Text of the determination
Determination
Case No: 452061 Determination Page 1 of 6
Case number: 452061 15 June 2017
1 Overview
1.1 Dispute
The dispute relates to credit facilities the Financial Services Provider (FSP) provided
to the Applicants. The Applicants are a company (Company) and Mr B in his capacity
as an individual borrower. Mr B is also the controlling director of the Company.
The Company‟s claims are in relation to funding for a development project which
included a proposed service station, retail outlets and other constructions at its D
Avenue site (Project). Mr B‟s claims relate to his Loan #3843 that financed his 35%
share in a motel business (Motel Loan).
The Case Manager provided the parties with a Recommendation dated 4 April 2017
on the issues in dispute. The Recommendation was substantially in favour of the
FSP. A copy of the Recommendation is attached to this Determination.
1.2 Issues and key findings
Were the findings of the Recommendation correct?
The findings contained in the Recommendation were correct and are adopted in this
Determination . Further submissions provided after the Recommendation have been
considered.
As the Recommendation appropriately dealt with the claims raised by the Applicants,
I do not propose to repeat them in this Determination.
Do the Applicants’ submissions change the outcome of the dispute?
The Applicants‟ submissions do not change the findings in the Recommendation but
the amount of non-financial loss is increased.
In relation to the Motel Loan, the further submissions do not change the findings
because:
any obligation on the FSP to advise the Guarantors of the Motel Loan status are
obligations owed to them, and not Mr B. FOS cannot consider any claim in this
regard as the Guarantors are not parties to this dispute and
any loss of employment claim by Mr B cannot be considered by FOS because
the Management Agreement was in the name of a separate company, BREPL.
It did not receive the financial service (ie. the Motel Loan) from the FSP as Mr B
personally received the loan. The claim is more appropriately dealt with in a
court in any event
Case No: 452061 Determination Page 2 of 6
FOS cannot otherwise review the FSP‟s commercial decision not to renew the
Motel Loan beyond its expiry date of 29 July 2016. Under the Terms of
Reference, FOS cannot review th e FSP‟s assessment of credit risk posed by a
borrower. Upon expiry, the full balance became due and payable immediately
under the Motel Loan terms and conditions, and the FSP was entitled to impose
the pre-agreed default interest rate. This was previously disclosed to Mr B in the
Motel Loan contract.
However, the FSP was obliged to provide Mr B with notice of the Motel Loan expiry
at least on the same day it took effect, which it did not do. The FSP should therefore
pay an additional amount of $500 in non-financial loss to Mr B for stress and
inconvenience.
1.3 Determination
This Determination is substantially in favour of the FSP.
Based on all the available information, I agree with the Recommendation and the
recommended outcome, except that I make an additional award for non-financial
loss.
If the Applicants accept this Determination, the following will apply:
The FSP is not required to pay any compensation to the Company
Within seven days of the Applicants‟ acceptance, the FSP should pay $1,500 in
non-financial loss to Mr B by reducing his personal debt. The non-financial loss
is based on the following errors:
o $250 as a result of not providing copies of requested documents to Mr B‟s
solicitor within 30 days, as required by the Code of Banking Practice
o $750 as a result of its uncooperative behaviour regarding the buyout of Mr
B‟s motel business share by his partners, and
o $500 as a result of not providing Mr B with notice of the Motel Loan expiry
at least on the same day it actioned the loan expiry.
The FSP is entitled to commence any collection or recovery action for the
repayment of the cancelled or expired facilities, including enforcing the Deed
terms, once the FOS dispute is closed.
Case No: 452061 Determination Page 3 of 6
2 Reasons for Determination
2.1 Were the findings in the Recommendation correct?
The Recommendation was accurate
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
Recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties.
I am satisfied that the Case Manager‟s Recommendation contains an accurate
summary of the dispute, the issues to be determined, a ny applicable paragraphs of
the Terms of Reference and any relevant law.
As the Recommendation appropriately dealt with the claims raised by the Applicants,
I do not propose to repeat them in this Determination.
2.2 Do the Applicants’ submissions change the outcome of the dispute?
The Applicants rejected the Recommendation
The Applicants rejected the Recommendation for the following reasons:
In relation to the Motel Loan, the FSP did not follow correct procedure or act in
accordance with the relevant terms and conditions when it cancelled this loan
There are two aspects not considered in the Recommendation:
o The Motel Loan expired previously but the FSP automatically renewed it
for a further three months without notice. It did not do so in August, even
though the Motel Loan was never in arrears.
o The FSP did not issue any correspondence that the Motel Loan was in
default or cancelled because it cannot do so while the FOS dispute is
open.
In relation to the Motel Loan, Mr B has provided a copy of a letter from the FSP
dated 7 March 2006. It states the FSP will “… advise all guarantors immediately
should any of the loans &/or any of their accounts relating to the hotel, become
30 days irregular”. It is signed by Mr B authorising the FSP to advise the
guarantors of the above.
It was the FSP’s commercial decision whether to renew the Motel Loan
The Motel Loan Contract states the Loan was to expire on 31 March 2016. On 11
May 2016, the FSP issued a notice to Mr and Mrs B, informing them of changes to
the Motel Loan. This included a new expiry date of 29 July 2016. I note that this is
contrary to Mr B‟s claim the FSP automatically renewed the Motel Loan without
notice. The FSP was required to provide notice of any renewal, in accordance with
the Motel Loan terms and conditions.
Case No: 452061 Determination Page 4 of 6
Under the new expiry date for the Motel Loan, it was set to expire on 29 July 2016.
There is no correspondence indicating the expiry date was extended beyond that
date. However, the FSP confirms it did not action the loan expiry until 8 August 2016.
The fact of a previous extension does not impact on the FSP‟s rights under the terms
and conditions to decline to extend the Motel Loan for a further term.
It i s the FSP‟s commercial decision whether or not it will renew a credit facility, based
on its credit risk assessment criteria and lending policy guidelines. Under paragraph
5.1(c) of FOS‟s Terms of Reference, FOS does not have the power to re view the
FSP‟s credit risk assessment of its borrowers, including any decision to decline to
extend the Motel Loan.
