Storm and mould damage claims: contents settlement, mould remediation, basement repairs and delay
Text of the determination
Determination
Case No: 455169 Determination Page 1 of 11
Case number: 455169 13 April 2017
1 Overview
1.1 Dispute
The applicant lodged two claims for storm damage on her strata and home contents
insurance policies with the financial services provider (FSP) policy, the first in
February 2015 (roof claim) and the second in November 2015 (basement claim).
During the lengthy claims process for the roof claim, mould damage was discovered
to both the building and applicant‟s contents. The applicant has been living in
temporary accommodation since October 2015 awaiting mould remediation.
The FSP accepted liability for the roof claim and completed the roof repairs. While
initially limited its indemnity for the mould to three rooms, it has since accepted
liability for mould remediation to the house. The FSP accepted liability for the
basement claim but has waited for the applicant to complete some necessary
maintenance works and for the mould remediation to be completed prior to starting to
arrange repairs.
While mould remediation and repairs from the roof claim is now completed, repairs to
the basement have not started.
The applicant says the FSP has not correctly assessed which contents items that are
non-salvageable, has not properly remediated the mould a nd has not commenced
work on the basement.
1.2 Issues and key findings
Has the FSP appropriately remediated mould at the insured property?
The FSP has not remediated the entire property and basement to ensure all mould
contamination has been remediated. Further testing is required.
What is the scope of the FSP’s repairs under the claims ?
The parties have agreed to the scope of works however to ensure all issues are
resolved the FSP should appoint an independent engineer to determine any further
works required and take the actions outlined in section 1.3
What is the appropriate settlement of the contents claims?
I am satisfied that the itemised list of non-salvageable contents items provided for the
basement claim is fair and reasonable and that the FSP should m eet the applicant‟s
claim as set out in section 2.3 of this determination. I am also satisfied the itemised
Case No: 455169 Determination Page 2 of 11
list of contents claimed as non-salvageable for the roof claim is fair and reasonable
however, I accept the applicant is concerned that there may be further damage to
items that she is unable to determine. This part of the dispute should be settled in
accordance with section 2.3.
Is the applicant entitled to consequential financial loss?
The applicant is entitled to consequential loss compensation for temporary
accommodation on 29 September 2016 and internet plan costs.
Is the applicant entitled to non-financial loss compensation?
The applicant has lodged four separate claims and suffered stress and
inconvenience outside the normal claims experience for each. The applicant is
entitled to non-financial loss compensation totalling $6,000.
1.3 Determination
This determination is in favour of the applicant.
The FSP is required to on completion of the works:
engage an independent mould remediation specialist to conduct mould testing
of all areas of the house, including basement, bathroom and laundry
appoint an independent engineer upon completion of the repairs to the
basement and mould remediation to confirm the repairs have been completed
to industry standard and the basement is water tight
pay the applicant $65,787 for the basement contents claim. The FSP is entitled
to deduct from this sum any payments already for this claim.
the FSP is liable t o meet the applicant‟s claim for the roof contents claim for the
non-salvageable items and any items damaged or lost whilst in storage. The
applicant and the FSP are asked to work cooperatively together to assess the
extent of this loss. The FSP may then c ash settle the applicant‟s claim based on
the assessment of the loss.
the FSP is to reimburse the applicant the internet costs incurred prior to
cancelling the plan upon the applicant providing invoices or relevant
documentation establishing the amount incurred.
the FSP is to pay the applicant non-financial loss compensation from the four
claims in the total sum of $6,000
the FSP is to continue to provide temporary accommodation to the applicant
and for the applicant‟s pets until such time as the independen t engineer has
verified the repair works have been completed to industry standard.
the FSP is liable to reimburse the applicants the costs of the exploratory works
to identify the cause of the basement leak subject to the applicant providing
relevant invoices
Case No: 455169 Determination Page 3 of 11
2 Reasons for determination
2.1 Has the FSP appropriately remediated the mould at the insured
property?
FSP has undertaken remediation and provided an air test report
The FSP engaged a contractor to conduct the required mould remediation in
November 2016. On 16 December 2016, mould hygienist EA provided a report
regarding the remediation. The report notes it:
“understands that the water damage occurred following water ingress into the dwelling via the
roof to the living room and along the north facing wall causing damage along the north of the
property. Consequently, this PRV refers only to those areas affected by the aforementioned
event and all other areas outside beyond fall outside the scope of this assessment.”
