Determination 453417

Tile matching after water damage repairs and repair delays

FirmFinancial Firm (Unknown - Insurer)
Decided2017-11-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$1,500
Amount claimed—
SourceAFCA PDF

Summary

Following water damage repairs, the applicant disputed a tile mismatch and repair delays that required nine months of temporary accommodation. AFCA found the policy's matching provision applied and ordered $1,500 for non-financial loss caused by delays.

The policy limits cover to repairing damaged parts only and excludes matching undamaged areas, and the FSP's agent's delays are attributable to the FSP.

Issues

Subjects and remedies

home or building damagepay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 453417 Determination Page 1 of 13 Case number: 453417 15 November 2017 1 Overview 1.1 Dispute The applicant lodged a claim under a home insurance policy held with the financial services provider (FSP) after discovering water damage to the walls and flooring in and around an ensuite bathroom. The FSP accepted liability for the resultant damage, and has undertaken associated repairs. A dispute has since arisen as to whether the FSP is liable for: 1. paying for (or contributing towards) the cost to rectify the mismatch that now exists where the old and new floor tiles meet at the hallway / kitchen doorway 2. paying the applicant compensation for non-financial loss in light of the length of time it took to complete the repairs which included a requirement for temporary accommodation, and its overall claim handling. 1.2 Issues and key findings Is the FSP liable to rectify the mismatching of the floor tiles? The FSP is not liable to rectify the mismatching of the floor tiles because:  the policy is clear in limiting the FSP’s liability to only replacing the damaged area of flooring, and not undamaged areas to create a uniform appearance  there is insuffi cient evidence to establish the FSP’s builder misled the applicant into believing any mismatching issue would be addressed following repairs. Is the FSP liable to pay compensation for non-financial loss? The FSP is liable to pay $1,500 compensation for non-financial loss because:  the applicant lodged the claim in April 2015, but repairs were only finalised in August 2016  the FSP’s builder caused significant delays (to the extent the FSP attempted to appoint another builder in February 2016)  the applicant ’s family were in temporary accommodation for nine months, four to five of which were a result of FSP related delays  the FSP erred in failing to keep the applicant properly informed of claim progress. 1.3 Determination This determination is partially in favour of the applicant. The FSP is required to pay compensation to the applicant in the amount of $1,500 for non-financial loss, but is not otherwise required to take any further action. Case No: 453417 Determination Page 2 of 13 2 Reasons for determination 2.1 Is the FSP liable to rectify the mismatching of the floor tiles? The policyholder is represented by her daughter (the applicant) in this dispute. For ease of reading, any reference to the applicant includes both the applicant and the policyholder. Floor tiling damaged and required replacement It is clear from the available evidence that extensive repairs were undertaken by the FSP as part of the applicant’s water damage claim. These repairs included the replacement of the damaged ceramic black and white floor tiles in the bathroom and hallway area. Original tiles no longer available There is no dispute the tiles originally laid in the applicant’s home were no longer available from commercial outlets. As a result, the applicant herself selected the replacement tiles to be laid in the affected areas. A mismatch now exists between the new hallway and original kitchen tiles There is no dispute that a mismatch is now evident between the new hallway tiles and the original kitchen tiles where they meet at the hallway / kitchen doorway. The mismatch is primarily a result of the new tiles having a higher level of sheen and an absence of the feint in-built pattern seen in the original tiles. FSP says applicant told of mismatch issue in advance and given alternatives With regards to discussions about the replacement tiles, the FSP’s builder summarises his recollection of these in an email set out in Section 3.2 below. In summary, he says:  he advised the applicant the original tiles were no longer available and as a result, there would be a matching issue  alternative options suggested to the applicant included laying completely different tiles, laying carpet or vinyl, or laying a floating or solid timber floor  the applicant elected to source the closest match of tiles they could find  prior to laying the tiles, he