Determination 452338

Cash settlement offer for rock-fall damaged garage

FirmFinancial Firm (Unknown - Insurer)
Decided2017-12-12
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$68,730
Non-financial loss$1,000
Amount claimed$68,730
SourceAFCA PDF

Summary

The applicant's garage damaged by a rock fall was to be replaced rather than repaired. AFCA ordered a cash settlement based on the builder's $68,730 plus GST quote, storage costs up to a cap, and $1,000 for non-financial loss.

The FSP's $37,739.39 cash offer did not allow the garage to be restored to its pre-incident condition, so the builder's quote is fair.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 452338 Determination Page 1 of 5 Case number: 452338 30 November 2017 1 Overview 1.1 Dispute The financial services provider (FSP) accepted the applicant‟s claim for damage to her garage. This was after a sewer pipe in the cliff face behind exploded causing rocks to fall on the garage. During the course of the claim, further damage occurred. The FSP has agreed to repair all the damage. However a dispute has arisen over the scope of works. The FSP has offered cash settlement on the basis the garage is repairable. The applicant‟s position is the garage requires demolition and rebuilding. 1.2 Issues and key findings Is the FSP’s offer sufficient? The FSP‟s offer is not sufficient because:  the garage should be demolished and replaced  the only builder who is prepared to undertake the works quoted the applicant $68,730 plus GST. Therefore, the FSP is to pay this amount minus what it has already been paid. Is the applicant entitled to consequential loss? The FSP should pay the applicant‟s c onsequential loss of vehicle storage costs from 1 May 2016 until the FSP pays the remaining amount owed for the garage damage. Is the applicant entitled to compensation for non-financial loss? The FSP is to pay $1,000 in non-financial loss. This is because the applicant suffered undue stress and inconvenience due to the FSP‟s handling of the claim. 1.3 Determination This determination is in favour of the applicant. The FSP is required to:  cash settle the applicant for $68,730 plus GST (less any sum already paid)  pay the applicant‟s vehicle storage costs from 1 May 2016 until payment of the above amount is issued – this is subject to FOS‟s compensation cap of $3,300  compensation for non-financial loss totaling $1,000. Case No: 452338 Determination Page 2 of 5 2 Reasons for determination 2.1 Is the FSP’s offer sufficient? FSP has decided to issue a cash settlement for the cost to repair the garage The FSP offered a cash settlement of $37,739.39 based on the quote of its repairer “SB” . SB declined to repair the garage as it says it is unable to warrant the works due to a number of issues. The applicant says the garage is not repairable and requires total replacement. She has obtained a quote for the replacement of the garage from her pr eferred builder “O” of $68,730.00 plus GST. Alternatively, the applicant requests SB carry out the repairs for the sum quoted by it. Policy entitles FSP to cash settle the claim The policy says the FSP can settle the claim in the following ways: “How w e settle your claim We choose how we settle home claims If we agree to pay a claim for loss, theft or damage to your home, we will decide if we will: • repair damage to your home; • rebuild your home; • pay you what it would cost us to repair or rebuild your home; • pay you the sum insured for your home; • give you a voucher, store credit or stored value card for the amount it would cost us to repair or rebuild an item.” Given this, it is clear the FSP has a discretion as to whether it will repair the damage or cash settle the claim. However, the exercise of a discretion must be used fairly, reasonably and consistent with the principles of utmost good faith. In determining whether to exercise the discretion to cash settle the claim, the FSP must take into account all reasonable factors. This includes the nature of the repairs required and whether a cash settlement would adequately ensure the applicant is able to properly complete all repairs. Significantly, by cash settling the claim, the risks associated with the restoring the property transfers from the FSP to the applicant. Further, by cash settling the claim, the FSP is relieved of its obligation to guarantee the work carried out. Further, any cash settlement should take a reasonable account for unk nown required repairs and variations. FSP’s offer does not adequately compensate the applicant The applicant says that due to the extent of damage, she has been unable to find a builder prepared to complete the proposed repairs. It is the applicant‟s posit ion the garage requires complete replacement. The parties have each provided expert evidence in support of their respective positions. Case No: 452338 Determination Page 3 of 5 The FSP has relied upon engineer “MP”. MP inspected and reported on the damage subsequent to the further rock fall even t in early 2016. MP‟s report said: “Given the nature of the masonry pier rotation we believe that no reinforc ement is present, and if this pier only was damaged due to a vehicle impact or the like, we would recommend its entire replacement. Given t he nature of damage at the rear corner, shown below we also suspect that the rear cavity wall has been somewhat compromised. The side wall is only single leaf and therefore propping while each end is reconstructed is likely to cost more than demolition and rebuilding, certainly given the extent of backfill now being supported by it. We therefore recommend an allowance be made to reinstate half of the entire masonry.” MP has prepared a detailed scope of works for the proposed repairs. MP notes the scope is not exhaustive and therefore an allowance for contingencies in calculating any cash settlement offer is appropriate: “Any additional loose or fractured areas of masonry discovered during the works shall be reported to the repair co-ordinator who may refer the matter to the Engineer for a determination of the extent of any additional demolition and reconstruction that may be required, before proceeding with that portion of rebuilding.” Further, MP said: “We understand that the owners‟ (sic) ha ve had