When the Motel Loan expired, the full outstanding balance became due and payable
immediately. As the full loan balance has not been repaid, the Motel Loan is in
default. Under the terms and conditions of the Motel Loan, it is irrelevant whether or
not the Motel Loan was in arrears before it expired.
The FSP gave notice to Mr B on 17 August 2016 of the Motel Loan expiry
On 17 August 2016, the FSP sent an email to Mr B advising that the Motel Loan had
expired, and advising that he should consider his options to refinance it. Mr B
confirmed receiving this email on 19 August 2016.
The FSP says that although the Motel Loan has expired, it has not been cancelled.
The FSP confirms that it has not sought to enforce the Partners‟ guarantee (as
security) or sought to recover the outstanding Motel Loan debt at this time.
Accordingly, it has not issued any notices to the Partners that the Motel Loan is in
default.
It is correct that the FSP cannot commence recovery action while this FOS dispute is
on foot.
The FSP did not give notice in accordance with the Motel Loan terms
The Motel Loan terms and conditions entitled the FSP at any time to cancel it, or
reduce the Loan limit (including to zero). The terms and conditions also provide that
the FSP is required to give notice no later than the date the change takes effect.
The FSP‟ s email dated 17 August 2016 does constitute a notice, but it was not
provided to Mr B on the same day it took effect. The FSP says it actioned the loan
expiry on 8 August 2016, but it did not provide notice to Mr B until 17 August 2016.
Therefore the FSP did not act in accordance with the Motel Loan terms and
conditions when it allowed the facility to expire.
Accordingly, the FSP should pay an additional amount of $500 in non-financial loss
to Mr B for the stress and inconvenience this caused.
Mr B has referred to clause 16.2 of the Motel Loan terms and conditions, saying the
FSP was required to:
provide at least 30 days written notice before introducing or varying a fee,
charge or interest rate. He says the FSP should have provided such notice
before imposing default interest or
Case No: 452061 Determination Page 5 of 6
provide at least 10 business days‟ notice if the FSP makes any variation to the
Motel Loan.
These provisions do not apply in this case because the FSP was not imposing a new
or increased fee, charge or interest rate that it had not already disclosed to Mr B in
the Motel Loan contract, terms and conditions, and notice of variation.
The FSP‟s notice of variation dated 11 May 2016, provided the loan expiry date of 29
July 2016 and the applicable interest rate of 5.2% per annum. The Motel Loan
contract disclosed the default margin rate was 4.5% in addition to the applicable
interest rate. The FSP did not vary the Motel Loan when it expired, rather it imposed
the pre-agreed default interest. The FSP was exercising its pre-existing contractual
rights under the Motel Loan contract, which were previously disclosed and agreed by
Mr B.
Mr B informed the Guarantors (Partners) of the status of the Motel Loan
Mr B has provided a copy of a letter from the FSP to the Motel Loan Guarantors
(Partners) dated 7 March 2006, signed by Mr B and his wife (as co-borrower). The
letter states the FSP will “… advise all guarantors immediately should any of the loans
&/ or any of their accounts relating to the hotel, become 30 days irregular”.
There is no information indicating the FSP advised the Guarantors of the Motel Loan
status. However, as outlined in the Recommendation, it appears Mr B informed the
Partners on or around 22 August 2016 about the status of the Motel Loan. It appears
they also began negotiations about whether to refinance or sell Mr B‟s share in the
motel business. This was three days after the FSP‟s email advising of the loan
expiry. Accordingly, Mr B was in no different position whether or not the FSP advised
the Guarantors of the loan status.
In any event, the FSP‟s obligations in this regard are owed to the Guarantors and not
the Company or Mr B directly. Any claim in this regard can only be made by the
Guarantors against the FSP. As they are not parties to this dispute, FOS cannot
consider this aspect of the dispute further or award compensation to the Company or
Mr B in this regard.
FOS cannot consider Mr B’s claimed loss of employment
Mr B‟s submi ssions do not change the outcome that FOS cannot consider his claim
for loss of employment.
As outlined in the Recommendation, the Management Agreement was not entered by
Mr B in his individual capacity but rather in the name of a company, BREPL. BREPL
is a separate legal entity to the Company and Mr B.
Under FOS‟s Terms of Reference, FOS can only consider a dispute lodged by an
applicant about a financial service provided to the Applicant by a financial services
provider. In this case, the financial service (the Motel Loan) is provided to Mr B and
not BREPL. Accordingly, FOS does not have jurisdiction to consider BREPL‟s claim
for loss arising from the termination of the Management Agreement. As the apparent
decision by the Partners to terminate BREPL‟s ro le necessarily involves a number of
Case No: 452061 Determination Page 6 of 6
factors and FOS is not able to obtain information from the relevant parties, the issue
is more appropriately dealt with in court in any event.
Recommendation
Case No: 452061 Recommendation Page 1 of 20
Case number: 452061 4 April 2017
3 Overview
3.1 Dispute
The dispute relates to the Applicants‟ credit facilities with the FSP. The Applicants
are a company (Company) and Mr B in his capacity as an individual borrower. Mr B
is also the controlling director of the Company. The Company‟s and Mr B‟s relevant
credit facilities with the FSP are summarised in section 3.1.
The Company‟s claims are about a service station and retail development and
construction project at its D Avenue site (Project). Mr B‟s claims relate to his Loan
#3843 that financed his 35% share in a motel business (Motel Loan).
The main claims raised in the dispute are that the FSP:
acted unconscionably in its dealings with the Company by breaching an
agreement with it to see the Project through to completion
forced the Company to enter into a Deed of Forbearance in May 2016 (Deed)
under duress
is wrongly withholding sale funds from two security properties sold by the
Company which it requires to meet its resulting Capital Gains Tax (CGT) and
Goods and Services Tax (GST) liabilities
is incorrectly treating the Motel Loan as a credit facility in default.
3.2 Issues and key findings
Did the FSP act unconscionably in its dealings with the Company by breaching
an agreement to see the Project through to completion?