met with the applicant on-site to confirm the laying pattern and the nature of the doorway break where the original and new tiles would meet  at the request of the applicant, he also provided a quote to re-tile the kitchen and lounge area with the new tiles. Case No: 453417 Determination Page 3 of 13 Applicant says builder advised any mismatching could be raised with the FSP The applicant has also summarised her recollection of discussions about the replacement tiles in an email set out in Section 3.3 below. In summary, the applicant says:  she was advised that the original tiles were no longer available and would need to be custom made, but the cost of custom made tiles would exceed the overall claim allowance for tiling  she advised she would be willing to pay the price difference in order to maintain a uniform appearance, and had paid extra for other fixtures and fittings  the builder advised he would seek advice from the FSP regarding this, but heard nothing further  she was then asked why she had not yet selected any replacement tiles  she was subsequently advised to attend a tiling retailer to select the tiles, and an attempt to blend these with the original tiles would be made  the builder advised that if she was unhappy with the blending, this could then be raised with and addressed by the FSP. In essence, the applicant accepts being advised of a potential mismatching issue, but says she relied upon the builder’s advice that this could then be raised with and addressed by the FSP at a later date. Applicant needs to show a loss suffered based upon misleading advice Broadly speaking, the applicant must prove the following regarding an assertion that the FSP (via its builder) misled her:  the FSP’ s builder made a statement or engaged in conduct that was false or misleading (representation)  she relied on this representation to her detriment. Insufficient evidence to show builder misled the applicant I am not satisfied there is sufficient evidence to establish, on the balance of probabilities, the FSP’s builder misled the applicant because:  the available evidence suggests the applicant originally requested a quote to re- tile the kitchen and lounge area, and so inconsistent with a belief the FSP would rectify any mismatching issue  file notes relating to discussions between the applicant and the FSP from July to September 2016 make no reference to the applicant relying upon advice having been given to her by the FSP’s builder  these discussions primarily surround the level of mismatch now devaluing the home, and whether the hall/kitchen should be deemed one room for the purpose of the policy. For these reasons, I am not satisfied there is sufficient evidence to establish (on balance) the FSP’s builder actively misled the appl icant causing her to suffer a loss. Case No: 453417 Determination Page 4 of 13 FSP entitled to rely upon policy provisions regarding materials being matched In denying liability for the cost to rectify the mismatch issue now seen, the FSP relies upon the following policy provisions: Matching materials Under Buildings Insurance  we only repair the damaged parts of your home. We don't pay for materials to match the undamaged parts of your home to create a uniform appearance. Carpet, vinyl, tiles or floorboards Under Buildings Insurance and Contents Insurance  we only repair or replace the … tiles … in the part of your home that was damaged  we don’t pay for any adjoining rooms, or your entire home. The FSP says the hallway and kitchen constitute separate rooms for the purpose of the policy because they are separated by a doorway and door. Whilst the applicant acknowledges there is a doorway and door between the kitchen and hallway, she says:  the hallway is a continuation of the property and is not a new room or space  the door needs to remain open all times because the house has ducted air conditioning / heating. Whilst acknowledging the potential impracticalities of having the door closed, I am satisfied its existence means the hallway and kitchen are two separate rooms for the purpose of the policy. Therefore, the FSP was entitled to deem the hallway and kitchen separate rooms when considering the material matching provisions of the policy. Policy excludes consequential loss I also acknowledge the applicant’s advice that the tile mismatch ha s devalued the home. However, the policy specifically excludes consequential loss in line with the policy provision set out in Section 3.4. Therefore, the FSP has no liability for (or obligation to address) any devaluation suffered as a result of the mismatch issue now seen. FSP is not liable to rectify the mismatching of the floor tiles For all the reasons discussed above, I am satisfied the FSP has met its obligations under the policy and is not liable to rectify the mismatching of the floor tiles. 