EA conducted air testing in the mandated areas and found “ the remediated areas as
part of the claimed event have returned to Condition 1 and restoration works can
commence at the property ”.
Applicant has provided photographs of mould post-remediation
The applicant questioned the FSP‟s assertion that the mould remediation is
satisfactory because the testing was done while the dehumidifiers were running.
The applicant has provided photographs of the visible mould she can still see in the
house.
The applicant requested the FSP appoint a second mo uld hygienist to confirm the
FSP‟s findings, or for the FSP to retest the property without the dehumidifiers on.
FSP required to test for mould in entire property and remediate
In discussion with the applicant on 12 April 2017, the applicant advised that the FSP
had completed the mould remediation work other than to the bathroom and laundry.
The applicant advised that with her son she had cleaned and painted both the
bathroom and laundry to complete the work.
According to the applicant there were visible signs of mould in the other rooms and
the FSP‟s assessor had advised that the painters to provide a mould inhibitor added
to the paint to seal the painting.
The applicant advised that the first painters sent by the FSP did not attempt to seal
the mould prior to the painting. The FSP was required to appoint a different painter.
The applicant has confirmed that the remediation work has now been completed but
is concerned with those areas painted by the FSP‟s first appointed painter and
whether there will be ongoing issues with mould.
I am concerned that the FSP did not complete the mould remediation throughout the
entire house and that the applicant was required to clean and paint both the
bathroom and laundry.
I am also concerned that the process of applying a mould inhibitor to the paint
without properly treating the mould may not be a successful process in the
Case No: 455169 Determination Page 4 of 11
remediation of the mould. In the circumstances, the FSP should on completion of the
works to the basement engage an independent mould remediation specialist to
conduct mould testing of all areas of the applicant‟s house including the basement. In
the event that the specialist believes further mould remediation is required, then the
FSP is to carry out that remediation as a matter of priority.
2.2 What is the scope of the FSP’s repairs under the claims ?
Applicant has worked with FSP to form relevant scope of works to repair
property
The applicant and FSP have worked together since a site visit on 10 November 2016
to form the repair scope of works. There appears to be open and productive dialogue
regarding the required repairs to the basement and upstairs area of the insured
property.
The applicant advised that whilst the mould remediation work has been largely
completed, the repairs to the baseme nt have not started. On the 11 April 2017 she
moved into new temporary accommodation. As she is now in an apartment, her dog
has had to be placed in a boarding kennel. The FSP has covered all costs associated
with the temporary accommodation and the boarding kennel costs.
Applicant has paid for repairs to prevent water ingress into the basement
The applicant was advised by a FSP representative on 20 November 2015 that she
was required to install drains and fix her window frames after she lodged her
basement claim. This was required before the remediation works could commence.
The policy provides cover for the escape of liquid and includes exploratory costs
being the reasonable costs of locating the source of the escape of liquid and to repair
and restore the damage to the home and contents caused by the exploratory work.
The applicant has advised that she has not been reimbursed for the exploratory costs
to determine the source of the leak.
The applicant has provided invoices and receipts for the work and materials pai d to
complete the work but I do not have any invoices or receipts for the exploratory work.
Subject to the applicant providing invoices and receipts for the costs of the
exploratory work and repairing and restoring the damage to the home caused by the
exploratory work, then the FSP is liable to meet that claim.
Insofar as the applicant has incurred costs in repairing or replacing the item or fixing
the leaks, the policy excludes cover for those costs and the FSP is not liable to meet
the same.
FSP to appoint an independent engineer
Given the ongoing issues with the basement and ongoing issues with the mould
remediation, in my view, it is fair that the FSP upon completion of the works including
the work to the basement, appoint an independent engineer to determine that the
work has been completed to appropriate industry standard. In the event that the
Case No: 455169 Determination Page 5 of 11
independent engineer identifies additional work is required, then the FSP should
complete that work in accordance with the terms of the policy.
2.3 What is the appropriate settlement of the contents claims?
The FSP is entitled to cash settle the applicant’s roof and mould claim
At the time of the first claim, the FSP‟s policy provided contents cover of up to
$100,000. According to the applicant she has not been settled other than $2,000
emergency payments for winter clothing for the loss of contents arising from the roof
and mould damage.
The FSP in its Notice of Response advised that as at 23 February 2017, its assessor
has submitted a review of the contents items claimed from the roof claim and had at
this stage approved an amount of $4,162 for payment with a review being finalised
for the new items submitted by the applicant.