Based on the available information, the FSP has not acted unconscionably in relation
to the Project:
The FSP was entitled to cancel the Company Facilities at any time, and it
provided the required notice when it did so on 3 October 2013
There was no agreement (express or implied) that the FSP would see the
Project to completion, including construction of a service station at the site
The FSP was under no obligation to provide the Company with construction
finance for the development.
The FSP is not responsible for the Company‟s CGT and GST liabilities resulting
from the sale of two other security properties. The FSP is entitled to retain the
total net proceeds in exchange for the release of its mortgages.
The FSP provided the Company with over 12 months (since July 2015) in which
to refinance its debts with another credit provider, and obtain the development
approval as a condition of any refinance.
Case No: 452061 Recommendation Page 2 of 20
The FSP was under no obligati on to accept the Company‟s private financing
proposal. The FSP was entitled to protect its security interests (first priority
mortgages).
The FSP and Company only entered into a Deed of Forbearance in May 2016.
The Company did not enter into under duress. The FSP did not engage in illegal
or illegitimate pressure. The Deed was also negotiated between the Company‟s
solicitor and the FSP over three months.
The FSP did fail to provide copies of loan documents requested by the Company‟s
solicitor on 18 August 2016 (after the Deed expired) within 30 days. There is no loss
to the Company resulting from this breach. However, the FSP should credit $250 to
the Motel Loan as compensation for the stress and inconvenience its failure to
provide loan documents in Mr B‟s personal name.
Has Mr B defaulted on the Motel Loan?
The Motel Loan expired on 29 July 2016. The FSP notified Mr B of this on 17 August
2016, but has not yet cancelled the Motel Loan or demanded its repayment or made
any demand for it to be repaid.
It app ears the FSP has not been cooperative with Mr B‟s requests for it to consider
the Partners‟ buyout offer. It acknowledges it did not respond to Mr B‟s email in this
regard. The FSP should credit $750 to the Motel Loan as compensation for the stress
and inconvenience its failure to communicate has caused Mr B.
FOS cannot consider Mr B‟s loss of employee claim due to FOS‟s jurisdictional
limitations.
3.3 Recommendation
This Recommendation is substantially in favour of the FSP.
If both parties accept this Recommendation, the following will apply:
The FSP is not required to pay any compensation to the Company
The FSP should pay $1,000 in non-financial loss to Mr B as a result of its
un cooperative behavior regarding the Partners‟ buyout of Mr B‟s motel business
share
The FSP is entitled to commence any collection or recovery action for the
repayment of the cancelled or expired facilities, including enforcing the Deed
terms, once the FOS dispute is closed.
Case No: 452061 Recommendation Page 3 of 20
4 Reasons for Recommendation
4.1 Did the FSP act unconscionably in its dealings with the Company by
breaching an agreement to see the Project through to completion?
The Company has been undertaking its Project since at least 2006
The Company says the FSP provided it with lending for its commercial development
project, consisting of the following to be designed, constructed and leased on the
Company‟s D Avenue site (Project):
a bulky goods retail outlet (completed but not tenanted)
a petrol service station (development approved for construction, with a 40-year
lease in place with a petrol station operator)
a car wash or fast food outlet (as a potential future development).
The FSP says that its initial lending to the Company for the Project in 2006 was to
refinance the Company‟s existing credit facilities with another credi t provider. The
FSP says it did not approve any construction finance.
The FSP cancelled three of the Company Facilities on 3 October 2013
On 3 October 2013, the FSP cancelled the Company Facilities 1, 2 and 3 (outlined in
section 3.1). On the same day, the FSP issued a Notice of Cancellation to the
Company, care of its accountant, stating:
The FSP has cancelled Company Facilities 1, 2 and 3 (outlined in section 3.1)
The limits of those facilities is reduced to zero, and
The Company must immediately repay the total amounts owing to the FSP.
The FSP was entitled at any time to cancel the Company Facilities under the relevant
terms and conditions (outlined in section 3.2). The FSP was required to provide
notice to the Company at least on the date the cancellation took effect. The FSP has
provided a signed declaration that the Notice of Cancellation was posted on 3
October 2013. At law, the notice was effective from the time it is posted.
The Company says the FSP acted unconscionably
The Company says the FSP acted unconscionably in relation to the Project following
the cancellation of the Company Facilities because:
The FSP elected to see through the completion of the Project when it was
unable to sell the D Avenue site at auction in December 2014.
The FSP has breached an enforceable, implied agreement:
o During an on-site meeting between the FSP and Company, the FSP said
„this is a joint venture, we are in it together and we will get out of it together‟
o The Company believed the Project would be completed jointly to the
satisfaction of all parties concerned.
The FSP only allowed the Company to apply for and obtain a development
approval from the local council (over a 12-month period) because it would add
approximately $1 to $2 million in value to the D Avenue site.
Case No: 452061 Recommendation Page 4 of 20
The Company voluntarily sold three of the security properties for the Company
Facilities to reduce debt. The FSP is now withholding funds required to pay the
Company‟s CGT and GST liabilities.
By December 2015, the FSP declined to further fund the completion of the
Project. Instead, the FSP sought for the Company Facilities to be refinanced or
repaid by 15 January 2016.
The Company was able to arrange private finance offered on a shared security
basis with the FSP. The FSP rejected the proposal.
In May 2016, the FSP forced the Company to sign a Deed of Forbearance
(Deed) under duress. The Deed required the Company to repay or refinance its
Facilities by 13 August 2016, or the FSP would appoint a Receiver over the
Company Facilities and securities (including security properties). The
appointment of a Receiver will leave a shortfall debt of around $1.7 million, and
require the Company to rescind its lease with a petrol station operator.
If the Project were completed, the total realisation would be $6.8 to $7.2 million.
The Company‟s solicitor requested copies of loan documentation and account
information on 18 August 2016. The FSP did not provide it until 19 December
2016 when prompted by FOS.
The Company, not the FSP, initiated the auction in December 2013
The FSP says that it did not attempt to auction any of the Company‟s security
properties, including the D Avenue site. Rather, it says that the Company arranged
the auction in late 2013.
