Home / Financial Firm (Unknown - Credit) / Determination 451393

Determination 451393

delay

FirmFinancial Firm (Unknown - Credit)
Decided2017-02-06
ProductCredit · Home loan
OutcomeFor the complainant
Amount awarded$14,610
Non-financial loss$1,250
Amount claimed$30,303
SourceAFCA PDF

Summary

The FSP could not locate the title to the applicant's former property, delaying its settlement and the simultaneous purchase of her new home by about two weeks. AFCA decided in favour of the applicant and ordered compensation of $15,860.25 plus interest, of which $1,250 is non-financial loss.

The FSP is liable for losses that were reasonably foreseeable from its delay in settlement, and the applicant is put back in the position she would have been in without the breach.

Issues

Subjects and remedies

pay compensationpay interestpay non financial loss

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 451393 Determination Page 1 of 7 Case number: 451393 2 Februar y 201 7 1 Overview 1.1 Dispute The Applicant had a loan with the Financial Services Provider (FSP) secured over her former property. In 2016 the Applicant sold her former property and purchased another property using finance provided by a different lender (new lender). The dispute relates to the delay in settlement that occurred when the FSP was unable to locate the title to the Applic ant‟s former property. A timeline of key events is set out in section 3.1 below. The Applicant says that the sale proceeds from her former property were required at settlement to contribute to the purchase, so the sale settlement had to occur at the same time as, or before, the purchase settlement. The Applicant claims various costs incurred between 22 August and 5 September 2016 due to the delay. It is not disputed that a delay occurred, but the parties disagree on the amount of the Applicant‟s losses. The Case Manager provided the parties with a preliminary view on the issues in dispute on 18 November 2016. The preliminary view was in favour of the Applicant and a copy is set out in section 3.2 of this Determination. 1.2 Issues and key findings Were the findings in the preliminary view correct? The issues and findings identified in the preliminary view are adopted in this Determination . Further submissions provided after the preliminary view have been considered. For the reasons set out in section 2, the FSP should compensate the Applicant for the losses set out in the preliminary view. The further submissions from the FSP do not change that outcome. 1.3 Determination This Determination is in favour of the Applicant. If the Applicant accepts this Determination within 30 days, the FSP is to pay compensation of $15,860.25 plus interest from 6 September 2016 at a rate of 2.8% per annum on that amount until payment. Payment should be made within 14 days of being notified of the Applicant‟s acceptance of this Deter mination. It should be paid to a bank account nominated by the Applicant with her acceptance. Case No: 451393 Determination Page 2 of 7 2 Reasons for Determination 2.1 Were the findings in the preliminary view correct? The FSP rejected the preliminary view The preliminary view was accepted by the Applicant but rejected by the FSP. The FSP‟s reasons for rejection were that:  If the Applicant required the sale proceeds from the sale settlement to pay the “ deposit ” for purchase at the purchase settlement, the purchase settlement could not have been held simultaneously.  The FSP has not viewed the Contract of Sale to confirm: o whether any special conditions were included o that the sale proceeds from the sale settlement were required to pay a deposit at the purchase settlement.  The FSP did not cause the delay of the purchase settlement to be held on 5 September 2016. Accordingly, it considers that the loss for which it should compensate the Applicant is limited to the period between 22 and 26 August 2016. It is not disputed that the sale settlement was delayed by the FSP According to the email correspondence between the Applicant‟s solicitor and the FSP:  the FSP was informed on 9 August 2016 of the exchange of sale contracts on the Applicant‟s former property. The FSP also received a signed Discharge Authority on the same day from the Applicant‟s solicitor by email. The FSP had sufficient time to prepare for settlement.  the FSP told the Applicant‟s solicitor it had been trying to locate the title to the Applicant‟s former property since 18 August 2016. As a res ult, the FSP was unable to proceed with settlement on 22 or 24 August 2016. The FSP located the title to the former property on 25 August 2016. Settlement for the Applicant‟s former property was then set for and took place on 26 August 2016. The incoming lender required the sale settlement to take place first The FSP was not involved with the settlement of the Applicant‟s new property which was being financed by another credit provider. The Applicant has provided the unconditional approval letter from the new credit provider dated 20 July 2016. It confirms that the Applicant obtained a loan for $637,500, and also that it was a condition that the settlement of “… [th e Applicant‟s former property] h as to settle on or before [the Applicant‟s new property”. The Contract of Sale for the new property shows