Text of the determination
Determination
Case No: 450561 Determination Page 1 of 12
Case number: 450561 6 November 2017
1 Overview
1.1 Dispute
The applicants lodged a claim on 3 March 2016 under their Home & Contents Policy
after discovering damage to their swimming pool.
The applicants say the damage is most likely the result of water leaking from the pool
due to a faulty hydrostatic valve, causing fill scouring, fill settlement, and rotation of
the pool.
The FSP denied the claim on the grounds that the applicants have not established a
claim within the terms of the policy, and that the damage is excluded from cover.
1.2 Issues and key findings
Have the applicants established a claim under the terms of the policy?
The policy provided accidental damage cover. Accidental damage is defined as
damage which is sudden, unforeseen and occurs without intent. The damage to the
applicants‟ property was sudden, unforeseen and occurred without intent.
Has the FSP established the application of an exclusion?
The FSP has not established, on the balance of probabilities, that an exclusion within
the terms of the policy applies to defeat the applicants‟ claim.
How should the claim be settled?
The FSP is entitled to settle the claim in accordance with the terms and conditions of
the policy.
1.3 Determination
This determination is in favour of the applicants.
The FSP is required to meet the applicants‟ claim in accordance with the terms and
conditions of the policy.
W ithin 28 days of the applicants‟ acceptance of this determination , the FSP must
arrange for a scope of works to be prepared. Upon receipt of the same, it may elect
to either repair or cash settle the claim in accordance with the terms of the policy.
Further, pursuant to paragraph 9.4 of the Terms of Reference of the Service, the FSP
must contribute up to $3,000 to the professional costs incurred by the applicants in
this dispute subject to the applicants providing relevant invoices.
Case No: 450561 Determination Page 2 of 12
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the information
exchanged.
Due to the complexities involved in this dispute, it has been referred to a panel for
determination.
The determination follows consideration of all of the information exchanged and is
based on what is fair in all the circumstances, having regard to the relevant legal
principles, terms of the policy, good industry practice including codes of practice and
prior determinations where applicable.
2.1 Have the applicants established a claim within the terms of the
policy?
Onus is on the applicants to establish entitlement to cover
An insured has the onus of establishing that they have suffered a loss caused by an
event for which their insurance policy provides cover.
Policy provides cover for accidental damage
The FSP submits that the policy is a defined events policy. However, the product
disclosure statement (PDS) and certificate of insurance make it clear that the policy
is an accidental damage policy.
Page 43 of the PDS is headed “Section Four : Accidental Damage Cover” , and states:
“If you choose and pay for this option it will be shown as covered on your certificate”.
The certificate of insurance provided by the FSP states: “ Accidental Damage Cover
Included”.
The PDS descri bes the policy‟s accidental damage cover as covering “accidental
damage to your home or contents… occurring during the period of insurance.” The
policy defines “accidental damage” as “ damage that is sudden, unforeseen and
occurs without intent ”.
Circumstances of the loss
The applicants purchased the property in December 2013. The first notification that
the pool was losing water occurred January 2014 at which time a hydrostatic valve
was replaced. The pool continued to leak and a further pressure test conducted in
March 2014 found additional small leaks on the eastern side of the pool at the top of
the hydrostatic valve and at the filter multi-port valve. The pool was treated with
epoxy resin and continued to leak. Further investigations in November 2014 found
leaks in cracks at the base of the pool and a crack on the house side of the pool.
There is no suggestion that the pool had any obvious damage prior to purchase of
the property in December 2013. The pool had been built in 2000 by the previous
Case No: 450561 Determination Page 3 of 12
property owners and there is no suggestion that it had not functioned properly over
that time.
The panel is satisfied that the damage first identified to the pool in January 2014 was
damage was accidental damage from the applicants‟ position , in that it was sudden,
unforeseen and occurred without intent. The onus is therefore on the FSP to
establish the application of an exclusion.
2.2 Is the FSP entitled to refuse payment of the claim?
Policy excludes cover in certain circumstances
The FSP in its notice of response ref erred to the applicants‟ policy as being a defined
events policy and argued that the applicants had not established that the damage
had occurred as a result of a defined event.
