Text of the determination
Determination
Case No: 451248 Determination Page 1 of 8
Case number: 451248 24 July 2017
1 Overview
1.1 Dispute
The applicants lodged a claim under their home insurance policy with the financial
services provider (FSP) for cracking and movement damage to their home.
The applicants say the damage was caused by the effects of water leaking from a
damaged Telstra pit in the right of way adjacent to their property.
After investigating the claim, the FSP concluded that the damage was not caused by
water leaking from the pit, but by naturally occurring earth movement over an
extended period of time (which is excluded from cover under the policy).
The FSP has offered to carry out further investigations to confirm whether leaking
stormwater pipes under the house may have caused or contributed to the damage.
However, the applicants have rejected this offer. In these circumstances, the FSP
says it is entitled to deny the applicants’ claim.
The applicants dispute the FSP’s decision. They also seek compensation for the
manner in which the FSP has handled their claim.
1.2 Issues and key findings
Is the FSP entitled to deny the applic ants’ claim ?
The available information establishes that the cracking and movement damage to the
applicants’ property was not caused by the effects of leaking water, but by naturally
occurring earth movement over an extended period of time.
Damage caused in this manner is excluded from cover under the policy. Accordingly,
the FSP is not liable for the applicants’ claim.
Are the applicants entitled to compensation?
The applicants are entitled to compensation for non-financial loss due to the manner
in which the FSP handled their claim. The FSP has also agreed to reimburse the
applicants for certain other expenses.
1.3 Determination
This determination is substantially in favour of the FSP.
The FSP is not liable for the applicants’ claim .
Case No: 451248 Determination Page 2 of 8
The FSP is required to pay the applicants an additional amount of $1,000 as
compensation for non-financial loss.
The FSP is also required to reimburse the applicants for the costs of SD’s report and
the cleaning of the storm water drains, subject to the applicants providing copies of
the relevant invoices. The FSP is also required to reimburse the applicants for the
$500 excess paid.
Case No: 451248 Determination Page 3 of 8
2 Reasons for determination
2.1 Is the FSP entitled to deny the applicants’ claim ?
Policy provides cover for insured events subject to exclusions
The applicants are required to show that, on the balance of probabilities, they have
suffered a loss caused by a risk insured against under the policy. This is known as a
valid (or prima facie ) claim.
If the applicants are able to establish a prima facie claim, then the onus shifts to the
FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion
under the policy or is otherwise entitled to deny the claim.
The applicants ’ policy provides cover for damage caused by the ‘incidents’ listed in
the policy (including ‘escape of liquid’), subject to the conditions and exclusions set
out in the policy.
The insured event of ‘escape of liquid’ provides cover for damage to the property
caused by liquid leaking from any drain, fixed pip e, drainage or sewerage system .
The policy contains a general exclusion for damage caused by erosion, subsidence,
collapse, shrinkage or any other earth movement (other than landslide or subsidence
covered by the insured events of storm, flood, earthquake or explosion).
FSP’s liability depends on proximate cause of damage
The reports prepared by the engineer (SD and FM) appointed by the parties to
inspect the property confirm there is cracking and movement damage to the front part
of the property (including the hallway and front entry). There is also significant
bowing to the external brick wall and the garden wall on the northern side.
The applicants say the cracking and movement damage was caused by the effects of
water accumulating in a broken Telstra pit in the right of way adjacent to the north
wall of the property. The applicants say the water from the pit leaked into the
surrounding soil, causing movement of the bluestone strip footings of their home.
In their initial submissions, the applicants advised the Telstra pit was damaged in
early 2015, during the installation of the National Broadband Network (NBN). The
applicants say they first noticed the cracking and movement damage to their property
approximately 12 months later.
The FSP’s plumber (PB) sug gested it was possible water was leaking from the cast
iron storm water pipes under the property, which had deteriorated over time.
However, PB was unable to confirm whether the pipes were leaking without cutting
holes in the floorboards to inspect the pipes (as there was no access to the sub-floor
area). The applicants did not agree to PB carrying out a further investigation.
The FSP disputes that the cracking and movement damage to the applicants ’
property was caused by the effects of water leaking from either the Telstra pit or from
the deteriorated storm water pipes.
