Determination 453857
Additional cracking and door jamming after leaking pipe denied as seasonal movement
Summary
The applicant claimed for water damage after a leaking pipe at her home, and the FSP denied some further cracking and door jamming as seasonal ground movement. AFCA found part of the damage was caused by the leak, ordered repairs in place of a cash settlement, and ordered reimbursement of the applicant's engineer report.
The leak caused some covered damage, while seasonal ground movement is not an insured event, and repairs were preferred over cash because the scope of works was uncertain.
Issues
- Claim denial primary · upheld
“I accept JK's report and determine that the cracks to bedroom 1 and the hallway and the damage to the tiling and the bathroom is as the result of the initial leak.”
- Claim amount dispute secondary · upheld
“Given the uncertainty, I do not believe it is fair in the circumstances for the FSP to cash settle the claim.”
Subjects and remedies
home or building damagepay compensationrepair or rectify
Text of the determination
Determination
Case No: 453857 Determination Page 1 of 6
Case number: 453857 19 December 2017
1 Overview
1.1 Dispute
The applicant lodged a claim under her home insurance policy with the financial
services provider (FSP) for water damage after she discovered a leaking pipe.
The FSP engaged an engineer (PB) who recommended that a plumber be
commissioned to resolve the suspected leaking pipe in the toilet and laundry and that
the ground moisture should be allowed to dry out prior to completion of repairs.
During the drying out period the applicant reported further cracking and jamming door
which she attributed to the leaking pipe.
The FSP has accepted claim for some of the damage but considers other damage
unrelated to the claim event and caused by seasonal ground movement over an
extended period of time, which is excluded from cover.
1.2 Issues and key findings
Is the FSP liable for the extra damage to the property?
The available information establishes that some of the extra damage to the
applicant’s property was caused by the leaking pipe in April 2015. Accordingly, the
FSP is further liable for the damage determined by JK.
Is the applicant entitled to compensation?
The applicant has offered to cash settle the claim for $47,050.60. Based on the
FSP’s builder quotation (PI) and the recent scope of works by the FSP’ s builder (JL).
This sum is insufficient.
1.3 Determination
The determination is partially in favour of the FSP.
The FSP is entitled to reject cover for some of the additional damage sought by the
applicant.
The FSP must complete the repairs as set out in the FSP’s email to FOS dated 27
November 2017 and repair the extra damage determined in JK’s report.
The FSP shou ld reimburse the applicant for the cost of JK’s report, upon
presentation of the invoice by the applicant.
Case No: 453857 Determination Page 2 of 6
2 Reasons for determination
2.1 Is the FSP liable for the damage to the property?
Policy provides cover for insured events subject to exclusions
The applicant is required to show, that on the balance of probabilities she has
suffered a loss caused by a risk insured against under the policy. This is known as a
valid (prima facie) claim. If the applicant is able to establish a valid claim, then the
onus shifts to the FSP to show that on the balance of probabilities, it is entitled to rely
on an exclusion under the policy or is otherwise entitled to deny the claim.
The applicant’s policy provides cover for damage caused by events listed in the
policy, including the insured event of escape of liquid from fixed pipes, sinks, toilets
and basins, subject to the conditions and exclusions set out in the policy.
The parties are in disagreement about the cause of the damage
The FSP appointed (R) to assess the loss of contents and on 19 May 2015 the
inspection of the crawl space under the house disclosed water logging and puddles
in low points. Drying equipment was installed in the affected areas to assist with the
drying process and the excess water was removed.
The FSP appointed an engineer (PB) who provided a scope of damage as follows:
suspected leaking pipes in sub floor area of toilet and /or laundry area – plumber
to inspect and resolve leaking pipes, if no such pipe leaks are found then further
investigate other possible water sources and resolve required
suspected leaking pipes has caused excessive moisture in found soils – allow
ground moisture levels to stabilize prior to carrying out the remediation works
outlined, (typically allow 4 to 6 months for stabilization)
heaved and up to ‘moderately’ cracked concrete slab – once ground moisture
levels have normalized/slab crack with have stabilized undertake repair of
concrete slab.