As indicated above, the applicants had taken out the additional optional cover for
accidental damage. Under the terms of the policy, the applicants are covered for
accidental loss or damage that occurs to the home during the period of insurance.
Such cover is limited to the relevant sum insured on the certificate and by the
exclusions that apply under the terms of the policy.
The FSP relies upon the exclusions as set out under section 3.3 of this
determination. Effectively, the FSP says that the loss or damage is excluded from
cover as it was caused by:
an event that occurred outside the period of insurance
wear and tear, lack of maintenance or inherent defect, including gradual
deterioration
structural defects or faulty workmanship, settling, shrinkage or expansion.
Experts disagree on cause of damage
Numerous investigations and reports have been provided by both parties. The
applicants rely largely upon reports from their expert, „ ERS ‟, whilst the FSP relies
largely upon its expert, „ JHA ‟ .
Initial inspections of the pool were undertaken by „ AR ‟ . A pressure test conducted on
31 March 2014 found small cracks at the top of the eastern wall and the hydrostatic
valve was replaced as a standard precautionary procedure. Further tests on 11
November 2014 identified cracks at the pool floor and walls. These cracks were filled
with epoxy sealant. The hydrostatic valve was again replaced as a standard
precautionary procedure.
A geotechnical inspection carried out by „ SSE ‟ referred to the sub-surface profile as
comprising silty clay gravel and sandy gravel and very stiff to hard silty sandy clay fill
material. A bore hole identified a distinctly weathered sandstone of very strong
strength at a depth of two metres. Ground water was not encountered in the bore
holes at the time of the investigation, but it was conceded that sub-surface seepage
may be expected, particularly following rainfall events.
The applicants‟ expert ERS considers that the pool has been built on a foundation of
fill material overlying a very strong weathered sand stone bed rock. ERS had noted
that the hydrostatic valve was replaced on three occasions. After last being replaced
in November 2014, there was no evidence of further leakage, implying that the
Case No: 450561 Determination Page 4 of 12
hydrostatic valve may have been faulty, causing the ingress of water to the underside
of the slab, generating the rotation and subsequent cracks. ERS considered that the
water leakage most likely contributed to the fill settlement and fill scouring under the
footings and slab, with the resultant rotation and subsequent cracking of the pool
base and walls.
The FSP‟s expert JHA considered the pool had twisted and cracked and leaked
because it was built on fill. JHA considered the damage was the result of gradual
settlement over an extended period of time due to the inadequate footings , which had
caused the fill material to slowly settle under the weight of the pool and resulted in
the tilting and rotation and eventual cracking and leaking of the pool shell. The FSP
believes the process started prior to the inception of the policy.
Pool foundation in natural ground not fill
The applicants have provided the plans for the pool. The plans confirm that the pool
was to be founded in natural ground. The FSP‟s expert says that whilst this
establishes what was intended to occur, it does not establish that this was how the
pool was actually built.
The applicants eventually obtained a further soil test from „ TST ‟ dated 17 February
2017. This was an invasive test which found the soil profile was made up of fill soils
overlying a top soil layer and natural clay soils. The natural clay soils included some
extremely weathered rock lenses. TST identified the bored pier extends between
0.9m and 1m into natural clay and that the pier footings were founded in the natural
soils, not in fill soil as previously identified by JHA.
ERS maintains that this test confirms the pier foundation had been implemented and
founded in natural material, as it had consistently maintained and as was consistent
with the engineering drawings and subsequent certification of the pool.
JHA now concedes that its theory that the pool footings were founded on fill is not
supported. JHA now maintains that the founding capacity of the in situ material clay
was inadequate for the pool loads imposed on it, or that the natural ground water
reduced the bearing capacity of the founding clay on which the pool had been
constructed.
All of the reports have merit and the views expressed by both experts can be
persuasive. The onus, however, is on the FSP to establish that is that it is more likely
than not that the damage to the pool fell within one of the relevant exclusions.
