Text of the determination
Determination
Case No: 451393 Determination Page 1 of 7
Case number: 451393 2 Februar y 201 7
1 Overview
1.1 Dispute
The Applicant had a loan with the Financial Services Provider (FSP) secured over
her former property. In 2016 the Applicant sold her former property and purchased
another property using finance provided by a different lender (new lender).
The dispute relates to the delay in settlement that occurred when the FSP was
unable to locate the title to the Applic ant‟s former property. A timeline of key events is
set out in section 3.1 below.
The Applicant says that the sale proceeds from her former property were required at
settlement to contribute to the purchase, so the sale settlement had to occur at the
same time as, or before, the purchase settlement. The Applicant claims various costs
incurred between 22 August and 5 September 2016 due to the delay. It is not
disputed that a delay occurred, but the parties disagree on the amount of the
Applicant‟s losses.
The Case Manager provided the parties with a preliminary view on the issues in
dispute on 18 November 2016. The preliminary view was in favour of the Applicant
and a copy is set out in section 3.2 of this Determination.
1.2 Issues and key findings
Were the findings in the preliminary view correct?
The issues and findings identified in the preliminary view are adopted in this
Determination . Further submissions provided after the preliminary view have been
considered.
For the reasons set out in section 2, the FSP should compensate the Applicant for
the losses set out in the preliminary view. The further submissions from the FSP do
not change that outcome.
1.3 Determination
This Determination is in favour of the Applicant.
If the Applicant accepts this Determination within 30 days, the FSP is to pay
compensation of $15,860.25 plus interest from 6 September 2016 at a rate of 2.8%
per annum on that amount until payment. Payment should be made within 14 days of
being notified of the Applicant‟s acceptance of this Deter mination. It should be paid to
a bank account nominated by the Applicant with her acceptance.
Case No: 451393 Determination Page 2 of 7
2 Reasons for Determination
2.1 Were the findings in the preliminary view correct?
The FSP rejected the preliminary view
The preliminary view was accepted by the Applicant but rejected by the FSP.
The FSP‟s reasons for rejection were that:
If the Applicant required the sale proceeds from the sale settlement to pay the
“ deposit ” for purchase at the purchase settlement, the purchase settlement
could not have been held simultaneously.
The FSP has not viewed the Contract of Sale to confirm:
o whether any special conditions were included
o that the sale proceeds from the sale settlement were required to pay a
deposit at the purchase settlement.
The FSP did not cause the delay of the purchase settlement to be held on 5
September 2016.
Accordingly, it considers that the loss for which it should compensate the Applicant is
limited to the period between 22 and 26 August 2016.
It is not disputed that the sale settlement was delayed by the FSP
According to the email correspondence between the Applicant‟s solicitor and the
FSP:
the FSP was informed on 9 August 2016 of the exchange of sale contracts on
the Applicant‟s former property. The FSP also received a signed Discharge
Authority on the same day from the Applicant‟s solicitor by email. The FSP had
sufficient time to prepare for settlement.
the FSP told the Applicant‟s solicitor it had been trying to locate the title to the
Applicant‟s former property since 18 August 2016. As a res ult, the FSP was
unable to proceed with settlement on 22 or 24 August 2016.
The FSP located the title to the former property on 25 August 2016. Settlement for
the Applicant‟s former property was then set for and took place on 26 August 2016.
The incoming lender required the sale settlement to take place first
The FSP was not involved with the settlement of the Applicant‟s new property which
was being financed by another credit provider.
The Applicant has provided the unconditional approval letter from the new credit
provider dated 20 July 2016. It confirms that the Applicant obtained a loan for
$637,500, and also that it was a condition that the settlement of “… [th e Applicant‟s
former property] h as to settle on or before [the Applicant‟s new property”.
The Contract of Sale for the new property shows that the purchase price was
$850,000. The Applicant has provided a copy of a deposit bond, showing that she
paid the 10% deposit ($85,000) this way. The deposit bond needed to be repaid at
Case No: 451393 Determination Page 3 of 7
settle ment for the Applicant‟s former property. The $850,000 purchase price less the
$637,500 finance amount indicates that the settlement of the new property still
required additional funds (around $212,500 plus fees and costs). The Applicant has
confirmed she required around $225,000 from the sale proceeds from the sale
settlement to contribute to the purchase settlement.