The correspondence between the Company and various real estate firms
(summarised in section 3.5) indicates that the Company initiated the proposed sale of
the D Avenue site by auction, on the recommendation of those real estate firms.
Further, the correspondence indicates that the Company was exploring this process
before the FSP cancelled the Company Facilities on 3 October 2013, even as early
as 12 months prior to that date.
The Company withdrew the D Avenue site from auction before the auction date given
the prospect of there being no bidder. In its email to the FSP on 3 December 2013,
the Company indicated that it did so based on its real estate firm‟s advice.
The Company‟s correspondence to the FSP also confirms that the Company initiated
the auction:
“In October 2013, [Company] advertised the whole site for sale with [C] & [P]. FSP agreed with
this strategy and consented to payment of the $11,143.83 in advertising costs.
The property was pulled from the Auction list the day before the proposed auction when no
contracts had been taken. Feedback received from several interested buyers was that a lead
tenant was required for them to commit to any sort of offer and that [Council‟s] stance on
possible tenants was causing the property to remain vacant.
The property is still listed for sale however this isn‟t a realistic short term option”.
Case No: 452061 Recommendation Page 5 of 20
As the proposed December 2013 auction of the D Avenue site was not required by,
nor the process managed by, the FSP, FOS cannot hold the FSP responsible for the
process nor the decision not to proceed to auction.
The FSP provided the Company until March 2014 to find tenants
The Company stated that a lead tenant was required for interested parties during the
marketing campaign to commit to an offer to buy the D Avenue site.
The Company had also put forward two other options to sell the D Avenue site:
To subdivide the units into community title, for which it had prepared a draft
plan. The Company stated:
o The draft plan had been forwarded by C and Mr B to potential
tenants/buyers, with interest received from two possible tenants
o The plan will stay in draft as it is not feasible to outlay the costs to complete
without a tenant/buyer in place
o „If either [interested party] commit to lease or buy, it would be the intention
to go back to C to sell the property onto another developer‟
To lease the existing building and sell/lease vacant land
Following the cancelled auction, by the end of December 2013, the FSP was already
considering appointing a Receiver over the D Avenue site to recover the outstanding
Company Facility debts.
However, as outlined in the correspondence in section 3.5, the FSP provided the
Company with a further opportunity until March 2014 to arrange tenancies and to sell
the D Avenue site by private treaty.
The FSP‟s actions to allow the Company to make its own arrangements to exit the
Project and repay its outstanding debts under the Company Facilities were not
unconscionable. The Company Facility debts were already five months overdue for
payment. The FSP was entitled to commence recovery action.
There was no agreement by the FSP to see through the completion of the
Project
In April 2014, there was an on-site meeting at the D Avenue site between the FSP
and Company. The Company says during that meeting, the FSP said to it: „This is a
joint venture, we are in it together and we will get out o f it together‟.
The Company says that, by making this statement, the FSP entered into an
enforceable, implied agreement with it to see the Project through to completion,
including the construction of a petrol service station on the site. The Company says i t
believed the Project would be completed jointly between it and the FSP to the
satisfaction of all parties concerned.
The FSP has not at this time responded to a request for information about the
alleged statement.
The FSP, as a credit provider, does not have a fiduciary duty or responsibility to its
customer. The relationship is primarily contractual in nature and the FSP is generally
entitled to act in its own interest to protect its financial position. Given this, in the
Case No: 452061 Recommendation Page 6 of 20
absence of a clear agreement to the contrary, the FSP would not be taken to be a
joint business partner of a customer.
The circumstances surrounding the parties‟ April 2014 meeting suggest it is most
unlikely the FSP agreed to see the Project through to completion with the Company.
The F SP had cancelled the Company‟s Facilities on 3 October 2013, with $2,801,555
immediately due and payable. The FSP had provided the Company with a period of
six months to sell the D Avenue site at auction, and then to find tenants before
attempting to sell it again.
Any variation to the Company Facilities, including their reinstatement or the FSP‟s
forbearance from taking or continuing recovery action, would in the ordinary course
have been documented. There is nothing to suggest the FSP documented any such
variation or agreement. Further, any additional financing for construction would have
been subject to the FSP‟s lending policy and guidelines. Given the Company was
already in arrears of several millions of dollars), it is most unlikely that the FSP would
approve further funding. As it eventuated, the FSP subsequently declined approving
any construction finance in March, July and August 2015.
The FSP‟s contemporaneous records of the April 2014 meeting indicate that it
suggested the Company consider subdividing the site and selling the units
individually (as previously suggested by real estate firm FP). The FSP‟s records are
consistent with the Company‟s position that the FSP suggested this option at the
meeting. The FSP‟s records do not support the claim tha t it agreed to see through
the Project to completion. The Company has not in any event provided any detail
around the alleged agreement. What would be required by each party in order “to get
out of it together”? The alleged agreement would be bad for uncer tainty.
In relation to the Company‟s claim that it was an implied agreement, the statement
again does not satisfy the requisite elements of an implied agreement, as follows:
It is not an agreement that the FSP would reasonably make.
It would be detrimental to the FSP (with increasing unpaid debts owed to it) and
the Company (with its debts increasing the longer they are unpaid)
The existing Company Facility agreements between the FSP and Applicant
could operate completely without the statement being an implied term.
It is not an obvious agreement that would go without saying. Having regard to
the reasonable bystander test, the statement (if made) was more that the FSP
would work with the Company to exit the Project and recover its monies as soon
as possible.
It is not sufficiently clear what the statement means – what does „getting out of it
together‟ mean? What standard had been set to determine whether it was
complied with or breached?
It was inconsistent with the express written agreements between the FSP and
the Company. The statement would contradict the position at the time that the
Company Facilities had been cancelled, and the total outstanding balances
were overdue and payable.
Case No: 452061 Recommendation Page 7 of 20
The Company has not shown it was misled by the alleged statement to see
through the completion of the Project
Even if FOS were to consider a claim that the Company was misled by the FSPs
alleged statement, Company would need to show the following to succeed in a claim
of misleading conduct:
the FSP made a representation that was untrue
the Company acted in reliance on the representation
in relying on the representation, the Company is in a worse position than it would
otherwise be in if the representation had not been made.