Whilst the panel accepts there is information to suggest that the hydrostatic valve
had been leaking over an extended period of time, there is no information to establish
that the damage to the pool had occurred at any time prior to January 2014. There is
no information to establish that the damage occurred outside the period of cover.
The information confirms that the pool was correctly constructed. There was no
apparent structural defect or faulty workmanship. There is no evidence of wear and
tear or lack of maintenance or an inherent defect in the pool or its construction.
In the circumstances, the panel is not satisfied that the FSP has established that an
exclusion applies to defeat the applic ants‟ claim. Accordingly, the FSP is liable to
settle the applicants‟ claim in accordance with the terms and conditions of the policy.
Case No: 450561 Determination Page 5 of 12
FSP may decide how to settle the claim
Page 60 of the PDS says that the FSP will decide whether it will settle a claim by
repairing damage or paying the cost of repairs.
The applicants say that if the FSP has the pool repaired, “that is simply unacceptable
as the dispute will continue ” . The applicants say that the FSP has a “proven track
record” of appointing experts with in sufficient knowledge and experience, and
therefore any repairer appointed by the FSP to repair the pool would probably cause
further disputes to arise.
The panel is not satisfied that the FSP has acted unreasonably in managing this
claim. The opinions provided by JHA were reasonable, given the evidence available.
The applicants say: “the two (2) pool builders that we got to quote on the repairs of
the pool would not provide a warranty if it was being repaired. They would only
provide a warranty on a new build. Obviously, if such repairs were to be undertaken,
we would want a warranty on all works.”
ERS‟s report of 19 February 2016 recommends stabilisation through underpinning, or
replacement of the pool shell. JHA‟s report of 23 May 2016 states that replacem ent
of the pool is “the only option that could guarantee the effectiveness of rectification”.
However, JHA‟s discussion of remediation options is based on the pool being
founded on fill, a conclusion JHA now admits was incorrect.
The available evidence is not sufficient to establish that the pool cannot be repaired.
The policy allows the FSP to decide how to settle the claim
The panel determines that within 28 days of the applicants accepting this
determination, the FSP is to commission a scope of works to determine whether the
pool can be repaired as well as the likely cost of the repairs. Upon receipt of this, the
FSP must, within 14 days, elect to either complete the repairs or cash settle the
applicants‟ claim.
In exercising its discretion to cash settl e the applicants‟ claim, the FSP must do so
reasonably and consistent with the principles of utmost good faith. Any cash
settlement must be sufficient to enable the applicants to complete the relevant
repairs and take into account the contingencies associated with the repair process
and the transfer of the risk of the repairs to the applicants.
FSP to contribute to the applicants’ cost
Paragraph 9.4 of the Terms of Reference provides that the Service may determine
an FSP contribute up to $3,000 to the cost of obtaining relevant expert reports.
In determining whether an FSP should contribute to the cost, it is necessary to look
at what is fair in all the circumstances, taking into account the complexity of the
dispute, whether the costs were genuinely incurred, and whether they were
reasonably needed in the circumstances.
The panel is satisfied that the reports obtained by the applicants, in particular the
reports from their engineer ERS and the soil tester TST were reasonably obtained
and assisted the panel in reaching its determination in this matter.
Case No: 450561 Determination Page 6 of 12
The panel determines it is fair in the circumstances that the FSP contribute up to
$3,000 to the applicants‟ cost of obtaining these reports , subject to the applicants
providing relevant invoicing.
Case No: 450561 Determination Page 7 of 12
3 Supporting information
3.1 Relevant policy terms
SECTION FOUR: ACCIDENTAL DAMAGE COVER page s 43 – 44
…
If you choose and pay for this option it will be shown as covered on your certificate.
…
WHAT IS COVERED
We will cover accidental loss of or accidental damage to your home or contents or
Enthusiast items occurring during the period of insurance.
…
WHAT IS NOT COVERED
…
The exclusions on pages 53 to 55 apply.
