding, however it should have kept the
Applicant better informed about his options at the time, and the FSP caused a short
delay in making the final payment.
Did the FSP cause the Applicant’s financial loss?
The Applicant has not shown that any delay by the FSP caused his financial loss.
The Applicant has instead pursued damages from the builder for loss of rental
income caused by its delay. Even if he did show the FSP caused some loss arising
from the delay, the remedy is not to require the FSP to put an indefinite hold on
recovery action.
Case No: 456073 Determination Page 2 of 8
Has the FSP complied with its obligations to the Applicant as a customer in
financial difficulty?
The FSP held off from starting legal proceedings for two years to allow the Applicant
to pursue legal proceedings against the builder. By the time the FSP commenced
legal action, the Applicant ‟s combined loans had exceeded their approved credit
limits by over $300,000 and he had made only one repayment to the loan account.
The FSP issued defective default notices in April 2016 and should refund to the
construction loan the associated costs.
1.3 Determination
This determination is substantially in favour of the FSP.
If the Applicant accepts the determination in full and final resolution of the dispute:
The FSP should refund a total of $205.56 to the construction loan (#6502) in
relation to the defective default notices issued in April 2016.
Within 14 days of accepting the determination, the Applicant should put forward
to the FSP a reasonable repayment plan in relation to the arrears and his loan
obligations. The FSP is not obliged to accept it but should work with the
Applicant to try and assist him and should consider any reasonable repayment
arrangement he provides.
If a repayment arrangement is not agreed within a further 14 days, or if the
Applicant does not submit one to the FSP, then the FSP may recommence
recovery action, once our file is closed.
If the Applicant does not accept this determination, the FSP may recommence its
legal action once the FOS file is closed.
Case No: 456073 Determination Page 3 of 8
2 Reasons for determination
2.1 Did the FSP unreasonably delay the final payment to the builder?
The Applicant says that the FSP improperly paid its arrears from loan funds
Under the building contract, the builder was due to handover the completed property
to the Applicant by June 2013. It appears the builder was not able to complete in time
because of an issue with power supply to the property and other issues. The builder
did not provide a certificate of completion until 15 November 2013.
The Applicant was relying on rental income to make loan repayments. Due to the
handover delay, the Applicant was not making repayments and arrears accrued on
the construction loan account. The Applicant says that the FSP “clawed back” the
arrears by paying itself from loan funds that had been allocated to pay for
construction.
The FSP did not cause the reduction in available funds
The constructio n loan contract states that the „amount of credit‟ was $1.020 million.
By July 2013, the loan account had been progressively drawn down and had a
balance of $994,375.84. As of July 2013, the Applicant stopped making loan
repayments.
The loan contract stated that interest was charged daily and then debited monthly.
The FSP was debiting interest to the loan account in accordance with the loan
contract. As the Applicant was not making repayments, the loan debt balance
increased and reduced the funds available for construction. The FSP did not pay
itself the arrears, the arrears remained unpaid.
The FSP could decide whether it would lend more funds for construction
When it became clear that there would be insufficient funds to pay the builder the
final progress payment in 2013, the Applicant made enquiries with the FSP. Initially,
the Applicant suggested that he had sufficient equity in his properties to cover the
missed repayments. However, the issue was not whether there was sufficient
security, but that he had insufficient credit approved to make the last repayment.
In late October 2013, the Applicant made enquiries about a line of credit to cover the
final payment to the builder and contingencies. By mid-November 2013 , the FSP‟s
debt collection area had told the Applicant that it could not approve credit, and
referred him to his branch. The Applicant met with his branch manager in late
November 2013. The branch manager told the Applicant the FSP would decline to
provide further credit until he had cleared the arrears. By this time his combined
arrears were over $20,000.
Under our Terms of Reference, we do not have the power to consider a dispute
about a financial services provider ‟ s credit risk assessment decision about lending or
security for a loan . The FSP‟ s initial decision not to provide the Applicant with further
credit was a credit risk assessment decision that we do not have the power to review.
Case No: 456073 Determination Page 4 of 8
The Applicant has not shown that the FSP breached an obligation
In mid-December 2013, the FSP decided to allow the Applicant to exceed his credit
limit in order to pay the builder the final progress payment. The FSP paid the final
scheduled progress payment of $27,150 to the builder on 8 January 2014. By
approving the final payment, the FSP allowed the loan balance to exceed the
„amount of credit‟ that it had originally approved by about $23,000.
The Applicant says that the FSP‟s eventual decision to make the final payment
shows that it had unreasonably delayed responding when he first asked for extra
credit. However, that the FSP later decided to approve the final payment does not
mean that the FSP breached an obligation to the Applicant when it initially declined
extra credit. As stated above, w e cannot review the FSP‟s credit risk assessment.
Also, the FSP had the right under the loan contract to decline progress payments as
more than 12 months had passed since its loan offer (see clause 2(b) of the terms
and conditions).