The engineer carried out a follow up inspection on 10 February 2016 and noted as
follows:
the leak has been repaired but a hole remains in the wall where access would
have been gained
the external masonry walls of the house features some negligible cracking –
cracking of this nature is considered consistent with the building of this age and
is likely to have been caused by seasonal ground movement.
internal cracking was observed in various areas around the house including the
plaster walls ceiling and cornices
during the inspection the owner mentioned that some doors and windows
around the house were jamming. All doors were checked and was found that
bedroom number 1 and the bathroom doors were both jamming the door to
bedroom number 3 was not jamming however it was observed there was a gap
between the door and the door frame of the top corner. It was noted that the
bedroom window was tested and appeared to be functioning correctly.
Case No: 453857 Determination Page 3 of 6
it was noted there was a slight dip in the flooring outside bedroom number 3
the concrete slab and stumps in the sub floor were inspected, the subfloor
generally appeared to be dry
the engineer spoke to the son who advised that prior to the leak the owner’s
husband had repaired some side cracks around the house.
It was the engineers opinion that ‘moderate’ cracking and heaving of the cellar
concrete slab has resulted from a swelling of the soil beneath, caused by altered
ground moisture levels instigated by the leaking pipe in the toilet (and laundry room).
‘Also given the widespread nature of the internal and external cracking, previous
crack repairs, and th e age of the house, it is the engineer’s opinion that additional
reported damage is most likely to have been caused by seasonal ground movement
over an extended period of time’.
‘It is plausible that some of the pre -existing cracking damage may have been made
worse by the pipe leak. In our opinion, cracking damage that may have been made
worse by the pipe leak includes cracking to the toilet, laundry and bathroom.
All other reported cracking and jamming of doors inside the house are considered
unrelated to the claim event.’
The applicant has raised the following concerns:
the wall cavity in the main toilet has been left exposed for almost 2 years and
the FSP has not had anyone look at this for mould issues
the patching of the cellar floor with a epoxy fill is not acceptable and the
damaged area should be brought back to its pre loss condition
(PI) builders advised they would not be willing to carry out and warrant the
repairs to the concrete slab as it was a patch repair
On 22 October 2015 the applicant contacted the FSP about additional damage she
noticed around the house. This damage included:
cracks to the walls, the hallway and bedroom 2 and 3
bathroom doors jamming and not being able to close
mould in the wall of the cavity toilet
The FSP rejects the additional damage and refers to the opinion of the engineer (PB)
and that the damage is caused by seasonal movement over an extended period of
time.
Is there sufficient evidence to establish the water leaks have caused the
additional damage?
The applicant disagrees with the report provided by engineer PB. The applicant says
that the cracking and door jamming did not occur until after the leaking pipe was
discovered.
PB’s report is substantial and provided by an expert in respect of the damage that
has occurred to the premises. The information provided indicates that prior to the
leaking pipe there were repairs carried out to the property.
Case No: 453857 Determination Page 4 of 6
The applicant obtained a report from a consulting structural and civil engineer (JK).
JK provided the following conclusions and recommendations:
‘As the site is located in Maidstone with reactive clays it is highly likely that movement
has occurred in the past and this was clearly throughout the residency in the area
where patching has had already occurred… However the are as we have seen have
new lateral and compression cracking is indicated to bedroom 1, hallway, adjusted to
area where the water leak occurred and the bathroom. The bathroom tiling has been
cracking and the vertical plain of the tile looks to be shifted from west towards east, the
vertical gap has increased considerably. Based on our observation this tile area needs
to be removed totally and made good.
Based on the degree of cracking that has been seen, it is this offices opinion that the
new cracking that has occurred (lateral shift and compression cracking) due to some
significant event (excessive water egress, flooding that occurred), meaning that stumps
have heaved in certain location due to the swelling of the underlying clay. It is highly
likely that the above cracking described has occurred as a result of the flooding that
occurred and progressed throughout the southern portion of the house, unbeknown to
the clients which was there for a long period of time.’