2.2 Is the FSP liable to pay compensation for non-financial loss? Applicant seeks compensation for non-financial loss The applicant seeks compensation for non-financial loss as a result of the time taken for the FSP to complete the repairs which required a period of temporary accommodation, and its overall claim handling. Case No: 453417 Determination Page 5 of 13 FOS awards non-financial loss conservatively FOS can award up to $3,000 for non-financial loss if the FSP caused the applicant to suffer an unusual degree or extent of inconvenience, delay or interference. It is important to note that an award is based on an unusual degree or extent. This would not encompass the normal degree of inconvenience a person would suffer when lodging an insurance claim or in a dispute with their insurer. FOS takes a very conservative approach when considering any award of compensation. I note the FSP did offer the applicant compensation in the amount of $1,000 during the course of the claim, but this was declined by her. FSP significantly erred in its repair timeliness and claim handling A detailed timeline of events in relation to the applicant’s claim is set out in Sect ion 3.1. From this timeline, the following becomes apparent: Date Activity April 2015  The applicant lodges the claim. May 2015  The FSP appoints its builder, BB, to undertake repairs. June 2015  BB identifies movement cracks and requests an engineer’s attendance. July 2015  The engineer attends site and provides a report and recommendations. August 2015  The FSP approves BB’s revised quote. September 2015  BB raises concerns regarding being able to warrant the repairs, but advis ed by the FSP to follow the engineer’s recommendations. October 2015  Repairs are delayed due to a family bereavement in the applicant’s family. November 2015  The applicant moves into temporary accommodation. November 2015 to March 2016  BB causes significant administrative delays to the extent of the FSP attempting to appoint a different builder. No repairs appear to have been complet ed during this period. March 2016 to August 2016  Repairs are completed, albeit completion timeframes given to the applicant are extended on a number of occasions.  The applicant moves back into the home. I acknowledge the significant delays throughout the claim were primarily caused by BB, and clearly acknowledged by the FSP in some of its claim file notes during February . However, as BB was the FSP’s appointed agent, it by default becomes liable for those delays. I also acknowledge that temporary accommodation became necessary due to the extent of repairs being undertaken. However, of the approximate nine months spent Case No: 453417 Determination Page 6 of 13 in this accommodation, four to five of these months were essentially unnecessary and a result of FSP related delays. It also appears a change of accommodation was required o n three occasions during this period due to the FSP not extending associated bookings in advance. With regards to communication between the parties, it is clear that on many occasions the applicant had to call the FSP to obtain updates. The FSP could have been significantly more pro-active in this regard. FSP required to pay compensation in the amount of $1,500 As stated above, FOS takes a very conservative approach when considering any award of compensation. However, for the reasons discussed above, I am satisfied the applicant has suffered a degree of inconvenience and delay beyond that which would ordinarily be expected. This is especially so considering the extended period of temporary accommodation. Therefore, I am satisfied an award of compensation for non-financial loss in the amount of $1,500 is appropriate in these specific circumstances. Case No: 453417 Determination Page 7 of 13 3 Supporting information 3.1 Timeline of events Date Activity 23 April 2015  Claim lodged by applicant.  FSP advises the cost to repair any leak is not covered, but resultant damage is. 5 May 2015  Applicant calls for an updat e.  FSP advises the cause of the water leak is unknown, and the plumbing report recommends a camera be placed down the ensuite sewer drain to determine the cause of the leak.  FSP advi ses any sewer pipe work will need to be rectified prior to addressing the resultant damage. 18 May 2015  BB report regarding damag e is received .  FSP calls BB who confirms the undamaged floor tiles in ensuite require replacement because the shower recess tiles need to be replaced and so leading to associated waterproofing requirements for the entire area.  BB also advised the damaged hallway tiles would be deemed a separate claim, but the applicant has some spa re tiles and may undertake replacement as private works.  