The applicant has advised that she has not received any payment whatsoever and is
concerned as to the manner in which her items have been stored and whether or not
items have been damaged, destroyed or lost in the process.
The original non-salvageable list totalled $22,365. It is unclear from the information
provided why this full amount was not approved by the FSP or why it has not been
able to assess whether all of these items are damaged or not.
In my view, the only way that this can be resolved is for the applicant and the FSP to
inspect the items currently in storage and determine those items that are non-
salvageable, those items that have been damaged, those items that can be repaired
and those items that may be lost or damaged. Once the parties have determined this,
then the FSP can cash settle the applicant for the cost of the non-salvageable items
and lost items.
Insofar as there are items that may be repairable, the FSP can elect to either repair
or cash settle the applicant for the cost to repair those items. In the event that the
parties are unable to reach agreement with respect to the amount of the cash
settlement, the parties may refer the dispute back to FOS.
The FSP is entitled to cash settle the basement contents claim
I have not been provided a copy of the schedule for the period 25 August 2015 to 25
August 2016 which covers the basement claim. I have been provided a copy of the
schedule for the period 25 August 2016 to 25 August 2017. I accept in the
circumstances that the contents cover provided under the policy at the time of the
November 2015 claim most likely covered contents for an excess of $100,000.
I have calculated the applicant‟s basement contents claim amount sought as
$69,382.
The applicant‟s home contents policy provides a fixed limit of $500 for uninstalled
building fittings, fixtures and materials that are kept locked at the insured address.
The applicant is claiming an amount of $4,095 for the below items.
Laminate flooring - $80 * 4 total $320
Lino flooring - $60
Case No: 455169 Determination Page 6 of 11
Hardware Loose screws and bolts - $80
Venetian blinds - $80 * 10 total $800
Underlay - $140
Tiles - $20
Doors - $250 * 3 total $750
6 glass window door - $350
Plasterboard - $20
Window - $200
Geelong cement - $20
Davc o Ceramacret e - $50
Bathroom Sink - $300
Marble tiles - $15
Johnson tiles - $50
Bathroom tiles - $30
Large drawer of nails - $330
Large tub of nails - $480
Gyprock cement - $30
Insulated copper pipes - $50
I am satisfied the listed items constitute uninstalled building fittings, fixtures and
materials which are limited to $500.
The applicant advised that the FSP has now paid $54,685 to cover the basement
contents claim and allowed $500 for the uninstalled building‟s fittings, fixtures.
The items claimed other than the building fittings, fixtures and materials appear
reasonable. The applicant has also incurred costs associated with purchasing other
tools to effect repairs to the property.
In the absence of any reason why the value of the conte nts claim be reduced, in my
view, it is fair that the FSP meet the applicant‟s claim.
The FSP is required to cash settle the applicant $65,787 for the basement contents
claim (total of contents $69,382 minus $3,595). As the FSP has already paid the
applicant $54,685 then the FSP should pay the applicant the balance being $11,102.
2.4 Is the applicant entitled to consequential loss compensation?
The applicant has provided emails dated 19 October 2016 from the FSP advising her
that it would not reimburse the accommodation costs for the night of 29 September
2016 due to the late check out notice. The FSP has not provided reasons why the
applicant should be responsible for such a cost.
It appears that the applicant may have been attempting to find accommodation after
the FSP had informed her that it would be ending her temporary accommodation
payments.
The applicant has now said the FSP has met all of her temporary accommodation
payments. In the event that the FSP has not reimbursed the applicant the cost of the
accommodation on 29 September 2016, it should do so.
The applicant has also advised that she continued to pay her internet plan as she
thought she would be moving back into her house in a timely manner. This is not
unreasonable. The applicant was required to cancel the policy only when she
realised she would not be moving back in.
I accept that the applicant has an obligation to mitigate her loss. However, in the
circumstances, I believe she has done so by cancelling the policy once she realised
Case No: 455169 Determination Page 7 of 11
she would be in long term temporary accommodation. The applicant claims the cost
for the internet was $960. Upon the applicant providing invoices or documentation to
establish this amount and to establish that the internet was not being used during the
relevant period, in my view, the FSP should reimburse the applicant this cost.
2.5 Is the applicant entitled to non-financial loss compensation?
FOS can award non-financial loss compensation
Under its Terms of Reference, FOS may consider awarding compensation for non-
financial loss where there has been an unusual extent of physical inconvenience,
time taken to resolve the situation or interference with the Applicant‟s expectation of
enjoyment or peace of mind.