Settlement on the new property was to occur simultaneously
The FSP queries whether there was to be a simultaneous settlement of the
Applicant‟s former and new properties or that a delay in one would have impacted the
other.
In addition to the information set out above, the Applicant has provided copies of
emails between her and her solicitor dated 15 and 16 August 2016, which confirm the
vendor on her new property was preparing to settle on 22 August 2016.
Based on the available information, I am satisfied that there was a planned
simultaneous settlement for both properties on 22 August 2016. It is clear the
Applicant needed sale proceeds for the settlement of the new property.
The FSP is liable for losses caused by its error
Where a party breaches an obligation of this nature to another party, it is generally
required to compensate that party to reflect the position as if it had fulfilled its
obligations. In other words, the compensation for damages is aimed to put the
wronged party back into the position they would have been in, had the breach not
occurred.
It is common practice where a customer is selling their primary residence to purchase
a new residential property at the same time. Although a different lender may be used
for the purchase, it is reasonably common for the settlements to be coordinated and
for the incoming lender to insist on the sale being completed first. Therefore, it should
have been reasonably foreseeable to the FSP that any delay in settlement due to a
lost certificate of title would also likely delay any purchase the Applicant planned for
her and her family. In addition, it should have been reasonably foreseeable that any
such delay would mean that the two transactions may not be coordinated easily and
would be delayed for a week or two.
As the simultaneous settlement could not take place on 22 August 2016, the second
settlement had to be rescheduled. Although the sale was quickly re-scheduled, the
the next available purchase settlement date for the new lender was on 5 September
2016, when settlement occurred. I have no reason to doubt that was the next
available date for the purchase settlement.
The available information shows that:
The two settlements were initially to occur on the same day. If the FSP had the
title to the Applicant‟s for mer property ready, both settlements could have
occurred on 22 August 2016
The unconditional loan offer from the incoming lender states that it was a
condition that the sale settlement had to occur on or before the purchase
settlement of the new property
Case No: 451393 Determination Page 4 of 7
The FSP was aware that the Applicant was selling her primary residence . It
should have been reasonably foreseeable that a purchase of a new residence
would be affected by a delay. A reasonable enquiry would have revealed her
plans to purchase a new residence
The Applicant‟s email to the FSP on 25 August 2016 , indicates that the
Applicant was purchasing a „new place‟, and that the delay in the first settlement
would have an impact on that
The FSP was unable to locate the required title until 25 August 2016 and
There was no basis for the FSP to assume that the Applicant‟s purchase
settlement with the new lender could be achieved within a day‟s notice of finding
the certificate of title.
The FSP is accountable for the Applicant’s losses
Based on all the available information I consider that the FSP should compensate the
Applicant for the losses as set out at section 3.2.
If the Applicant accepts this Determination within 30 days, the FSP should pay
compensation of $15,860.25 plus 2.8% per annum interest from 6 September 2016
until payment, to be paid within 14 days of receiving notice of the Applicant‟s
acceptance. The amount is calculated as set out in section 3.2 and in accordance
with the Preliminary View. The amount should be paid to a bank account nominated
by the Applicant.
Case No: 451393 Determination Page 5 of 7
3 Supporting information
3.1 Key events
On 22 August 2016, there was to be a simultaneous settlement of the Applicant‟s
former property and her new property. The FSP was only required to discharge its
mortgage over the former property.
The Applicant vacated the former property on 19 and 20 August 2016 to provide
vacant possession to the purchaser at settlement.
The settlement on the former property was delayed because the FSP was unable to
locate the title for it. Settlement occurred instead on 26 August 2016 once the title
was located.
The Applicant could not proceed with settlement of her new property until the sale
settlement took place. Part of the sale proceeds were to be used for the settlement of
the new property. As a result of the delay, settlement for the new property occurred
on 5 September 2016.
3.2 FOS’s Preliminary View (made on 18 November 2016)
On the basis of the available information and subject to any additional information
that might be provided, if we apply the FOS approach to the specific facts and
circumstances of the dispute the likely outcome is:
[The FSP] should compensate [the Applicant] a total amount of $15,860.25.
If both parties accept this Preliminary View, [the FSP] should pay this amount
within 14 days of receiving [the Applicant‟s] signed resolution agreement
(required by [the FSP]). It should be paid to an account nominated by [the
Applicant].