Case No: 451248 Determination Page 4 of 8
The FSP says the damage occurred as a result of differential movement of the
footings due to naturally occurring variations in the moisture content of the highly
reactive clay foundation soils.
Damage caused in this manner is not covered under the policy.
Accordingly, in order to determine the FSP’s liability for the claimed damage, it is
necessary to identify the proximate cause of the damage (that is, the real, effective or
dominant cause).
Engineers have provided differing opinions
As outlined above, the applicants say the cracking and movement damage to the
property was caused by the effects of water leaking from the damaged Telstra pit.
The applicants have provided a report from their engineer (SD) which concludes that
the damage was caused by water leaking from the Telstra pit. In his report, SD states
that:
the Telstra pit adjacent to the north-east corner of the property appeared to
have subsided allowing water to accumulate and leak into the surrounding soil
directly beneath the bluestone strip footings; and
the leaking water had softened the ground near the footings, which has caused
a reduction in the bearing capacity of the soil, resulting in movement of the
footings. SD noted that excess water can also result in heave, causing
differential movement.
SD noted that the applicants had advised that the property had not experienced any
significant movement issues before the 6 to 12 month period following the damage to
the pit in early 2015.
Accordingly, SD considered the primary cause of the cracking and mo vement
damage was water leaking from the pit. SD ’s conclusion was based on the location of
the pit, the timing of the damage and the absence of any prior cracking and
movement damage.
The FSP disputes that the claimed damage was caused by leaking water, based on
the findings of its engineer (FM), who inspected the property to determine the cause
of the damage in October 2016.
In his report, FM concluded the cause of the damage was long term differential
movement of the footings, which had occurred as a result of variations in the
moisture content of the reactive clay foundation soils.
Specifically, FM considered that the foundation soils at the property had dried out,
resulting in shrinkage and settlement (downwards movement) in the front section of
the house.
FM noted that the absence of sub-floor ventilation at the property meant that the soils
in the sub-floor area would retain a relatively high moisture content even during
periods of low rainfall (while the soils at the perimeter would dry out).
FM advised that the lateral displacement of the northern brick wall at the property
had occurred as a result of the relative difference in moisture content between the
Case No: 451248 Determination Page 5 of 8
sub-floor soils (which supported the inside of the footings) and the perimeter soils
(which supported the outside of the footings), which had caused the footings to rotate
outwards.
Damage was caused by naturally occurring earth movement
Having carefully reviewed the available information, the panel considers that the
proximate cause of the damage to the applicants ’ property was naturally occurring
earth movement over an extended period of time (and not by the effects of leaking
water).
The panel considers that FM’s report provides a logical explanation as to the
mechanism by which the damage occurred – that is, as a result of seasonal
variations in the moisture content of the foundation soils resulting in downwards
movement (settlement) and the outward rotation of the footings.
While a damaged Telstra pit was identified in the vicinity of the northern wall of the
property, the panel is not satisfied that the nature of the cracking and movement
damage observed is consistent with this damage having been caused by water
leaking from the pit.
The floor level surveys carri ed out by the FSP’s engineer (FM ) showed a clear
pattern of downwards movement (settlement) towards the northern (front) section of
the property. The level surveys do not show localised heave (upwards movement) in
the area of the damaged Telstra pit, as would be expected had the foundation soils
been affected by excess moisture.
The irregular nature of the water flows through the pit means there is unlikely to have
been sufficient volumes of leaking water to have caused the soil in the area of the
northern wall to lose its bearing capacity.
The pattern of settlement reflected in the floor level surveys is also more pronounced
towards the south side of the property, indicating there has been greater differential
movement of the foundation soils in areas which are more remote from the Telstra
pit.
The photographs included in FM’s report confirm that the cracking and movement
damage to the property is not confined to the areas in the immediate vicinity of the
Telstra pit but extends to the southern wall of the hallway and the walls and corni ces
of the bedrooms.
In addition, the available information indicates that the property had suffered long-
term cracking and movement damage prior to the damage to the Telstra pit in
February 2015. In particular, the photographs contained in FM’s report show:
evidence of previous repairs to internal areas in the north-east corner of the
property, including newspapers inserted to fill gaps and then painted over;
bowing in the northern wall of the property as early as 2013 (based on Google
maps images from that date);
evidence of the installation of a steel tie to the northern external double brick
wall, as is common in circumstances where the wall is rotating outwards; and
signs of prior repairs to other areas of the property, including the cornices in the
bedrooms.