FSP appoints BB to undertake ensuite repairs.  FSP calls the applicant to provide an update. The applicant advises a claim for the hallway tiles will not be made. 22 May 2015  FSP authoris es BB subcontractor L to undertake mould remediation works. 11 June 2015  FSP waiting on BB to commence repairs. 18 June 2015  BB advises the FSP of movement cracks being identified in the ensuite, and which requires the attendance of an engineer. At this stage, BB unable to warrant repairs. FSP appoints engineer CC. 19 June 2015  FSP sends CC a copy of the prior CCTV report. 25 June 2015  Applicant calls to advise no contact received from CC. FSP follows up CC. 10 July 2015  FSP follows up CC. CC advised it attended on 7 July, with a report expected in a week’s time. 4 August 2015  FSP re views CC’s report and sends a copy to BB.  FSP contacts applicant to apologise for the delay, but advises the claim is now progressing and awaiting repair quot e from BB. 11 A ugust 2015  FSP sends an email to BB to follow up on quot e. Case No: 453417 Determination Page 8 of 13 12 August 2015  BB advise it is waiting on a return call from the applicant to arrange re - attendance. FSP queries whether this is necessary in light of CC’s report. 21 August 2015  CC cont acts FSP querying a new allocation. FSP confirms it was made in error. 27 August 2015  FSP approves BB quote and provides an update to the applicant. 8 September 2015  BB advise the FSP regarding warranty concerns in light of the crack running through the ensuite slab.  FSP advises BB follow CC advice , and seek CC’s re - attendance once the ensuite is stripped out. 1 October 2015  BB advise the FSP repairs have been delayed due to an applicant family bereavement.  Applicant advises repairs can continue in two weeks. 15 October 2015  FSP seeks an updat e from BB. BB advises that applicant wants works to re - commence in late October and due to call on 19 October to confirm a date. 20 October 2015  FSP follows up with the applicant.  Applicant advises BB have been in contact, but mentioned about waiting on additional aut horisation.  FSP contacts BB who advise they are calling the applicant today. 7 November 2015  FSP attempts to get an update from both the applicant and BB. 17 November 2015  Applicant contacts FSP saying BB requested they make contact to arrange for temporary accommodation bec ause they are without a bathroom.  FSP identifies BB notes suggest accommodation required for a four week period subject to demolition removal.  FSP arranges accommodation quotes in line with applicant preferences. 18 November 2015  Accommodation confirmed until 15 December. 23 November 2015  FSP contacts BB for an update. BB advised bathroom has been ripped out and L will be attending for mould remediation works.  BB advises it will not be able to complete repairs and requests an engineer attend site.  FSP is unsure why an engineer is required (despit e CC’s report confirming this) and re - s ends BB a copy of CC’s report.  FSP waiting on advice from BB. 27 November 2015  BB advises th e crack in the slab could be a weak point and damage waterproofing membrane once laid. BB requests an engineer attend.  FSP arranges for CC to re - attend. 9 December 2015  Applicant calls for an updat e advising CC attended last Thurs day.  CC report confirms the crack in the slab is a result of the shower breach and will need to be repaired.  FSP requests call back from BB. Case No: 453417 Determination Page 9 of 13 14 December 2015  Applicant calls for an updat e and understands a revised scope of works is being arranged.  BB advised it tried to return c all to FSP, but on hold for an extended period. L is attending to mould remediation works, but CC’s report yet to be received.  BB advise the applicant will require temporary accommodation for some time yet.  FSP arranges an extension of accommodation to 1 F ebruary, although the applicant will be required to move to a different room. 4 January 2016  Applicant calls for an updat e. 6 January 2016  FSP follows up BB for revised scope of works. 11 January 2016  Applicant calls FSP requesting it forward CC’s sketch to BB.  FSP calls BB asking why it asked applicant to request the sketch and did not follow up itself. BB advised it had been on hold for over an hour to the FSP. FSP forwards the sketch to BB. 12 January 2016  FSP emails BB to confirm receipt of the sketch and requesting an update. 13 January 2016  Applicant calls for an updat e as the accommodation provider advises rooms are being booked out if the applicant will require a further extension.  FSP contacts BB which advises repairs are yet to commence a nd will take around t wo months.  