FOS‟s Terms of Reference allow FOS to make an award of up to $3 ,000 per claim
made in the dispute.
In this matter, the applicant has four separate claims with the FSP and FOS can
award up to a maximum of $12,000.
Non-financial loss compensation is warranted
Building claim lodged in February 2015
The FSP placed make safe tarps on the applicant‟s roof shortly after she lodged her
claim in February 2015. The applicant advises the tarps were on the house until the
roof was repaired in October 2015.
The applicant says the roof repair only took four days, however it was nine months
from the storm event until this occurred. The applicant says she chased up the FSP
and builders to have the roof repaired.
On the information available, it appears the mould was a result of the FSP‟s delay in
repairing the water damage to the property and roof.
The presence of mould has had a significant impact on the applicant‟s life, requiring
her to live in temporary accommodation and to see her son struggle to keep up in
school due to the disruption.
The applicant is entitled to $1,500 compensation for non-financial loss due to the
FSP‟s delays in claims handling.
Contents claim lodged in February 2015
The applicant‟s original contents claim was for water damage to a cabinet, rug and
armchair.
However, due to mould spreading in the property, the applicant had contents
removed from the property in July 2016. The FSP has not provided any reasons why
contents items were removed in July 2016 when the mould was discovered in
October 2015. There appears to be a nine month lapse where the FSP failed to
prevent further damage to the applicant‟s contents.
Case No: 455169 Determination Page 8 of 11
The applicant has been without her contents items while living in temporary
accommodation since October 2015.
Further, the applicant says she and her child were without winter clothes and only at
that point did the FSP provide a $2,000 contents payment to the applicant.
The applicant has advised she was sent kitchen contents that had mould on them
which caused her concern as to what contents the FSP was deeming salvageable.
It appears the applicant will not have access to her contents until the building repairs
are completed. FOS has not been provided a completion date.
There is no doubt the applicant has suffered stress and inconvenience outside of the
claims experience due to not having access to her contents, and not receiving a
contents settlement from the FSP.
In the circumstances, the applicant is entitled to $1,500 compensation for non-
financial loss due to this inconvenience.
Building claim lodged in November 2015
As discussed in section 2.3, the FSP required the applicant to rectify a defect prior to
commencing its basement repairs.
The applicant completed the repairs in April 2016. The FSP has not yet started the
basement repairs. It provided the applicant with a scope of works dated 28
November 2016 but this has not yet been actioned.
The basement was further damaged by water ingress from a neighbour‟s property in
a December 2016 storm.
The applicant has suffered delays and in inconvenience outside of the usua l claims
experience due to the FSP‟s delays in assessing and repairing her basement.
The applicant is entitled to $1,500 non-financial loss compensation.
Contents claim lodged in November 2015
The applicant‟s basement contents were removed in November 2015. The applicant
received a non-salvageable list of items on 26 September 2016, nearly twelve
months later.
The applicant advised on 24 October 2016 that she was so stressed when she saw
the incomplete non-salvageable list that she was physically ill.
The applicant spent time and inconvenience attempting to recall all items that were in
the basement due to the FSP‟s failure to provide an accurate list of all items that
were disposed of on site and those which were taken off site.
The applicant is entitled to $1,500 compensation for non-financial loss for the stress
caused by the FSP‟s inadequate assessment of her contents items.
Summary
Upon review of all four claims, the applicant is entitled to compensation for non-
financial loss in the amount of $6,000.
Case No: 455169 Determination Page 9 of 11
3 Supporting information
3.1 FOS Approach
As advised to the parties, FOS has considered it appropriate to expedite this dispute
in accordance with the Operational Guidelines to the FOS Terms of Reference, due
to the failure to respond. Accordingly, this dispute has not been the subject of a FOS
recommendation and has proceeded directly to determination.
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered for the purposes of this determination.
This dispute has been decided on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous Financial Ombudsman Service
(FOS) decisions.
3.2 Strata Product Disclosure Statement
Dealing with defects
If a known defect is the cause of the damage
We do not pay for loss or damage caus ed by a defect, structural fault or design fault at your
building that you knew about (or should reasonably have known about ) and did not fix before
the loss or damage occurred.
If an unknown defect is the cause of the damage
If an incident covered by your policy damages your building and an unknown defect was the
cause or part of the cause, we will pay for the resulting damage. If the unknown defective part of
your building is also damaged by the same incident, we will fix this as well.
