Home / Financial Firm (Unknown - Insurer) / Determination 453857

Determination 453857

Additional cracking and door jamming after leaking pipe denied as seasonal movement

FirmFinancial Firm (Unknown - Insurer)
Decided2017-12-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant claimed for water damage after a leaking pipe at her home, and the FSP denied some further cracking and door jamming as seasonal ground movement. AFCA found part of the damage was caused by the leak, ordered repairs in place of a cash settlement, and ordered reimbursement of the applicant's engineer report.

The leak caused some covered damage, while seasonal ground movement is not an insured event, and repairs were preferred over cash because the scope of works was uncertain.

Issues

Subjects and remedies

home or building damagepay compensationrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 453857 Determination Page 1 of 6 Case number: 453857 19 December 2017 1 Overview 1.1 Dispute The applicant lodged a claim under her home insurance policy with the financial services provider (FSP) for water damage after she discovered a leaking pipe. The FSP engaged an engineer (PB) who recommended that a plumber be commissioned to resolve the suspected leaking pipe in the toilet and laundry and that the ground moisture should be allowed to dry out prior to completion of repairs. During the drying out period the applicant reported further cracking and jamming door which she attributed to the leaking pipe. The FSP has accepted claim for some of the damage but considers other damage unrelated to the claim event and caused by seasonal ground movement over an extended period of time, which is excluded from cover. 1.2 Issues and key findings Is the FSP liable for the extra damage to the property? The available information establishes that some of the extra damage to the applicant’s property was caused by the leaking pipe in April 2015. Accordingly, the FSP is further liable for the damage determined by JK. Is the applicant entitled to compensation? The applicant has offered to cash settle the claim for $47,050.60. Based on the FSP’s builder quotation (PI) and the recent scope of works by the FSP’ s builder (JL). This sum is insufficient. 1.3 Determination The determination is partially in favour of the FSP. The FSP is entitled to reject cover for some of the additional damage sought by the applicant. The FSP must complete the repairs as set out in the FSP’s email to FOS dated 27 November 2017 and repair the extra damage determined in JK’s report. The FSP shou ld reimburse the applicant for the cost of JK’s report, upon presentation of the invoice by the applicant. Case No: 453857 Determination Page 2 of 6 2 Reasons for determination 2.1 Is the FSP liable for the damage to the property? Policy provides cover for insured events subject to exclusions The applicant is required to show, that on the balance of probabilities she has suffered a loss caused by a risk insured against under the policy. This is known as a valid (prima facie) claim. If the applicant is able to establish a valid claim, then the onus shifts to the FSP to show that on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The applicant’s policy provides cover for damage caused by events listed in the policy, including the insured event of escape of liquid from fixed pipes, sinks, toilets and basins, subject to the conditions and exclusions set out in the policy. The parties are in disagreement about the cause of the damage The FSP appointed (R) to assess the loss of contents and on 19 May 2015 the inspection of the crawl space under the house disclosed water logging and puddles in low points. Drying equipment was installed in the affected areas to assist with the drying process and the excess water was removed. The FSP appointed an engineer (PB) who provided a scope of damage as follows:  suspected leaking pipes in sub floor area of toilet and /or laundry area – plumber to inspect and resolve leaking pipes, if no such pipe leaks are found then further investigate other possible water sources and resolve required  suspected leaking pipes has caused excessive moisture in found soils – allow ground moisture levels to stabilize prior to carrying out the remediation works outlined, (typically allow 4 to 6 months for stabilization)  heaved and up to ‘moderately’ cracked concrete slab – once ground moisture levels have normalized/slab crack with have stabilized undertake repair of concrete slab. The engineer carried out a follow up inspection on 10 February 2016 and noted as follows:  the leak has been repaired but a hole remains in the wall where access would have been gained  the external masonry walls of the house features some negligible cracking – cracking of this nature is considered consistent with the building of this age and is likely to have been caused by seasonal ground movement.  internal cracking was observed in various areas around the house including the plaster walls ceiling and cornices  during the inspection the owner mentioned that some doors and windows around the house were jamming. All doors were checked and was found that bedroom number 1 and the bathroom doors were both jamming the door to bedroom number 3 was not jamming however it was observed there was a gap between the door and the door frame of the top corner. It was noted that the bedroom window was tested and appeared to be functioning correctly. Case No: 453857 Determination Page 3 of 6  it was noted there was a slight dip in the flooring outside bedroom number 3  the concrete slab and stumps in the sub floor were inspected, the subfloor generally appeared to be dry  the engineer spoke to the son who advised that prior to the leak the owner’s husband had repaired some side cracks around the house. It was the engineers opinion that ‘moderate’ cracking and heaving of the cellar concrete slab has resulted from a swelling of the soil beneath, caused by altered ground moisture levels instigated by the leaking pipe in the toilet (and laundry room). ‘Also given the widespread nature of the internal and external cracking, previous crack repairs, and th e age of the house, it is the engineer’s opinion that additional reported damage is most likely to have been caused by seasonal ground movement over an extended period of time’. ‘It is plausible that some of the pre -existing cracking damage may have been made worse by the pipe leak. In our opinion, cracking damage that may have been made worse by the pipe leak includes cracking to the toilet, laundry and bathroom. All other reported cracking and jamming of doors inside the house are considered unrelated to the claim event.’ The applicant has raised the following concerns:  the wall cavity in the main toilet has been left exposed for almost 2 years and the FSP has not had anyone look at this for mould issues  the patching of the cellar floor with a epoxy fill is not acceptable and the damaged area should be brought back to its pre loss condition  (PI) builders advised they would not be willing to carry out and warrant the repairs to the concrete slab as it was a patch repair On 22 October 2015 the applicant contacted the FSP about additional damage she noticed around the house. This damage included:  cracks to the walls, the hallway and bedroom 2 and 3  bathroom doors jamming and not being able to close  mould in the wall of the cavity toilet The FSP rejects the additional damage and refers to the opinion of the engineer (PB) and that the damage is caused by seasonal movement over an extended period of time. Is there sufficient evidence to establish the water leaks have caused the additional damage? The applicant disagrees with the report provided by engineer PB. The applicant says that the cracking and door jamming did not occur until after the leaking pipe was discovered. PB’s report is substantial and provided by an expert in respect of the damage that has occurred to the premises. The information provided indicates that prior to the leaking pipe there were repairs carried out to the property. Case No: 453857 Determination Page 4 of 6 The applicant obtained a report from a consulting structural and civil engineer (JK). JK provided the following conclusions and recommendations: ‘As the site is located in Maidstone with reactive clays it is highly likely that movement has occurred in the past and this was clearly throughout the residency in the area where patching has had already occurred… However the are as we have seen have new lateral and compression cracking is indicated to bedroom 1, hallway, adjusted to area where the water leak occurred and the bathroom. The bathroom tiling has been cracking and the vertical plain of the tile looks to be shifted from west towards east, the vertical gap has increased considerably. Based on our observation this tile area needs to be removed totally and made good. Based on the degree of cracking that has been seen, it is this offices opinion that the new cracking that has occurred (lateral shift and compression cracking) due to some significant event (excessive water egress, flooding that occurred), meaning that stumps have heaved in certain location due to the swelling of the underlying clay. It is highly likely that the above cracking described has occurred as a result of the flooding that occurred and progressed throughout the southern portion of the house, unbeknown to the clients which was there for a long period of time.’ Based on all of the information provided by both the FSP and the applicant I am satisfied, on the balance of probabilities, some of the cracks to the walls of the bedrooms and hallway and the jamming of the doors was not as the result of the water leak but instead as the result of seasonal movement which is not an event covered by the policy. However I accept JK’s report and determine that the cracks to bedroom 1 and the hallway and the damage to the tiling and the bathroom is as the result of the initial leak. I note that the FSP raised a question o ver the qualifications of JK however I have confirmed JK holds registration with Victorian Building Authority and I am satisfied his experience and qualifications is sufficient for me to take due notice of his report. I confirm that FSP is required to cover the cost of repairing this damage including removal and making good all the tiles in the bathroom. Outstanding matters to be dealt with by the FSP Since the recommendation was made the FSP has offered a total cash settlement of $47,050.60. This offer does not take into account repairs required to address the issues raised in JK’s report. The FSP must r epair the damage as specified in clause 4 of the FSP’s email, to FOS, dated 27 November 2017, subject to any changes required to incorporate the repairs as set out in JK’s report. This email is set out in the next section. The report, from JK, provided by the applicant has influenced my decision and I therefore determine that the cost of this report should be paid by the FSP. Fairness, reasonableness and utmost good faith The information available, and in particular, the scope of works provides for several variations which will not be apparent until the repairs are commenced. The scope of Case No: 453857 Determination Page 5 of 6 works does not include the repair of the damage to bedroom 1, the hallway or to the tiling in the bathroom. Given the uncertainty, I do not believe it is fair in the circumstances for the FSP to cash settle the claim. The FSP must complete the works identified in clause 4 of the email dated 27 November 2017 addressed to FOS and set out in the email to FOS of 22 November 2017 which are as follows:  ‘A1 repair liability quote (AR attachment 3) in the sum of $33,260.79  AR liability quote (AR attachment 5) in the sum of $4,769.60  Mould remediation quoted by JL (AR attachment 6) in the sum of $6, 136.66  Repair to the crack in the hallway adjac ent to bedroom and additional grouting repair (AR 2 attachment 3) in the sum of $1,036.54 .’ The above quote should be adjusted subject to any changes required to incorporate the repairs as set out in JK’s report. Case No: 453857 Determination Page 6 of 6 3 Supporting information 3.1 Key records Record Key points FSP’s plumber (AL) Report 17 - 05 - 2015  Testing to washing mac hine in laundry and waste pipe found a drip external to the laundry when waste pipe was in use  Drip got worse as waste pipe was put under more pressure  Drip does not appear to be contributing to damages to sub floor. FSP’s engineer (PB) Report 05 - 05 - 2016  Given the widespread nature of the internal and external cracking, previo us crack repairs, and the age of the house, additionally reported damage is most likely to have been caused by seasonal ground movement over an extended period of time.  With the amount of previous patch repair work evident in the plaster walls, re - blocking of internal stumps and re - pointing of the mortar that these damages have most likely been occurring over an extended period of time.  Since a wall has reportedly been removed adjacent to the kitchen indicates that modifications have been made to the house in the past that have changed support to the ceiling in that area.  The additional damages reported after the initial inspection are most likely to have been caused by seasonal ground movement over an extended period of time and are not considered related to the claim event.  Although not the primary cause it is plausible that some of the pre - existing cracking damage may have been accelerated by the pipe leak.  Cracking damage that may have been made worse by the pipe leak includes internally, cracking to the toilet, laundry, bathroom and the sunroom plaster wall and stepped mortar cracking to the rumpus room, and externally stepped mortar cracking in the sout h east corner.  All other reported horizontal cracking and jamming doors inside the kitchen, dining roo m, living room and bedroom 1, 2 and 3 are considered unrelated to the claim event. Applicant’s Structural and Civil Engineer (JK) Report 11 - 10 - 2017  Areas with new lateral and compression cracking in bedroom 1, hallway and bathroom tiling  Bathroom tiling n eeds to be removed and totally made good.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.