…
EXCLUSIONS APPLICABLE TO YOUR POLI CY page s 53 – 55
IN RESPECT OF ALL SECTIONS IN THE POLI CY, WE WILL NOT COVER YOU FOR DAMAGE,
LOSS OR LIABILITY CAUSED BY, ARISING FROM OR INVOLVING ANY OF THE FOLLOWING:
An event that occurred outside the period of insurance shown on your certificat e.
…
Wear and tear, lack of maintenanc e or inherent defect, including gradual deterioration.
…
Structural defects or faulty workmanship, settling, shrinkage or expansion.
HOW WE SETTLE YOUR CLAIM page s 60 – 61
HOW WE SETTLE A CLAIM FOR YOUR HOME, CONTENTS, ENTHUSIAST ITEMS OR
PERSONAL EFFECTS
We discuss with you what is necessary to make good the loss or damage, and in respect of loss or
damage to your home, contents, Enthusiast items or pers onal effects, we decide whether we will:
repair damage; or
replace your home, cont ents, Enthusiast item or pers onal effect; or
pay you what it would cost us to repair or replace your home, contents, Enthusiast item or
personal effect; or
pay you the relevant sum insured.
DEFINITIONS OF IMPORTANT WORDS AND PHRASES page s 68 – 70
…
Accidental damage means damage that is sudden, unforeseen and occurs wit hout intent.
…
Case No: 450561 Determination Page 8 of 12
3.2 Summary of relevant expert reports
ERS report dated
19 February 2016
The pool shows deformation and cracking.
The “fill surrounding the wall footings on the eastern down
slope has settled… exposing the underside and leading
edges of the footings… the extent to which it occurs under the
pool base slab is unclear”.
There is “some evidence of material settlement at the
north ‐ west corner… due, in part, to loose surface fi ll being
washed away down the steep slope”.
In March 2014, a leakage detection company, „PT‟, found
leaks from cracks in the pool walls. These cracks were filled
with an epoxy sealant. As a standard pre cautionary
procedure, the hydrostatic valve was replac ed.
In November 2014, PT found leaks from cracks in the pool
wall and floor. These cracks were filled with an epoxy sealant.
As a standard pre cautionary procedure, the hydrostatic valve
was replaced.
In January 2015, PT tested the pool and found no leaks. “This
implies that the hydrostatic valve may have been faulty
causing egress of water to the underside of the slab,
generating the rotation and these subsequent cracks.”
FSP internal
assessor‟s report
11 March 2016
The ERS report says that the hydrostatic valve was
replaced on several occasions, which indicates that it
was not the source of the leaks.
Damage to the pool has been occurring since 2014.
JHA report
23 May 2016
The pool was founded on fill, not on the weathered rock
beneath the fill. The fill has slowly settled over a long
period of time.
Settlement of fill has caused tilting and rotation of the
pool shell, which has caused cracking and leaking.
Settlement of fill has been aggravated by water from
pool splashing, rain, and crack s in the pool shell. A
leaking hydrostatic valve may have contributed to
settlement, but if so, “[t]his aggravation has occurred
after the pool has started to settle”.
The applicants called PT to investigate leaks in March
2014, about a year after they pur chased the home. This
suggests that there was no leaking when the home was
purchased, so settlement was occurring for some time
before the appearance of the cracks/leaks.
There is no direct evidence that the hydrostatic valve
was faulty; it was replaced as a precautionary measure
without being tested for faults. ERS says that the leaking
stopped after the hydrostatic valve was replaced.
However, cracks were sealed at the same time the
hydrostatic valve was replaced (on both occasions). The
leaks could have stopped because the cracks were
Case No: 450561 Determination Page 9 of 12
sealed, not because the hydrostatic valve was replaced.
The greatest amount of settlement has occurred at the
shallow end of the pool, far from the hydrostatic valve.
This suggests that a faulty hydrostatic valve is not the
main cause of settlement.
ERS report
15 June 2016
ERS considers the possible causes of settlement listed in the JHA
report and makes the following comments:
The fill under the pool was inadequately compacted during
construction, and has slowly been settling since.
There is no evidence that the fill was inadequately
compacted. A conclusion that this was the cause of
settlement is “at best, a guess”. In this scenario, settlement
“would be expected to be consistent across the pool due to
the large and r igid surface area that the pool base provides”.