We do not rectify structural or design faults
When we accept a claim, we will not pay extra to rectify a structural or design fault at your
building that you knew about (or should reasonably have known about ). We will only pay you
what it would have cost us to fix the damage from the incident covered by your policy, or if we
agree, you can pay us the extra amount it costs to rectify the structural or design fault at your
building.
If undamaged defective parts of your building will not support repairs
If undamaged defective parts of your building you knew about (or should have reasonably have
known about) will not support repairing the damage caused by an incident covered by your
policy, we will only pay what it would have cost us to repair the damage had your building not
been defective.
For known defects or faults
Once you become aware of a defect, structural or design fault at your building, you must rectify
it as soon as possible because there is no cover for loss or damage due to that defect. If you do
not rectify the defect or fault, you may not be covered or we might not offer a renewal of your
policy.
3.3 Home Contents Product Disclosure Statement
The most we will pay for home claims
If we accept your claim, the most we will pay fo r loss or damage to the home is its sum insured
shown on your certificat e of ins urance, unless a different limit elsewhere in your policy applies.
Some items also have fixed limits that cannot be increased and these limits are the most we will
pay for those items as shown in the table below.
…
Uninstalled building fittings, fixtures and materials but only when kept in a locked and secured
building at the insured address
Case No: 455169 Determination Page 10 of 11
Classic: Up to $500 in total
…
We choose how we settle contents claims
If we agree to pay a claim for loss, theft or damage to your contents (including contents with
flexible limits and portable valuables), we will decide if we will:
repair damage to the contents;
replace the contents „new for old‟;
pay you what it would cost us to repair or replace your contents or any lower limit that applies.
pay you the sum insured for your contents or any lower limit that applies;
give you a voucher, store credit or stored value card for the amount it would cost us to repair
or replace the contents.
If we replace (or pay you what it would cost us to replace), we will do so on a „new for old‟ basis.
If we repair (or pay you what it would cost us to repair), we will at our option do so on a
„new for old‟ basis or to a similar condition to what the contents were in before the loss or
damage occurred.
Unless we tell you otherwise, we will deduct any amounts you owe us from any amount we owe
you.
3.4 Timeline of events
Date Action
February 2015 Applicant lodges claim for storm damage that occurred in
January 2015.
14 September 2015 Applicant noticed mould growing in her son‟s bedroom.
Notified FSP.
14 October 2015 Roof repaired but there is mould.
19 Oct 2015 Applicant moves into temporary a ccommodation due to
mould.
5 Nov 2015 Basement flooded in separate storm event
8 Nov 2015 FSP contractor attends property and removes contents from
the basement.
11 Nov 2015 FSP advises applicant during meeting that mould is pre -
existing.
12 Nov 2015 Applicant lodges IDR complaint with FSP.
20 Nov 2015 FSP advises Applicant if she fix es drains to prevent water
entering basement, FSP will fix all of house. Applicant says
she agreed to find the cause of the flooding in the basement
and rectify it.
19 April 2016 Applicant completes repairs and engineer sent out by FSP
who confirms works are satisfactory. Applicant notes
engineer was puzzled he was engaged to inspect the job
rather than instruct what work was to be done before
applicant repaired.
30 M ay 2016 FSP calls applicant with rec ommendations from engineer
based on site inspection. Says they are recommendations
only.
25 July 2016 FSP removes home contents from the house (not
basement).
Case No: 455169 Determination Page 11 of 11
27 Sep 2016 Applicant lodges disput e with FOS.
28 Sep 2016 FSP provides list of non - salvageable contents items.
Applicant disput es the list is complete.
10 Oct 2016 FSP confirms it will provide ongoing accommodation.
10 Nov 2016 FSP assessor requests applicant installs a grate at the front
of the basement steps. Applicant engages tradespers on to
do this.
14 Nov 2016 FSP provides applicant with a login to view non - salvageable
and restored contents.
16 Nov 2016 FSP advises mould remediation will start 21/11/16. Applicant
advis es this did not take place.
25 Nov 2016 Applicant advises she has been told mould remediation will
start 28/11/16. Applicant advises did not take place due to
technician illness.
28 Nov 2016 FSP provides repair scope of works to applicant.
10 Jan 2017 A provides quote for repairs
25 Jan 2017 A provides various receipts
20 Feb 2017 A provides photos re poor repairs and painting
04 Mar 2017 FSP provides Notice of Response and attachments