Home / Financial Firm (Unknown - Insurer) / Determination 449459

Determination 449459

Delay in cash settling commercial vehicle bonnet theft claim; claimed loss of income

FirmFinancial Firm (Unknown - Insurer)
Decided2017-10-16
ProductGeneral Insurance · Motor
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$1,000
Amount claimed$396,000
SourceAFCA PDF

Summary

The applicant's company sought $396,000 for lost income, which it attributed to delays in cash settling a bonnet theft claim. AFCA found the settlement delay unreasonable but the lost income was not established, and awarded $1,000 for non-financial loss.

The settlement delay was unreasonable, but the applicant gave no documentary evidence that the delay caused a loss of income.

Issues

Subjects and remedies

business interruptionsmall businesspay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 449459 Determination Page 1 of 3 Case number: 449459 15 September 2017 1 Overview 1.1 Dispute The applicant holds a commercial motor vehicle policy with the financial services provider (FSP). In April 2016 the applicant lodged a claim for damage sustained to his vehicle as a result of the theft of the insured vehicle’s bonnet. The FSP accepted liability and eventually cash settled the claim for $16,126. The applicant maintains that due to delays it has suffered a significant loss of income. The applicant seeks $396,000 compensation for loss of income. 1.2 Issues and key findings Is the applicant entitled to loss of income? The applicant claims that as a result of the FSP’s delay in handling his claim he was unable to obtain a contract for transporting grain and as a result suffered loss of income of approximately $33,000 gross per month. The applicant has not provided any information to substantiate this loss. In the absence of any further information I am not satisfied that the applicant has established either the FSP’s conduct was inappropriate or that he has suffered a loss of income as a result of the FSP’s conduct. Is the applicant entitled to compensation for non-financial loss? I acknowledge there have been delays in the handling of the dispute and settlement of the claim. I accept the delays would have caused inconvenience. In the circumstances it is appropriate to award compensation for non-financial loss of $1,000. 1.3 Determination This determination is in favour of the FSP. The FSP is entitled to limit its liability in accordance with the terms and conditions of the policy. The applicant is entitled to compensation under paragraph 9.3 of the Terms of Reference of $1,000. Case No: 449459 Determination Page 2 of 3 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. In addition to the information exchanged the applicant has been asked by the Service to supply documentation including receipts, bank statements, invoices and other statements indicating the income he would normally make during a comparable period. He was also asked to provide information from his accountant. No documentation has been supplied. This determination follows consideration of all of the available information and is based on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes of practice and prior determinations where applicable. 2.1 Is the applicant entitled to compensation for loss of income ? Applicant has not established a loss due to the FSP’s claims handling The applicant lodged its claim with the FSP on 7 April 2016 following the theft of the bonnet to the vehicle in March 2016. The applicant provided a quote for repairs on 29 April 2016 and an assessor was appointed on 10 May 2016 to assess the damage. Following discussions with the FSP’s assessor the applicant lodged a claim with the Service on 9 August 2016 because of the delays. The FSP offered to cash settle the claim on 12 August 2016. The offer was accepted by the applicant on 1 September 2016 but the cash settlement not paid until 12 October 2016. I accept given this timeframe that the FSP had unreasonably delayed the settlement of the claim. Part of this delay was due to difficulty in finding a bonnet for the vehicle. I accept however given the information provided that the FSP could have cash settled this claim much earlier. In this respect I accept that the delays were unreasonable. Applicant has not established any loss of contract The applicant says that as a result of the delays he was unable to take up a contract to work with BQS, carting grain. The applicant claims that he had spent five years getting to a position where BQS would offer him work. He claims he would have earnt up to $300,000 for six months work. T he applicant’s broker claims the applicant’s income would have been at least $33,000 per month. The applicant says BQS will not put anything in writing or make any statement to indicate that he would have been offered the grain work. He is unable to provide any documentation to show any arrangements had been put in place with BQS. He has Case No: 449459 Determination Page 3 of 3 not provided any receipts, bank statements, invoices or other statements to show the income that he would be likely to earn in a comparable period. I contacted the applicant on 7 August 2017 to request further information. The applicant undertook at that time to get onto his accountant and obtain the financial information. This information has not been provided. In the circumstances I am not satisfied the applicant has established that as a result of the delays in finalising the applicant’s claim he has suffered a loss of income. 2.2 Is the applicant entitled to compensation for non-financial loss? Under the Terms of Reference the Financial Ombudsman Service can award compensation up to $3,000 in the event that there is an unusual degree of inconvenience or time taken to resolve a dispute. As I have indicated I am satisfied the delay in cash settling the claim was unreasonable. In my view the FSP should have been in a position to settle the applicant’s claim by 28 June 2016. The FSP has not explained why another month passed before it requested photographs of the vehicle or a further 18 days passed before the offer was made. It has not explained why after acceptance of the offer on 1 September 2016 it delayed payment of the claim to 12 October 2016. I have no doubt that these delays were unusual and resulted in considerable stress for the directors of the company. In the circumstances I am satisfied that an award of compensation for non-financial loss of $1,000 is appropriate.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.