However, on the available information, and in light of the following, FOS is not
satisfied that the Company would be in any different position even if it were misled by
the FSP:
It had been unable to sell the D Avenue site or find tenants for an extended
period of time since 2013
It was unable to refinance its debts with another credit provider in 2015
It was and is not in a position to pay its outstanding debts owed to the FSP.
The FSP allowed time for the development approval so the Company could
refinance with another credit provider
In May 2014, the Company informed the FSP that it had received a leasing proposal
from a petrol station operator. The Company ultimately entered into a 40-year lease
with the petrol station operator, which required the Company to construct a petrol
service station at the D Avenue site.
In July 2014, the FSP sought an independent assessment of the D Avenue site,
including leasing potential, opportunities to market the site for sale, and clarification
on current zoning. This was to enable the FSP to consider its security position and
the options presented by the Company. There is no mention of the development
approval adding $1-2 million to the land value, as claimed by the Company.
On 5 January 2015, the FSP and Company met to discuss a proposal for a petrol
station operator to lease the D Avenue site. This was subject to Council approval of a
development application, to be lodged within 3 months of 22 December 2014. It also
required the associated construction of a service station.
The Company requested the FSP to fund the proposed construction. The FSP
declined to approve any further finance. This was a commercial decision that the
FSP was entitled to make, in accordance with its lending policy guidelines. FOS does
not have the power to review the FSP‟s decision to decline approval of further
lending, or to compel the FSP to provide further finance to the Company.
The Company lodged the development application with the Council on 9 March 2015.
The FSP had advised the Company that would will not approve further finance for
construction on 22 March 2015.
In July 2015, the Company informed the FSP that it was arranging a refinance of all
Company Facilities with another credit provider. The FSP advised the „re -finance
would need to be for all facilities currently held with [it]‟. It appears that unconditional
approval from the other credit provider was also subject to the development approval.
Case No: 452061 Recommendation Page 8 of 20
On 12 August 2015, the Company re-lodged the development application with the
Council to address issues of concern to the Council. The Company conti nued to
update the FSP of the progress of its refinancing with another credit provider.
According to the FSP‟s email to the Applicant on 22 November 2015, it had agreed to
defer any enforcement action until 15 January 2016. This had the effect of giving the
Company a 12-month period to obtain the development approval and to seek
unconditional refinance with another credit provider.
The FSP is not responsible for the Company’s tax liabilities
To reduce its outstanding debts owing to the FSP, the Company voluntarily sold two
of its commercial properties (Ba Street and Bl Street) used as security for its facilities
with the FSP. The settlements took place on 2 September 2014. The Company
incurred capital gains (subject to CGT) and a GST liability which it is required to remit
to the ATO. The Company says that the FSP is withholding funds from the sales,
which it should release to the Company to meet its tax liabilities.
The FSP was entitled to receive the proceeds from the sale of the properties it held
as security in exchange for discharging its mortgages over the properties.
There is no obligation on the FSP to provide funds for the Company‟s CGT or GST
liabilities arising from the sale of its properties.
The FSP has not breached any obligation owed to the Company in declining its
request to release funds to meet the Company‟s CGT or GST liabilities.
The FSP was under no obligation to accept the private finance offer
The Company was unable to refinance with the other credit provider. Alternatively, it
had a private funding proposal on a shared basis with the private financier, which
required the FSP to give the private financier priority over its registered mortgages,
and receive no payment of any principal or interest on the Company Facilities.
The FSP was under no obligation to accept the private finance offer. This was the
FSP‟s commercial decision based on its risk, security and other internal policies,
which FOS does not have the power to review. The FSP was entitled to protect its
own security interests, having first priority registered mortgages. FOS does not have
the power to compel the FSP to accept the private finance offer.
The Company did not enter into the Deed under duress
In February 2016, the FSP began negotiations with the Company‟s solicitor o n the
terms of a formal forbearance arrangement. By 20 May 2016, the parties agreed to
the terms of a Forbearance Deed (Deed). This was signed by the Company on 20
May 2016.
The Deed provided that the FSP would forbear from taking enforcement action on the
Company Facilities and securities if the Company repaid its outstanding debts owed
to the FSP in full by 13 August 2016. The Company was ultimately unable to repay or
refinance its debts by that date.
Case No: 452061 Recommendation Page 9 of 20
The Company says that it entered into the Deed under d uress. However, for a claim
of duress to succeed in the circumstances at issue here, it must be established that
the FSP‟s conduct amounted to illegitimate or illegal pressure . A threat by the FSP
that it may exercise its legitimate legal or contractual rights would not be considered
illegal pressure. The FSP has been entitled to recover the total outstanding debts
owed to it since 3 October 2013.
Further, the Deed was negotiated by the Company‟s solicitor over a three -month
period. The solicitor had a fiduciary duty to the Company to act in its best interests,
including in negotiation of the Deed terms. If the Company had any concerns that it
was experiencing unlawful duress or about the terms, it had the opportunity to raise
this with its solicitor before signing the Deed.
There is no information to support a conclusion that the Company enter into the Deed
under duress.
The Deed terms are enforceable, including appointment of a Receiver
On 16 August 2016, the FSP issued a notice to the Company that:
the forbearance term had ended, and the Company had not repaid the
outstanding debts owing by 13 August 2016
all amounts owing by the Company to the FSP are immediately due and
payable
the FSP may, at its discretion, enforce the Company Facility agreements,
securities and the Deed without further notice (including appointing a Receiver).
The Deed terms are enforceable against the Company. The Deed provides that if the
Company does not repay its debts by 13 August 2016, the FSP has the right to
exercise recovery action, including appointing a Receiver. The FSP has not at this
time appointed a Receiver but is entitled to do so once the FOS dispute is closed.
The FSP failed to provide requested documents within 30 days
On 18 August 2016 and following the expiry of th e Deed, the Company‟s solicitor
wrote to the FSP requesting copies of the Company Facility documents and provision
of the Facility balances.