Despite this, the Applicant was understandably frustrated that the FSP did not tell
him earlier to provide the builder‟s final invoices to the progress payments team for
assessment or discuss his available options with him. The builder issued the final
invoices on 29 November 2013, and the FSP indicated it would pay the final
scheduled invoice on about 18 December 2013.
There were also other factors that contributed to the delay in handover
After the FSP approved the final progress payment, the Applicant instructed his
agent to complete a final inspection of the property. However, the Applicant was
unable to take possession of the property as the builder had not provided a
compliance certificate for utility services. This was not available until January 2014.
The builder also invoiced the Applicant for a variation to the building contract rela ting
to the hot water service. The FSP had to separately consider approval to pay this
invoice. The FSP approved payment of the variation invoice in January 2014, but it
appears there was then a delay of several weeks in payment of the invoice. The FSP
paid the variation invoice on 31 January 2014. Despite this, the Applicant says that
the builder did not provide „practical completion‟ of the property until 18 February
2014.
The significance of these matters is that they show the other issues that contributed
to completion of handover of the property.
2.2 Did the FSP cause the Applicant’s financial loss?
The Applicant says that the FSP caused his financial loss
The Applicant says that he had an offer from a tenant to pay $2,800 per week in
November 2013. The Applicant says that he was unable to accept the offer because
of uncertainty about whether the FSP would make the final payments to the builder.
He says by the time he took possession of the property, available rents had
substantially declined due to increased rental supply and the mining downturn.
Case No: 456073 Determination Page 5 of 8
The Applicant has stated that the FSP was the „proximate cause‟ of his financial loss.
The Applicant has not shown that the FSP caused his loss
Even if the FSP caused an unreasonable delay, the Applicant has not shown that the
FSP caused his loss.
The Applicant told the FSP in mid to late November 2013 he was concerned about
losing a tenancy offer. However, the Applicant has not provided a ny supporting
documents to show he had an offer to lease the property for $2,800 per week. Such
documents could have included written offers from the tenant or emails from the
property manager, and documents showing when any offer was withdrawn. These
have not been provided to FOS.
The Applicant has provided a rental appraisal dated 1 December 2013 estimating the
rental income at $2,300 to $2,800 per week.
The FSP‟s debt collection notes include an entry dated 19 February 2014. This entry
records that the Applicant had received an offer of $2,300 per week rent. This offer
was in line with the December rental appraisal. In this case, any delay of weeks by
the FSP was not the cause of the Applicant‟s loss as the Applicant took hand over of
the property in February 2014.
The Applicant has also provided a retrospective rental market valuation completed in
October 2015. The valuation states that the rental market was already declining by
late 2013. The Applicant has relied on this opinion in his closing submission in his
legal proceedings against the builder.
The Applicant say s that the FSP was the “proximate cause” of his loss. However, he
has pursued the builder for compensation for the entirety of lost rent over a three
year period starting in mid-2013. Therefore, he has sought compensation from the
builder, not the FSP, for the period after handover of the property in early 2014. The
Applicant‟s claim against the builder , which is still on foot, is inconsistent with the
Applicant‟s statement that the FSP was the cause of his loss.
If the FSP is at fault, the remedy is not for suspension of debt recovery
If the Applicant showed that he suffered a financial loss as a result of the FSP
causing an unreasonable delay, then the remedy is compensation for loss, not a
suspension of legal proceedings.
The Applicant says the loss caused by the delay was the loss of the opportunity to
secure a long-term tenant paying higher rent. The Applicant has not made a claim for
this loss against the FSP, but has pursued the builder. The Applicant has instead
said the FSP should suspend debt recove ry action until his claim against the builder
is finalised. He has also claimed the FSP should refund extra interest it has charged
due to the lack of loan repayments.
Under the loan contract, the FSP is entitled to charge interest on the outstanding loan
balance. It is also entitled to charge default interest on amounts that exceed the
approved credit balance. If the Applicant is in default of his loan obligations, and does
not remedy that default, then the FSP is entitled to take action to recover its debt.
Case No: 456073 Determination Page 6 of 8
However, the FSP‟s rights under the contract are subject to it complying with its
obligations to the Applicant as a customer in financial difficulty.
2.3 Has the FSP complied with its obligations to the Applicant as a
customer in financial difficulty?
The FSP has obligations to try and assist a customer in financial difficulty
The FSP is obliged to try and assist a customer in financial difficulty and to give
genuine consideration to a customer‟s request for assistance. A customer seeking
assistance should propose a realistic repayment plan that will result in the eventual
repayment of the debt, including arrears.
The FSP has allowed a reasonable time for the Applicant’s legal proceedings
A timeline of the FSP‟s dealings with the Applicant about his financia l difficulty is set
out in Section 3.1 of this determination. This shows that the FSP complied with its
obligations as follows:
1. In early 2014, the FSP offered to capitalise existing arrears on the construction
loan account if he made his regular repayments for six months.