Case No: 451248 Determination Page 6 of 8
The evidence of pre-existing cracking and movement damage indicates that the
property was susceptible to differential foundation movement over a prolonged
period.
While the applicants’ engineer (SD) concluded that the damage was caused by water
leaking from the Telstra pit, he did so on the basis that the damage was localised to
the area adjacent to the pit and had only become apparent in recent months.
However, it appears that SD did not undertake any floor level surveys, which would
have identified that differential movement was evident on the south side of the
property as well as on the north side.
Further, SD’s report does not refer to the signs of past repairs identified by FM, which
suggest that the movement issues were long term.
FSP is not liable for applicants’ claim
For the reasons outlined above, the panel considers that the cracking and movement
damage to the applicants ’ property was caused by naturally occurring earth
movement and not by the effects of water leaking from the Telstra pit.
Damage caused by naturally occurring earth movement is excluded from cover under
the policy. Accordingly, the FSP is not liable for the claimed damage.
The panel has considered the comments by the FSP’s plumber (PB) that water may
have been leaking from minor holes in the cast iron storm water pipes under the
property, which PB’s CCTV investigations revealed had deteriorated over time.
As noted above, PB advised that a visual inspection of the outside of the pipe would
be required to confirm whether or not there was a water leak.
The applicants declined to consent to a further inspection, even after the FSP offered
to pay for the cost of undertaking the inspection and repairing any resulting damage
to the floorboards.
The FSP’ s engineer (FM) advised that the damage to the front of the house was
unlikely to have been caused by leaking storm water pipes.
FM noted that:
water leaking from the storm water pipes would be expected to have caused
localised heave (upwards movement), which was not apparent from the floor
level surveys; and
the applicants had reported the damage to the property became apparent
during the summer months, when the volume of water flowing through the storm
water drains would have been less.
Having regard to the nature and extent of the damage to the property, the panel
considers it is unlikely to have been caused by water leaks from the storm water
pipes.
In any event, there is no information which confirms the storm water pipes were in
fact leaking, given the applicants’ decision not to allow a visual inspection.
Case No: 451248 Determination Page 7 of 8
2.2 Are the applicants entitled to compensation?
FOS may award compensation for non-financial loss
Under the Terms of Reference, FOS may award compensation (capped at $3,000)
for non-financial loss where an applicant has suffered an unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
However, FOS adopts a conservative approach to the award of compensation for
non-financial loss. FOS expects applicants to be moderately robust and bear the
usual stress and inconvenience associated with an insurance claim.
FOS does not award compensation for the monetary value of the time spent by an
applicant in pursuing their claim.
Applicants are entitled to compensation for non-financial loss
The applicants are dissatisfied with the way the FSP handled their claim. Among
other things, they say the FSP:
unreasonably delayed the progress of their claim by failing to arrange for its
contractors to attend the property;
repeatedly failed to update them on the progress of the claim and respond to
their enquiries; and
sent claim-related correspondence to an out of date email address.
The FSP has acknowledged the concerns raised by the applicants.
The claim records reflect that significant delays occurred during the course of the
applicants’ claim, they were not kept inform ed as to progress and the FSP and its
contractors failed to promptly follow up agreed actions.
The FSP has agreed to reimburse the applicants for costs incurred in obtaining SD’s
report and arranging for the cleaning of the storm water drains so PB could carry out
his CCTV inspection. The FSP will also reimburse the applicants for the $500 excess
paid in respect of their claim.
The panel considers it is appropriate that the FSP reimburse the applicants for these
amounts, given their claims experience.
In light of the service issues identified, the panel considers it is fair in all the
circumstances that the FSP also pay the applicants an additional amount of $1,000
as compensation for non-financial loss.
Case No: 451248 Determination Page 8 of 8
3 Supporting information
3.1 FOS approach to this disput e
This dispute has not been the subject of a FOS Recommendation. Due to the nature
of the dispute, it has been referred directly to a panel for determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The panel has decided this case based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous Financial Ombudsman Service (FOS) decisions.
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, the panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.