that the purchase price was $850,000. The Applicant has provided a copy of a deposit bond, showing that she paid the 10% deposit ($85,000) this way. The deposit bond needed to be repaid at Case No: 451393 Determination Page 3 of 7 settle ment for the Applicant‟s former property. The $850,000 purchase price less the $637,500 finance amount indicates that the settlement of the new property still required additional funds (around $212,500 plus fees and costs). The Applicant has confirmed she required around $225,000 from the sale proceeds from the sale settlement to contribute to the purchase settlement. Settlement on the new property was to occur simultaneously The FSP queries whether there was to be a simultaneous settlement of the Applicant‟s former and new properties or that a delay in one would have impacted the other. In addition to the information set out above, the Applicant has provided copies of emails between her and her solicitor dated 15 and 16 August 2016, which confirm the vendor on her new property was preparing to settle on 22 August 2016. Based on the available information, I am satisfied that there was a planned simultaneous settlement for both properties on 22 August 2016. It is clear the Applicant needed sale proceeds for the settlement of the new property. The FSP is liable for losses caused by its error Where a party breaches an obligation of this nature to another party, it is generally required to compensate that party to reflect the position as if it had fulfilled its obligations. In other words, the compensation for damages is aimed to put the wronged party back into the position they would have been in, had the breach not occurred. It is common practice where a customer is selling their primary residence to purchase a new residential property at the same time. Although a different lender may be used for the purchase, it is reasonably common for the settlements to be coordinated and for the incoming lender to insist on the sale being completed first. Therefore, it should have been reasonably foreseeable to the FSP that any delay in settlement due to a lost certificate of title would also likely delay any purchase the Applicant planned for her and her family. In addition, it should have been reasonably foreseeable that any such delay would mean that the two transactions may not be coordinated easily and would be delayed for a week or two. As the simultaneous settlement could not take place on 22 August 2016, the second settlement had to be rescheduled. Although the sale was quickly re-scheduled, the the next available purchase settlement date for the new lender was on 5 September 2016, when settlement occurred. I have no reason to doubt that was the next available date for the purchase settlement. The available information shows that:  The two settlements were initially to occur on the same day. If the FSP had the title to the Applicant‟s for mer property ready, both settlements could have occurred on 22 August 2016  The unconditional loan offer from the incoming lender states that it was a condition that the sale settlement had to occur on or before the purchase settlement of the new property Case No: 451393 Determination Page 4 of 7  The FSP was aware that the Applicant was selling her primary residence . It should have been reasonably foreseeable that a purchase of a new residence would be affected by a delay. A reasonable enquiry would have revealed her plans to purchase a new residence  The Applicant‟s email to the FSP on 25 August 2016 , indicates that the Applicant was purchasing a „new place‟, and that the delay in the first settlement would have an impact on that  The FSP was unable to locate the required title until 25 August 2016 and  There was no basis for the FSP to assume that the Applicant‟s purchase settlement with the new lender could be achieved within a day‟s notice of finding the certificate of title. The FSP is accountable for the Applicant’s losses Based on all the available information I consider that the FSP should compensate the Applicant for the losses as set out at section 3.2. If the Applicant accepts this Determination within 30 days, the FSP should pay compensation of $15,860.25 plus 2.8% per annum interest from 6 September 2016 until payment, to be paid within 14 days of receiving notice of the Applicant‟s acceptance. The amount is calculated as set out in section 3.2 and in accordance with the Preliminary View. The amount should be paid to a bank account nominated by the Applicant. Case No: 451393 Determination Page 5 of 7 3 Supporting information 3.1 Key events On 22 August 2016, there was to be a simultaneous settlement of the Applicant‟s former property and her new property. The FSP was only required to discharge its mortgage over the former property. The Applicant vacated the former property on 19 and 20 August 2016 to provide vacant possession to the purchaser at settlement. The settlement on the former property was delayed because the FSP was unable to locate the title for it. Settlement occurred instead on 26 August 2016 once the title was located. The Applicant could not proceed with settlement of her new property until the sale settlement took place. Part of the sale proceeds were to be used for the settlement of the new property. As a result of the delay, settlement for the new property occurred on 5 September 2016. 