Based on all of the information provided by both the FSP and the applicant I am
satisfied, on the balance of probabilities, some of the cracks to the walls of the
bedrooms and hallway and the jamming of the doors was not as the result of the
water leak but instead as the result of seasonal movement which is not an event
covered by the policy. However I accept JK’s report and determine that the cracks to
bedroom 1 and the hallway and the damage to the tiling and the bathroom is as the
result of the initial leak.
I note that the FSP raised a question o ver the qualifications of JK however I have
confirmed JK holds registration with Victorian Building Authority and I am satisfied his
experience and qualifications is sufficient for me to take due notice of his report.
I confirm that FSP is required to cover the cost of repairing this damage including
removal and making good all the tiles in the bathroom.
Outstanding matters to be dealt with by the FSP
Since the recommendation was made the FSP has offered a total cash settlement of
$47,050.60. This offer does not take into account repairs required to address the
issues raised in JK’s report.
The FSP must r epair the damage as specified in clause 4 of the FSP’s email, to
FOS, dated 27 November 2017, subject to any changes required to incorporate the
repairs as set out in JK’s report. This email is set out in the next section.
The report, from JK, provided by the applicant has influenced my decision and I
therefore determine that the cost of this report should be paid by the FSP.
Fairness, reasonableness and utmost good faith
The information available, and in particular, the scope of works provides for several
variations which will not be apparent until the repairs are commenced. The scope of
Case No: 453857 Determination Page 5 of 6
works does not include the repair of the damage to bedroom 1, the hallway or to the
tiling in the bathroom.
Given the uncertainty, I do not believe it is fair in the circumstances for the FSP to
cash settle the claim.
The FSP must complete the works identified in clause 4 of the email dated
27 November 2017 addressed to FOS and set out in the email to FOS of
22 November 2017 which are as follows:
‘A1 repair liability quote (AR attachment 3) in the sum of $33,260.79
AR liability quote (AR attachment 5) in the sum of $4,769.60
Mould remediation quoted by JL (AR attachment 6) in the sum of $6, 136.66
Repair to the crack in the hallway adjac ent to bedroom and additional grouting repair (AR
2 attachment 3) in the sum of $1,036.54 .’
The above quote should be adjusted subject to any changes required to incorporate
the repairs as set out in JK’s report.
Case No: 453857 Determination Page 6 of 6
3 Supporting information
3.1 Key records
Record Key points
FSP’s plumber (AL)
Report
17 - 05 - 2015
Testing to washing mac hine in laundry and waste pipe found a drip
external to the laundry when waste pipe was in use
Drip got worse as waste pipe was put under more pressure
Drip does not appear to be contributing to damages to sub floor.
FSP’s engineer (PB)
Report
05 - 05 - 2016
Given the widespread nature of the internal and external cracking,
previo us crack repairs, and the age of the house, additionally
reported damage is most likely to have been caused by seasonal
ground movement over an extended period of time.
With the amount of previous patch repair work evident in the
plaster walls, re - blocking of internal stumps and re - pointing of the
mortar that these damages have most likely been occurring over
an extended period of time.
Since a wall has reportedly been removed adjacent to the kitchen
indicates that modifications have been made to the house in the
past that have changed support to the ceiling in that area.
The additional damages reported after the initial inspection are
most likely to have been caused by seasonal ground movement
over an extended period of time and are not considered related to
the claim event.
Although not the primary cause it is plausible that some of the pre -
existing cracking damage may have been accelerated by the pipe
leak.
Cracking damage that may have been made worse by the pipe
leak includes internally, cracking to the toilet, laundry, bathroom
and the sunroom plaster wall and stepped mortar cracking to the
rumpus room, and externally stepped mortar cracking in the sout h
east corner.
All other reported horizontal cracking and jamming doors inside the
kitchen, dining roo m, living room and bedroom 1, 2 and 3 are
considered unrelated to the claim event.
Applicant’s Structural
and Civil Engineer (JK)
Report
11 - 10 - 2017
Areas with new lateral and compression cracking in bedroom 1,
hallway and bathroom tiling
Bathroom tiling n eeds to be removed and totally made good.