The FSP did not provide the requested docume nts to the Company‟s solicitor until 19
December 2016. This was after the FSP was prompted by FOS in this regard, and
the same documents were provided to FOS.
Under clauses 13.3(b) of the Code of Banking Practice 2013 (CBP), the FSP was
required to provide the requested documents within 30 days (given that original
documents came into existence more than a year ago but less than seven years ago.
The FSP has not complied with its obligation under the CBP. There is no loss to the
Company resulting from this breach. However, the FSP should credit $250 to the
Motel Loan as compensation for the stress and inconvenience its failure to provide
loan documents in Mr B‟s personal name. FOS‟s approach to non -financial loss is
outlined in section 3.3 below.
Case No: 452061 Recommendation Page 10 of 20
4.2 Has Mr B defaulted on the Motel Loan?
The Motel Loan financed Mr B’s share in a motel business
Mr B borrowed $1.835 million under the Motel Loan and used it to finance his and
Mrs B‟s 35% partnership share in a motel business. His partners are a company (AI)
and four individuals (collectively, the Partners), which together own the other 65%
share of the motel business.
The Partners provided a $1.905 million guarantee for the Motel Loan.
Under the Partnership Agreement, if any default occurs on the Motel Loan, the
Partners have a pre- emptive right to purchase Mr and Mrs B‟s proprietary rights in
the Motel land and premises, and their shareholding in the business.
The Motel Loan expired on 29 July 2016
The Motel Loan Contract states that the Loan was to expire on 31 March 2016. On
11 May 2016, the FSP issued a notice to Mr and Mrs B, information them of changes
to the Motel Loan. This included a new expiry date of 29 July 2016.
Mr B says that there is uncertainty about when the Motel Loan expired. This is
because the FSP‟s email to him (on 17 August 2016) said it expired on 12 August
2 016. Further, the FSP‟s response to FOS (on 23 December 2016) indicates it
expired on 8 August 2016.
Under the Motel Loan contract as varied, the Motel Loan expired on 29 July 2016.
There is no correspondence indicating that the expiry date was extended beyond that
date. Even if the FSP unilaterally and without notice allowed an additional one or two
weeks before the Motel Loan expired, that was to Mr B‟s benefit.
The Motel Loan is in default
The relevant terms and conditions for the Motel Loan are summarised in section 3.4.
Under clause 3.1(b) of the Motel Loan terms and conditions, Mr B was required to
repay the outstanding loan balance in full on the „Final Repayment Date‟. The „Final
Repayment Date‟ is defined as the last day of the „Facility Term‟, whic h ends on the
expiry date (that is, 29 July 2016).
As the full loan balance has not been repaid, the Motel Loan is in default. Clause
12.1(a) of the Motel Loan terms and conditions states that the loan is in default if Mr
B does not pay on time any amount due. Accordingly, the FSP is entitled to recover
the total loan balance owing without notice, and enforce any security. Further, the
FSP is entitled to charge default interest on the Motel Loan (under clause 12.3).
The FSP has not cancelled or called in the Motel Loan
The FSP says that, although the Motel Loan has expired, it has not been cancelled.
The FSP confirms that it has not sought to enforce the Partners‟ guarantee (as
security) or sought to recover the outstanding debt at this time. Accordingly, it has not
issued any notices to the Partners that the Motel Loan is in default.
Case No: 452061 Recommendation Page 11 of 20
The FSP gave notice to Mr B on 17 August 2016 of the loan expiry
On 17 August 2016, the FSP sent an email to Mr B advising that the Motel Loan had
expired, and he should consider his options to refinance it. Mr B confirmed receiving
this email on 19 August 2016.
Mr B says that the FSP has not issued any notices to his Partners (as guarantors)
that the Motel Loan is in default. However, the FSP has not sought to recover the
Motel Loan balance, cancel the Motel Loan, or enforce the guarantee.
Any issue about the FSP‟s requirement to issue notices to the Partners in relation to
Mr B‟s debt under the Motel Loan are not relevant to the Company and Mr B‟s
dispute. Accordingly, FOS cannot consider this aspect of the dispute.
Mr B appears to have informed the Partners of the status of the Motel Loan
In his email to the FSP dated 19 August 2016, and in the context of acknowledging
the FSP‟s suggestion that he consider refinancing the Mote l Loan, Mr B said:
“In this regard I wish to inform you that negotiations will begin wit h my partners on Monday
22nd August next to decide whether to refinance or sell the asset”.
This is consistent with Mr B‟s statement that he informed the Partners of th e status of
the Motel Loan as a matter of conscience. While Mr B may have a fiduciary duty to
the Partners to inform them of the Loan‟s status, the FSP has not made any recovery
demand on either Mr B and Mrs B, or the Partners.
As the Motel Loan has an outstanding debt and is in default, there is no basis for
FOS to hold the FSP responsible for the Partners‟ decision to enforce the Partnership
Agreement.
FOS cannot consider Mr B’s claimed loss of employment
Mr B has provided a copy of a letter from the Partners dated 16 February 2017. It
states that they are holding a meeting of the members of AI to consider the
termination of the Management Agreement with Mr B‟s company, BREPL, in respect
of the Motel.
Mr B says that this comprises is notice of the imminent termination of his employment
with the Motel. However, BREPL is a company (a separate legal entity) appointed as
manager of the Motel, and not Mr B in in his individual capacity. Any loss resulting
from wrongful termination of the Management Agreement is a claim to be made by
BREPL, not Mr B.
Under FOS‟s Terms of Reference, FOS can only consider a dispute lodged by an
applicant about a financial service provided to the Applicant by a financial services
provider. In this case, the financial service (the Motel Loan) is provided to Mr B and
not BREPL. Accordingly, FOS does not have jurisdiction to consider BREPL‟s claim
for loss arising from the termination of the Management Agreement.