Water from pool splashing and from rain on the timber deck,
has penetrated the fill resulting in it consolidating.
Water from pool splashing would be minimal and would not
cause significant scouring due to it s inconsistent application.
Rainwater runoff “has caused some scouring”, but it is “a very
minor amount”.
Water from a leaking hydrostatic valve has penetrated the fill.
This is the most likely cause because “[t]he scouring
observed under the concrete wall overspill is consistent with
water ingress under the pool shell”. “External sources would
not produce this type of significant scouring. The only source
[of water] under the pool is the hydrostatic valve.”
Water leaking through cracks in the pool shell ha s penetrated
the fill.
“In my view the wall cracks are an indirect result of the
scouring, not the reverse. In any event, when put in context,
this would be a very minor amount of water which could not
cause the degree of scouring/settlement.”
“ There would be up to 2m head of water pressure on the
hydrostatic valve location. At that pressure, pool water would
be forced to all points of the pool base… That could be
anywhere under the base… ”
The report concludes:
“ It is my opinion… that the [damage] could onl y have been
caused by a significant event that produced extensive
subbase scouring and voids under the pool that
subsequently rotated the pool shell. A hydrostatic valve
failure would produce such an event. ”
ERS email
10 August 2016
I have recently received the original structural drawings for the
pool design at [applicants‟ address]. The design engineer was
[DN Engineers].
Case No: 450561 Determination Page 10 of 12
I have reviewed the drawings and have the following comments:
The pool design drawings are dated 20/07/2000
The drawings clearly show that the foundation design
requires the perimeter walls of the pool to be constructed in
the existing natural surface material (not on fill);
There is no indication of the geotechnical composition of the
natural surface material on the drawing s e.g. fill or other, but
the drawings require the pool to be built into natural material;
[MY], from [DN Engineers] has provided an inspection
confirmation, that the reinforcement steel and footings were
inspected at the time of construction. This means t hat the
engineer that undertook that inspection was satisfied that the
footings used in constructing the pool were taken down to
natural surface material (not fill) as per the pool design
drawings;
On the basis that the engineer signed off on the pool, (w hich
is the best indicator that we have some 16 years later) it is
appropriate to say that the footings of the pool have been
constructed in accordance with the design intent... i.e. founded
on natural surface (not on fill).
DN engineer
17 November 2016
Fr om 1984 till 2006 I owned and operat ed the engineering firm [DN
Engineers]…
In 2000 we prepared plans for construction of a pool at [applicants‟
address]… The shell was constructed in July of that year and before
concrete was placed the reinforcing and so il conditions were inspected
by an engineer from my office. The downhill wall was extended down to
weat hered rock and a dwarf wall built up to the underside of the pool
shell proper. All grass and top soil were stripped from under the
structure and the lev el raised to the underside of floor wit h screened
recycled concret e which, being inc ompressible uniformly transferred the
weight down to natural ground with a minimum bearing capacity of 100
KPa.
…
The pool was duly completed and certified as structurally adequate at
the time of handover.
AR email
21 November 2016
You have asked me to comment on [JHA‟s contention] that there
was no evidence of a damaged or faulty hydrostatic valve…
The first thing I did after inspecting of your pool was to replace
the hydrostatic valve. This resulted in an immediate water loss
reduction of over 90%.
In my experience, some 20 years in the pool building industry,
replacing an item that stops a leak is a very good indicator of the
thing that failed…
In my 20 years of buil ding/maintaining pools, I have replaced and
installed 100's of hydrostatic valves. Metal fatigue is not
something that can be easily seen how ever dirty and damaged
rubber seals is very common. This is why replacing the
hydrostatic valve is an important thi ng to do with any leaking pool.
JHA report
25 November 2016 The report concludes as follows:
The available evidence (rotation of the pool) is consistent with
Case No: 450561 Determination Page 11 of 12
the pool being founded on fill which has settled.
The available evidence (rotation of the pool) is not consistent
with the pool being founded on the weathered rock beneath
the fill.