difficulty organising anyone to stabilise the slope rear of the garage while the garage is still present. It is therefore a case of no rectification work being able to proceed until the slope is stabilised and the slope cannot be completely stabili sed until the garage is completely removed.” The fact the scope of works are not complete is relatively consistent with SB‟s refusal to proceed with repairs. SB cited the following factors when explaining why it cannot warrant the works:  the applicant is required to stabilise the rear upper rock face and clear out all subsided sediment against the perimeter walls  prior to reconstruction, the applicant is to ensure adequate site drainage around the entire garage structure  SB is unable to comply with MP‟s requirement for a thick membrane to be installed at the rear wall as only half of it was scoped to be rebuilt  MP‟s specifications for the new tiled roof pitch of seven degrees cannot be followed through with as it is not in accordance with manufacturer‟s specifications. As a minimum, SB‟s last two points highlight gaps in MP‟s scope of works. FSP should settle the claim based on O’s quotation The applicant notes she is unable to address the drainage issues around the garage as the repair quote only allows for replacement of one half of the rear wall. This means she does not have access to the existing drainage system. The report provid ed by the applicant‟s builder, O, confirms:  the perimeter walls have shifted from the base footings  the three front piers housing the roller shutters have altered off their footings  as a result of the extensive and significant damage the garage will need to be demolished and reconstructed  the slab is showing unstable signs of cracking and the size of the slab thickness, steel and strength cannot be determined – therefore new footing and slab needs to be constructed with tie down rods and up turn starter bars for strength and stability. Case No: 452338 Determination Page 4 of 5 The FSP has been provided with O‟s report. The FSP has provided no evidence to contradic t O‟s findings or asserted the estimate for the cost to demolish and rebuild the garage is either unfair or unreasonable. The available evidence shows the garage cannot be restored to its pre -incident condition without stabilising the rock face and allowi ng drainage works being carried out. All of the information says this cannot be done whilst the garage is in situ. Given all this, I do not accept the FSP‟s offer would allow the applicant to repair the damage sustained to the garage. Therefore, I prefer t he applicant‟s position. It is supported by O. O is the only contractor prepared to do the necessary works to restore the garage to its pre- incident condition. Accordingly, it is fair in all the circumstances the FSP cash settle the applicant‟s claim based on O‟s quotation. 2.2 Is the applicant entitled to recover consequential loss? FSP to pay for storage costs from 1 May 2016 Due to the garage damage rendering it unusable, the applicant has had to make alternative arrangements for the storage to her vehicle. The applicant is seeking reimbursement of this cost. Pursuant to paragraph 9.3 of the Terms of Reference (TOR), FOS may make an award for consequential financial loss if it is reasonable in the circumstances. This can include where an applicant su ffers a financial loss due to an insurer‟s failure to comply with its policy obligations. In this case, the applicant‟s claim followed a sewerage leak that was required to be repaired by the responsible authority. This did not occur until early March 2016. It is clear this leak had to be addressed before repairs to the garage could begin. Therefore, I do not accept the FSP is liable for the storage costs incurred during this period. Following the repairs to the sewer pipe, it is reasonable to accept the FSP would do the following:  inspect the damage and provide a scope of works  obtain quotations to complete the scope of works  issue a payment to the applicant. In this case, it took the FSP almost two months to complete all this. This timeframe appears reasonable. However, as the amount offered by the FSP was not sufficient for the garage damage, then I accept the applicant‟s storage costs incurred from this point onwards was due to the FSP‟s failure to adequately compensate her. Given this, the FSP is requi red to reimburse the applicant‟s vehicle storage costs from 1 May 2016 until the FSP pays out the remaining amount owed for the garage damage. Any amount payable is subject to FOS‟s compensation cap of $3,300 and the applicant producing invoices in support. Case No: 452338 Determination Page 5 of 5 2.3 Is the applicant entitled to compensation for non-financial loss? FSP’s handling of the claim was unreasonable The applicant says she was provided with limited assistance from the FSP as a „clean - up crew‟ was arranged to assist that did not attend and the applicant was left to deal with effluent and asbestos disposal. The FSP provided FOS with a copy of its claim notes. These indicate the applicant complained on numerous occasions about the lack of communication on the claim, with responses not being received within promised timeframes. It is also apparent the make- safe works undertaken by the FSP‟s contractor were only temporary in nature and unlikely to be suitable whilst the leak remained unrepaired. This is evident by the additional damage that occurred. FOS can award compensation up to $3,000 for non-financial loss where there is:  an unusual degree or extent of physical inconvenience  time taken to resolve the situation  interference with the a pplicant‟s expectation of enjoyment or peace of mind. Any amount awarded will depend on the degree suffered. For instance, the more extreme the circumstances experienced by an applicant, the higher the amount to be awarded. Further, FOS awards non-financial loss conservatively. I accept the FSP‟s handling of the claim has caused an unusual amount of delay in resolving the claim and interference with the applicant‟s peace of mind. Given this, and taking into account FOS‟s conservative approach, I accept the FSP should pay the applicant $1,000 in non-financial loss.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.