Case No: 452061 Recommendation Page 12 of 20
It appears the FSP has not been cooperative with the Partners’ buyout of Mr
B’s share of the motel business
The following is correspondence between Mr B and the FSP about the Partners‟
buyout of his share of the motel business:
It appears the FSP has not been cooperative in providing a timely response to Mr B‟s
request for the FSP to consider and respond to the buyout offer. The FSP
acknowledges it has not responded to Mr B‟s emails in this regard.
The FSP should pay $750 as compensation for the non-financial loss in the form of
significant stress and inconvenience caused to Mr B by its failure to respond
appropriately to his requests about the Partners‟ offer. This amount should be
credited to the Motel Loan.
Date From / To Content
12 December 2016 Email – Mr B to FSP Mr B advised the FSP that he
received an offer for his
interest in the motel of $1.4
million.
It is being purchased by the
Partners under the terms of
the Partnership Agreement .
Mr B requested that the FSP
give consideration to
acceptance of this offer.
Mr B acknowledged he is
liable for the loan short fall of
around $300,000
11 January 2017 Email – FSP to Mr B Advised that Mr B‟s email had
been forwarded to the relevant
FSP staff members to contact
Mr B urgently
12 January 2017 Email – Mr B to FSP Requested urgent response
by FSP to offer made
16 February 2017 Letter – Partners to Mr B Buyout still not finalised;
contracts not exchanged
Case No: 452061 Recommendation Page 13 of 20
5 Supporting information
5.1 The Company’s and Mr B’s relevant credit facilities with the FSP
The Company’s credit facilities with the FSP (Comp any Facility)
Mr B’s Motel Loan with the FSP
5.2 Relevant terms and conditions for the Company Facilities
Specific and General Conditions for Company Facilities 1 and 2
3. CANCELLATION AND REDUCTION OF THE FACILITY LIMIT
Credit Facility Loan Amount Date Opened Date Expired Balance and
current status
(as at 17 March 2017)
1 - Market Rate
Facility #9690
$1,125,000 21 February 2013 2 December 2013 $1,939,269.76
($814,269.76 in
arrears)
2 - Market Rate
Facility #6504
$870,000 21 February 2013 31 March 2014 $1,421,510.48
($551,510.48 in
arrears)
3 - Business
Cheque Account
#7551 (with
Overdraft)
$60,000 21 February 2013 30 November
2013
$405,720.19
($345,720.19 in
arrears)
4 - Business
Options Interest
Only Loan #3340
$800,000 21 February 2013 N/A
(expires 31 December
2021)
$1,075,745.11
($275,745.11 in
arrears)
Total Lending: $2,855,000 Total
Outstanding
Debt:
$4,842,245.54
($1,987,245.54 total
arrears)
Credit Facility Loan Amount Date Opened Date Expired Balance and
current status
(as at 14 March 2017
Business Markets
Loan #3843
$1,835,000 6 August 2014 29 July 2016 $ 1,730,984
Case No: 452061 Recommendation Page 14 of 20
(a) [The FSP] may cancel the Facility or reduce the Facility Limit at any time, even if the
Facility has an Expiry Date and even if this means the new Facility Limit is lower than
the Balance Owing.
15. CHANGES TO THIS AGREEMENT
15.1 What [the FSP] can change
[The FSP] can, at any time:
(a) reduce any limit, including a Facility Limit, Debtor Limit and a Component Limit;
…
(h) make any change which [the FSP] is permitted to make under the Specific Conditions;
…
15.2 How [the FSP] will notify you of changes
[The FSP] will notify you of any changes it makes under clause 15.1 as follows:
…
(d) [The FSP] will notify you of any other change, by writing to you… no later than the date the
change takes effect.
Specific and General Conditions for Company Facility 3
3. CANCELLATION AND REDUCTION OF THE FACILITY LIMIT
(a) [The FSP] may cancel the Facility or reduce the Facility Limit at any time, even if the
Facility has an Expiry Date and even if this means the new Facility Limit is lower than
the Balance Owing.
…
16. CHANGES TO THIS AGREEMENT
16.1 What [the FSP] can change
[The FSP] can, at any time:
(b) reduce any limit, including a Facility Limit, Debtor Limit and a Component Limit;
…
(i) make any change which [the FSP] is permitted to make under the Specific Conditions;
…
16.2 How [the FSP] will notify you of changes
[The FSP] will notify you of any changes it makes under clause 15.1 as follows:
…
Case No: 452061 Recommendation Page 15 of 20
(e) [The FSP] will notify you of any other change, by writing to you… no later than the date the
change takes effect.
5.3 FOS approach to non-financial loss
FOS can only consider non-financial loss for individuals
Under FOS‟s Terms of Reference, FOS can consider claims for non-financial loss.
Non-financial loss claims include claims for stress or inconvenience caused by an
error of the Financial Services Provider (FSP). The maximum amount that can be
awarded for non-financial loss is $3,000 for each claim.
However, FOS takes a conservative approach to compensation for non-financial loss.
We are unlikely to decide a substantial amount of monetary compensation should be
paid (it would be in the hundreds of dollars rather than thousands of dollars).
FOS cannot award non-financial loss for companies
When a company lodges a dispute with FOS, it is the legal entity that makes a claim
for financial loss. The claim must be made by the legal representatives of the
company, that is, the directors of the company. However, the directors of a company
cannot make a claim for personal loss because the entity lodging the dispute is the
company. Therefore we cannot consider a claim by directors of a company for
inconvenience, distress or anxiety arising from the FSP ‟s conduct with respect to the
company‟s accounts.
5.4 Relevant terms and conditions for the Motel Loan
Specific and General Conditions for the Motel Loan
3. REPAYMENT AND PREPAYMENT
3.1 Repayment
…
(b) You must repay to [FSP] the Facility Amount Owing in full on the Final Repayment Date.
11. DEFINITIONS
For the purposes of these [FSP] Facility Specific Conditions:
…
Availability Period means, in respect of the Facility, the period from the date of this Letter of
Offer to the Final Repayment Date.