FSP contacts applicant to provide an update. Applicant says it is a ‘little up and down’ with the house, but is okay. 14 January 2016  FSP emails BB requesting revised scope of works. 19 January 2016  Applicant calls for an updat e. FSP advises it is waiting on BB. 27 January 2016  Applicant calls for an updat e. FSP advises BB are waiting on a certified scope of works from CC.  FSP advises the applicants it is ‘sick of [BB’s] going back and forth with this claim’ and will follow up CC again.  FSP calls CC and advis es BB still not happy with the scope of works. CC will follow up.  FSP makes a file note: ‘Builder to start repairs – they are wasting time’. 2 February 2016  Applicant calls for an updat e. FSP advises revised scope of works was received yesterday and will be actioned in 24 hours. 3 February 2016  BB confirms a certified copy of the scope of works has been received advising how the works can be complet ed.  FSP notes BB is still delaying and ‘will discuss with tec h manager as I am getting sick of BB delays and constantly changing what they need. BB to advise if they are prepared to do the work as per the engineer’s instructions. If not, I will send to another builder – I am sick of BB wasting time.’  FSP provides an update to the applicant. Case No: 453417 Determination Page 10 of 13 8 February 2016  Applicant calls for an updat e and advises she wants to go home.  FSP says it is following up on this today and will call back with an update. 9 February 2016  FSP cancels repair allocation to BB and will allocate to JP.  FSP advises the applicant of this. 12 February 2016  Applicant ret urns FSP call, and advises she is waiting for repairs to commence. FSP advises it will be in contact later today or Monday. 15 February 2016  Applicant calls for an updat e. FSP advises it is in the process of allocating JP to the claim. 19 February 2016  FSP attempts to return applicant’s call.  FSP notes it is now unable to allocate repairs to another builder. It needs to look at an alternative method of repairs due to the crack in the slab. 23 February 2016  Applicant calls for an updat e. FSP advises BB is looking into repairs in order for the applicant to return home.  Applicant requests a call once a further update is available. 25 February 2016  Applicant calls to express dissatisfaction that she needs to keep calling for an update.  FSP advises it is still waiting to hear from BB.  Applicant says she will escalate the matter if she does not hear back from the FSP tomorrow. 29 February 2016  Applicant calls saying she has yet to hear from BB, and wishes to add her daughter to the claim.  FSP advises it has emailed BB and approved for a building consultant to attend and complete a new scope of works. March to April 2016  No FSP claim file notes due to the fact the applicant would be liaising directly with the builder. 22 April 2016  BB advises repairs are well under way and everything is running smoothly. 17 May 2016  Repairs are continuing with the applicant remaining in temporary accommodation. 24 May 2016  Applicant calls to advise she needs to be out of temporary accommodation today at 3PM, but repairs are still three weeks away from completion. She also advises she is unhappy with the lack of updates from the FSP’s assessor.  FSP confirms accommodation extended. 14 June 2016  BB advises the FSP a further two weeks before repairs are completed. 12 July 2016  Applicant calls to dispute mismatch of tiling between the kitchen and hallway.  Applicant says the door bet ween the rooms remains open b ecaus e they have ducted air conditioning / heating, and so the mismatch Case No: 453417 Determination Page 11 of 13 becomes very obvious.  Applicant understands the matching provision cannot be overruled, but would like to discuss with a manger. 15 July 2016  Applicant calls to follow up on a call back from a manger regarding the tiles. The applicant also advises the temporary accommodation will need to be extended.  BB advises the FSP repairs should be complet ed by 27 July.  Regarding the tiling, the FSP advises it does not cover matching costs and w ill send a letter to the applic ant confirming this. 25 August 2016  FSP calls applicant to discuss issues.  Applicant advises there were numerous occasions where expectations were set but not met, and it was a six week job that should have been completed in Dec ember 2015.  Applicant confirmed she was made aware of the matching provision and the issue with matching the tiles. However, there is a difference between the tiles which will always be visible and has devalued the house. 27 August 2016  Applicant move s back into her home on or around this dat e . 9 September 2016  FSP speaks with the applicant maintaining i ts decision regarding the tiling, but makes an ex - gratia offer of $1,000. 14 September 2016  Applicant calls FSP to discuss further.  