2. In September 2014, the Applicant requested an eight month extension to clear
the arrears before the FSP pursued legal action.
3. In mid-2015, the Applicant asked for the FSP to further suspend recovery
proceedings as his claim against the builder had been referred for arbitration.
4. In August 2015, the FSP agreed to wait until November 2015 if he made his
loan repayments. The Applicant declined to make loan repayments. In
December 2015, the FSP agreed to put further action on hold until April 2016.
The FSP should refund costs incurred for the default notices in April 2016
The FSP issued default notices in April 2016 for the Applicant‟s loans. However, the
FSP did not send a default notice for the construction loan to the Applicant‟s
residential address. For this reason, the FSP issued default notices again in July
2016.
Under the loan contract and the mortgage, the FSP is entitled to recover from the
Applicant its reasonably incurred costs in enforcing its mortgage.
The FSP passed on the cost of preparing the April default notices to the Applicant.
However these default notices were defective due to an error by the FSP‟s solicitor.
Therefore, it is not reasonable for the FSP to recover the cost of issuing the April
2016 default notices from the Applicant. The FSP charged an arrears notice fee and
„production of legal notices‟ cost in April and May 2016. The FSP should refund a
total of $205.56 to construction loan account (loan ending #6502).
It is likely that the July 2016 default notice was validly served
The FSP ‟s solicitor issued new default notices in July 2016. The cover letters for the
default notices sent to the Applicant‟s residential address contain a minor spelling
Case No: 456073 Determination Page 7 of 8
error in the street name. An „n‟ has been omitted in the second half of the street
name, however the street name is still readily apparent.
On balance, it is more likely than not that the default notice was validly served. This
is because:
The incorrect spelling does not match another street name in the suburb or
state.
All other address details are correct, and the correct street name is identifiable
despite the minor spelling error.
The FSP‟s solicitor did not receive returned mail.
The FSP had sent default notices for the Applicant‟s other loans to the Applicant‟s
residential address in April 2016. Overall, I am satisfied that the Applicant was aware
that the FSP was threatening to start legal proceedings for debt recovery.
It was reasonable for the FSP to commence legal action
The FSP commenced legal proceedings in September 2016. At the time that the FSP
commenced legal proceedings:
The Applicant‟s combined loans were over $300,000 in excess of their original
credit limits
The Applicant had only made one loan repayment since July 2013 and
The FSP had held off commencing debt recovery proceedings for two years to
allow the Applicant to pursue proceedings against the builder, which were still
not finalised.
In the circumstances, it was reasonable for the FSP to commence legal action.
This was understandably frustrating for the Applicant, as he had been told that the
outcome of his arbitration proceedings was imminent. However, the FSP had been
told that an outcome to his dispute against the builder was imminent on a number of
occasions . For instance, on 4 May 2016 the Applicant‟s barrister had told the FSP
that the decision was expected in four to six weeks. From the information available,
the Applicant has still not received the arbitration decision.
The FSP was not obliged to indefinitely withhold from debt recovery proceedings,
and was entitled to commence court action.
Case No: 456073 Determination Page 8 of 8
3 Supporting information
3.1 Timeline of financial difficulty dealings between the parties
Date Event
31/1/ 20 14 The FSP makes f inal payment of $4,614 to the builder for the variation invoice .
The FSP offers to capitalise the arrears if the Applicant makes 6 m on ths regular
repay ment s .
10/2/ 20 14 The Applicant requests reduced repay ment s while he secure s tenants .
19/2/2014 The Applicant tells the FSP he has “offer for tenants, $2,300 weekly, [the
Applicant] asking for more, will have lease written up, was expecting $2, 800
weekly”.
Sept ember 20 14 The App licant requests an 8 m on th extension to repay arrears so he could purs ue
legal action against the builder .
Dec ember 2 014 The Applicant obtains a lease of $800 per w eek .
5/5/ 20 15 $1,000 deposit by Applicant, first payment since July 2013. No repayments have
been made since.
19/6/ 20 15 The court refers the Applicant‟s proceedings against his builder to arbitration. The
Applicant asks the FSP to hold off recovery action until arbitration completed.
Aug ust 20 15 The FSP tells the Applicant it would wait until Nov ember 20 15 for arb itration
outcome if he makes loan repay ment s . The Applicant declines to make
repayments.
Dec e mber 20 15 The FSP says it will wait until 1/4/ 20 16 for the results of arbitration.
1 - 3/3/ 20 16 Arbitration hearings.
19/4/ 20 16 Final written sub m issions made to the arbitrator.
22/4/ 20 16 The FSP issues a d efault notice , although not to the Applicant‟s home address for
the construction loan .
4/5/2016 The Applicant‟s barrister tells the FSP that a decision is expected in 4 - 6 weeks .
29/7/ 20 16 The FSP issues a d efault notice to the Applicant.
12/9/ 20 16 The FSP initiates proceedings in the County C ou rt