3.2 FOS’s Preliminary View (made on 18 November 2016) On the basis of the available information and subject to any additional information that might be provided, if we apply the FOS approach to the specific facts and circumstances of the dispute the likely outcome is:  [The FSP] should compensate [the Applicant] a total amount of $15,860.25.  If both parties accept this Preliminary View, [the FSP] should pay this amount within 14 days of receiving [the Applicant‟s] signed resolution agreement (required by [the FSP]). It should be paid to an account nominated by [the Applicant]. The reasons for the preliminary view are detailed below, going through each item claimed by [the Applicant] and the adjusted amounts awarded by FOS listed (in bold) for each item:  Additional Legal Costs $1,921.15 [The FSP] should reimburse [the Applicant] the full amount ($1,921.15 inclusive of GST) as the tax invoice is itemised solely for additional legal costs incurred resulting from the delay in settlement.  Dog Boarding Kennel $ 764.50 The invoiced amount is for $1,478.40 (inclusive of GST) for the period from 20 August to 6 September 2016 (18 days, as stated on the invoice) but:  If settlement had occurred on time, [the Applicant] still would have incurred boarding and meal costs for 20 to 22 August 2016 (three days). Case No: 451393 Determination Page 6 of 7  A pro-rata amount for the remaining 15 days to be compensated for boarding amounts to $570 + $57 GST = $627.  A pro-rata amount for the remaining 15 days to be compensated for meals amounts to $125 + $12.50 GST = $137.50.  [The Applicant] would have incurred the pickup charge ($60 + $6 GST) in any event. FOS is not awarding compensation for this amount.  The obedience training fee ($450 + $45 GST) appears to be an item that [the Applicant] would have incurred anyway. FOS is not awarding compensation for this amount. Accordingly, [the FSP] should compensate $764.50 in this regard.  Hotel Accommodation $5,096 The invoiced amount is for two rooms at $6,188 (inclusive of GST) for the period from 19 August to 4 September 2016 (for 17 nights). The Applicant and her family departed on 5 September 2016.  If settlement had occurred on time, [the Applicant] still would have incurred accommodation for the initial three nights (19 to 21 August 2016) being $1,092 (pro-rata). FOS is not awarding compensation for this amount.  A pro-rata amount for the remaining 14 nights to be compensated amounts to $5,096 (inclusive of GST) Accordingly, [the FSP] should compensate [the Applicant] $5,096 in this regard.  Moving and Storage $6,828.60 The invoiced amount for the period from 20 August to 6 September 2016 is $11,028.60 (inclusive of GST) but:  [The Applicant] has provided an email from the storage company confirming that the original quote for two days‟ storage was only going to be $4,200 (inclusive of GST).  The additional storage costs incurred is $6,828.60. Accordingly, [the FSP] should compensate $6,828.60 in this regard.  Furniture Nil The invoiced amount for the furniture is $9,687. However, there is no basis on which [the FSP] is liable to compensate [the Applicant] for the cost of [her] furniture. This is because [the Applicant] has received it and has the benefit of it. [The Applicant] otherwise confirmed that [she has] not incurred any additional costs in this regard, such as furniture hire costs or other additional charges.  Compensation for stress and inconvenience $1,250 FOS can award non-financial loss for stress and inconvenience caused by an error or breach by a Financial Services Provider. However, FOS takes a Case No: 451393 Determination Page 7 of 7 conservative approach in awarding such compensation and it is generally not a substantial amount. In FOS‟s view, the $1,250 amount in non -financial loss for the stress and inconvenience caused by the overall situation, given:  The concerns about breaching the Contract of Sale on the [Applicant‟s former] property, particularly in receiving the Notice to Complete on 25 August 2016.  The worry and time required to make further arrangements with accommodation for her family, storage, boarding kennel, and furniture deposit (payable on 23 or 24 August 2016).  She had no new furniture i n her new home for three days (it was delivered on 8 September 2016).  The stress and inconvenience caused and loss of enjoyment in not being able to live in the new home for a two-week period. 3.3 Other issues Building insurance for the former property (nil awarded) As a result of the delay in settlement for the former property, the Applicant took out a building insurance policy (Policy) on the former property for the period from 25 August 2016 to 27 August 2017. The Policy was to be paid by monthly instalment of $74.61 via direct debit, commencing on 28 August 2016. The Applicant cancelled the Policy on 27 August 2016. Accordingly, the first instalment would not have been debited from the Applicant‟s nominated account on the following day. Further, even if it was debited, the Certificate of Insurance clearly states that a 14- day cooling off period applies. As the Policy was cancelled within that timeframe, the Applicant would be entitled to a full refund from the insurer.