FSP re - iterates the matching provision, but maint ains the ex - gratia offer.  Applicant maint ains the hallway and kitchen are not separate rooms despite there being a doorway and door because the hallway flows into the kitchen area.  Applicant says a real estate agent confirm s the property has been devalued as a result of the mismatched tiles.  Applicant suggests paying for labour, but the FSP contributes towards the materials.  FSP says the builder made the mismatching issue clear from the outset, and if the applicant had not a ccepted the proposed alternatives, it would have cash settled this aspect of the claim. Therefore, the applicant would remain in the same situation in that the kitchen tiles would still require replacement.  FSP confirms this discussion in writing. 3.2 Builder ’ s email regarding tile discussions In regards to your query the insured went to [tile retailer] and selected the tiles that were then installed. Please see below det ails. As we had advis ed the insured that the tiles could not be matched multiple options where provided to the insured- 1. Floating floor or solid timber in the hallway area. 2. Completely different tiles to be selected 3. Carpet or vinyl in the hallway area. The insured sourced their own tiles and placed a hold on them through [tile retailer] we simply arranged the quantities as required. Prior to laying tiles we met on site with the insured [Name] Case No: 453417 Determination Page 12 of 13 and confirmed the laying pattern and door way break where it was agreed that the tile would be laid in 45 degree alternating pattern similar to previous pattern and Black band of tiles would be placed on the doorway between the hallway and kitchen area. Despite advising the insured that matching was not a possibility the insured insisted on selecting closest match they could find. In addition as requested we provided the insured a quote for costing purposes to complete the Kitchen, lounge area. 3.3 Applicant’s email regarding tile discussions As requested here is the summary of events that had taken place during the repair of our hallway and two bat hrooms: - 1st builder came in and commenced the demolition that was required - advised us to go and choose the various materials including tiles - we inquired about tile matching and were notified that our current tiles would know longer be available but could be custom made - we want ed our hos e to remain consistent. Was advised that if they were custom made they would be approx double the pric e of our allowance through ins urance - we notified the builder we wanted the same tiles and would pay the difference if required he said he will pass this information to [FSP] to request a quote ( we did pay the difference for other fixtures and fittings such as tap ware as well) - first builder disappeared and did not continue work for numerous weeks - [FSP] assigned a new builder - Second builder came in and we notified him why we hadn't picked tiles yet. He told us to go to [tile retailer] to go and have a look - Second builder advised lets progress with the work to get us back in the home as soon as possible (we had already been out of home for over 3 months) with the tiles mum viewed as the closest to our current and they will try and blend them as much as possible and if we were un happy we would raise it and manage it with [FSP] - As the tiles were laid we expressed our concerns and the mismatch, they put a black boarder in the hall to try and blend the tiles. We stated we weren't happy with the outcome and the builder told us to now manage that with our ins urer. - Insurance advised that they will not cover the matching of tiles and we went around in loops - We then raised it with the FOS for review Personally, I believe the link in the chain that broke was the change over of builder with no communication and a lack of consistency between both builders and the case manger from [FSP] [sic] 3.4 Policy provisions How we settle certain things When we pay your claim, we settle certain things in line with the information shown in this section. Matching materials Under Buildings Insurance  we only repair the damaged parts of your home. We don't pay for materials to match the undamaged parts of your home to create a uniform appearance. Carpet, vinyl, tiles or floorboards Under Buildings Insurance and Contents Insurance  we only repair or replace the carpet, vinyl, tiles or floorboards in the part of your home that was damaged  we don’t pay for any adjoining rooms, or your entire home. Exclusions for all cover These exclusions apply to all cover under your policy. What we don’t cover …  consequential financial loss Case No: 453417 Determination Page 13 of 13

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.