If the pool has been founded on rock no explanation by any
party of how this rotation could have occurred has been
offered.
JHA report
2 December 2016 Regardless of what the drawings show, they can only indicate
what was intended, not necessarily what was constructed.
There is no proof that the pool was constructed in accordance
with the drawings.
Response from DN
7 December 2016
[T]he fact that I cannot remember which engineer inspected the soil
conditions and reinforcing steel prior to concrete placement, is
irrelevant…
The fact remains that the pool was inspected and certified by a qualified
civil engineer with full membership of the Institution of Engineers
(Australia) which shows the esteemed level of qualification I had for
employing engineers…
I have the utmost faith in the fact that my engineers signed off on the
pool having been built as per the plans, namely, down to weathered
rock. My confidence comes from the fact that in my 30 years of
certifying 30,000 pools, not once have I discovered one of my engineers
to have acted negligently or dishonestly.
JHA report
21 December 2016 “ No plausible explanation has been offered as to why
rotation of the pool w ill occur at the shallow end if the pool
was founded on weathered rock. ”
TST report
17 February 2017
[TST] was commissioned to assess the soil profile under the existing
pool footings at the above address and det ermine whether or not the
pool footings wer e founded into natural or fill soils .
…
The test pit exposed part of the footings of the pool which included the
base of the pool edge and a bored pier .
The total depth of the footing from the top of the concrete thickening at
the base of the pool edge to the base of the bored pier was
approximately 1.9m. The bored pier extends approximately 0.9m – 1.0m
into the natural clay soils .
…
From the results of the investigation it has been concluded that the base
of the pool edge is founded in fill soils . However, the bored pier footing
supporting the base of the pool edge is founded into the natural soils .
ERS report
20 February 2017
The no tes on the [engineering drawings] require that if a fill material is
present then a pier foundation solution should be considered. [ The TST]
inspection confirms that a pier foundation system has been
implemented and is founded in insitu material.
Although the wall base strip footing is in the fill material, the concrete
piers transfer all pool loads to the insitu materials as per the design
requirements...
Any assertion that the foundation system was built on fill is incorrect.
Case No: 450561 Determination Page 12 of 12
JHA report
28 February 2 017
The New Evidence
The New Evidence
The recent investigations…
1. Confirm the presenc e of significant fill under the pool - despit e the
assertions of [the applicants].
2. Confirm that the pool is not founded on weathered rock - des pite
the assertions of [DN].
3. Confirm that the pool is founded on natural clay soils containing
discontinuous layers (lenses) of extremely weathered rock.
…
The new evidence means that our initial assertion that the pool
rotation and movement being caused by settlement of fill was
inco rrect.
…
The following discusses possible causes of the settlement:
1. The natural clay does not have adequate bearing strength to
support the loads imposed on it by the piers. The piers were not
founded on weathered rock but plastic clays.
2. Moisture from a le aking hydrostatic valve or cracks in the pool has
softened the natural clay so that its bearing strength is reduced.
…
The evidence does not support the hydrostatic valve being the
cause of the settlement.
If a leak from the hy drostatic valve was the cause , then it would be
reasonably expected that the greatest amount of settlement would
occur at the deep end of the pool where the weight of the pool was
the greatest and also the softening of the clay soils due to the
water would be the great est.
3. Moisture fr om natural processes, such as rain, has softened the
natural clay so that its bearing strength is reduced. Both of the
reports (by [TST] and by [ERS]) indicat e that the soil profile was
moist to very moist.
The last information available to us… indicated t hat… the pool was
no longer losing water. Based on this information, it is unlikely that
the soil profile would still be moist to very moist, so many months
later, if the pool was the source of the moisture…
The moist to very moist condition of the soil pr ofile is therefore
likely to be due to natural rain conditions.
The available evidence therefore does not support the rot ation and
movement of the pool having been caused by water leaking from a
faulty hydrostatic valve, but by the founding capacity of th e clay
being inadequate for the pool loads imposed on it, or by natural
ground water reducing the bearing capacity of the founding clay on
which the pool has been constructed.