…
12. DEFAULT
12.1 When you are in default
Case No: 452061 Recommendation Page 16 of 20
You are in default if, in relation to a Transaction Document, or any other agreement you or a
Security Provider has with [the FSP] (each an “Arrangement” ):
(a) you or the Security Provider do not pay on time any amount due;
…
12.2 What can happen then? (Consequences of Default)
(a) Upon the occurrence of an Event of Default, [the FSP] may, at its option and without the
need to give any notice other than that required by law, treat the Total Amount Owing
as being payable immediately and may immediately or at any later time enforce any
Security.
…
12.3 Default Interest
(a) Unless otherwise stated in the Specific Conditions, you must pay [the FSP] default
interest charges on any part of the Balance Owing which is overdue (including amounts
which are drawn in excess of the Facility Limit). Interest charges payable under this
paragraph are calculated daily by applying the Daily Default Interest Rat e to the
overdue amount.
…
24. DEFINITIONS
…
24.2 Meaning of other terms
(a) These meanings apply to this Agreement, unless otherwise stated:
…
Facility Amount Owing means all money which you (whether alone or not) are, or at any time
may be, liable to pay [the FSP] under this Agreement in relation to a particular Facility, for any
reasons whatsoever including… money by way of principal, interest, fees, Costs, indemnity,
charges, duties or expenses…
…
Facility Term means:
…
(ii) for any other Facility, the period beginning on its Commencement Date (if any) or
otherwise on its First Drawdown Date and ending at the expiry of the Facility Term or the Expiry
Date (or the Extended Facility Term or the Extended Expiry Date, if applicable).
…
Final Repayment Date means in relation to a Facility the earlier of:
(i) the last day of the Facility Term (if any);
(ii) the date the Facility Limit is cancelled; or
Case No: 452061 Recommendation Page 17 of 20
(iii) the date the Facility is terminated or otherwise ends,
or if that day is not a Business Day, the next Business Day unless otherwise stated in the
Specific Conditions for that Facility or unless otherwis e agreed.
5.5 Relevant correspondence about the D Avenue site
About the 2013 auction
Date From / To Content
2 Octo ber 2013 Email - Company to real estate
firm (FP)
Company has been trying to
find tenants for D Avenue site
but several possible tenants
either have business activities
not permissible with zoning,
have preferred other sites, do
not have a franchise in pla ce,
and new business delayed
due to slow economic
conditions
„In order to achieve some
positive action with the
project, it is my intention to
submit it to market and see
what is out there‟.
Invited FP to make a sale and
marketing campaign
submission
11 October 2013 Email - Real estate firm (KF) to
Company
Provided sale and mark eting
submission for the sale of the
D Avenue site „on behalf of
[Company]‟
Suggested auction as the
most appropriate method of
sale
Advised they are selling an
unrelated third - par ty property
at auction on 28 November
and would like to run the D
Avenue site at the same time
to increase interest and have
the marketing completed
before Christmas
14 October 2013 Email - Real estate firm (FP) to
Company
Provided a brief outline of
pres entation, marketing and
auction proposal for the D
Avenue site
Also provided outline of
various sale options, including
Case No: 452061 Recommendation Page 18 of 20
strata titling the existing three
units; strata titling the existing
premises, land and car park;
and selling vacant land
25 October 2013 Letter – Real estate firm (C) to
Company
Provided marketing and sale
campaign submission
Suggested to sell by auction
on 5 December 2013
29 October 2013 FSP internal email Company has provided it with
copies of the marketing
proposals from three agen ts
Company wants to appoint C
to hold the auction on 5
December 2013
C needs to know today if
Company wants to go on its
listing
The D Avenue site has
multiple broken windows,
which C indicates needs to be
replaced before marketing
Total cost of the window
repairs are $9,360.
Company wants FSP to assist
with payment for the broken
windows and marketing costs
until the settlement of other
security properties that have
been sold
18 November 2013 Email – Real estate firm (C) to
Company
Provided marketing campaign
update for week 1
Had 11 enquiries on the D
Avenue site and currently
working closely with those
interested parties to firm up
their interest
2 December 2013 Email – Real estate firm (C) to
Company
„Early pricing feedback has
been received in the early $2 -
$2.5 million price range and
[C] are continuing to work
closely with the interested
parties to provide all market
insights including market
rents, leasing activities,
vacancies to assist the buyers
to complete their pricing
assessment‟.
Case No: 452061 Recommendation Page 19 of 20
Prospects of finding tenants following the unsuccessful auction
Advise s auction will be
unsuccessful because
interested parties will not
attend – „developers/investors
genuinely need to have extra
time to assess further on the
possibilities to lease bulky
good retails and taking into
consideration of the letting
time, leasin g incentive and
who are the prospective
tenants‟.
3 December 2013 Email – Company to FSP Forwarded copy of C‟s email
dated 2 December 2013
Company is taking C‟s advice
and not submit the D Avenue
site to an empty auction
However, enquiries suggest
there is a lot of scope
Mentions the possibility of
selling the existing building on
a community title basis, which
Company will follow up
Real estate firm (FP) has
been suggested this option for
12 mont hs
Two Bl Street properties to
settle in early January 2014 ,
which will release around
$670,000 in net proceeds for
the FSP in the short term
Date From / To Content
31 December 2013 FSP internal email „[I]f [Company] and his
appointed agents have not
been able to effect a sale or
obtain tenants so that the
rental is sufficient to meet
interest, the [FSP] will be
looking to appoint receivers
and managers in early
February‟
9 January 2014 FSP internal email „We don't feel that early
February will have given
[Company] & [its] Estate
Agents sufficient time to follow
Case No: 452061 Recommendation Page 20 of 20
up all leads and provide time
for negotiations/ visits to
[location] where necessary‟.
4 February 2014 FSP internal email [Company] and [FSP] have
been keeping in regular
contact noting t he mid - March
timeline if nothing substantial
is achieved regarding new
tenants
[Mr B] is being extremely
proactive in sourcing tenants
FSP put Company in contact
with a local GP, already wit h
four surgeries and two
pharmacies, always looking to
expand
Comp any has advertised the
D Avenue site in the local
news paper as a potential site
for a medical centre
This has resulted in the
Company being in contact and
negotiating with three
interested parties