The reasons for the preliminary view are detailed below, going through each item
claimed by [the Applicant] and the adjusted amounts awarded by FOS listed (in bold)
for each item:
Additional Legal Costs $1,921.15
[The FSP] should reimburse [the Applicant] the full amount ($1,921.15 inclusive
of GST) as the tax invoice is itemised solely for additional legal costs incurred
resulting from the delay in settlement.
Dog Boarding Kennel $ 764.50
The invoiced amount is for $1,478.40 (inclusive of GST) for the period from 20
August to 6 September 2016 (18 days, as stated on the invoice) but:
If settlement had occurred on time, [the Applicant] still would have incurred
boarding and meal costs for 20 to 22 August 2016 (three days).
Case No: 451393 Determination Page 6 of 7
A pro-rata amount for the remaining 15 days to be compensated for
boarding amounts to $570 + $57 GST = $627.
A pro-rata amount for the remaining 15 days to be compensated for meals
amounts to $125 + $12.50 GST = $137.50.
[The Applicant] would have incurred the pickup charge ($60 + $6 GST) in
any event. FOS is not awarding compensation for this amount.
The obedience training fee ($450 + $45 GST) appears to be an item that
[the Applicant] would have incurred anyway. FOS is not awarding
compensation for this amount.
Accordingly, [the FSP] should compensate $764.50 in this regard.
Hotel Accommodation $5,096
The invoiced amount is for two rooms at $6,188 (inclusive of GST) for the period
from 19 August to 4 September 2016 (for 17 nights). The Applicant and her family
departed on 5 September 2016.
If settlement had occurred on time, [the Applicant] still would have incurred
accommodation for the initial three nights (19 to 21 August 2016) being
$1,092 (pro-rata). FOS is not awarding compensation for this amount.
A pro-rata amount for the remaining 14 nights to be compensated amounts
to $5,096 (inclusive of GST)
Accordingly, [the FSP] should compensate [the Applicant] $5,096 in this regard.
Moving and Storage $6,828.60
The invoiced amount for the period from 20 August to 6 September 2016 is
$11,028.60 (inclusive of GST) but:
[The Applicant] has provided an email from the storage company
confirming that the original quote for two days‟ storage was only going to
be $4,200 (inclusive of GST).
The additional storage costs incurred is $6,828.60.
Accordingly, [the FSP] should compensate $6,828.60 in this regard.
Furniture Nil
The invoiced amount for the furniture is $9,687. However, there is no basis on
which [the FSP] is liable to compensate [the Applicant] for the cost of [her]
furniture. This is because [the Applicant] has received it and has the benefit of it.
[The Applicant] otherwise confirmed that [she has] not incurred any additional
costs in this regard, such as furniture hire costs or other additional charges.
Compensation for stress and inconvenience $1,250
FOS can award non-financial loss for stress and inconvenience caused by an
error or breach by a Financial Services Provider. However, FOS takes a
Case No: 451393 Determination Page 7 of 7
conservative approach in awarding such compensation and it is generally not a
substantial amount.
In FOS‟s view, the $1,250 amount in non -financial loss for the stress and
inconvenience caused by the overall situation, given:
The concerns about breaching the Contract of Sale on the [Applicant‟s former]
property, particularly in receiving the Notice to Complete on 25 August 2016.
The worry and time required to make further arrangements with
accommodation for her family, storage, boarding kennel, and furniture deposit
(payable on 23 or 24 August 2016).
She had no new furniture i n her new home for three days (it was delivered on
8 September 2016).
The stress and inconvenience caused and loss of enjoyment in not being able
to live in the new home for a two-week period.
3.3 Other issues
Building insurance for the former property (nil awarded)
As a result of the delay in settlement for the former property, the Applicant took out a
building insurance policy (Policy) on the former property for the period from 25
August 2016 to 27 August 2017.
The Policy was to be paid by monthly instalment of $74.61 via direct debit,
commencing on 28 August 2016. The Applicant cancelled the Policy on 27 August
2016. Accordingly, the first instalment would not have been debited from the
Applicant‟s nominated account on the following day.
Further, even if it was debited, the Certificate of Insurance clearly states that a 14-
day cooling off period applies. As the Policy was cancelled within that timeframe, the
Applicant would be entitled to a full refund from the insurer.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.