Home / Financial Firm (Unknown - Insurer) / Determination 449151

Determination 449151

Storm damage to roof declined; repair quality and asbestos handling disputed

FirmFinancial Firm (Unknown - Insurer)
Decided2018-02-15
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The applicants claimed for storm damage to their roof and for rectification of FSP repairs, including asbestos concerns. AFCA found the tiled roof was not storm damaged, ordered a 50% contribution to rectification and an expert asbestos report, and awarded $3,000 non-financial loss.

The insured must prove storm damage, while the insurer remains liable for unsatisfactory repairs it carried out and for its unaddressed asbestos concerns.

Issues

Subjects and remedies

pay claimpay interestpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 449151 Determination Page 1 of 15 Case number: 449151 17 January 2018 1 Overview 1.1 Dispute This dispute arises in relation to a claim lodged by the applicants with the financial services provider (FSP) on their home and contents insurance policy. In February 2013, the applicants lodged a claim after the discovery of water entering their home. The FSP accepted internal resultant damages. The applicants raised concerns with the quality of work undertaken, which was accepted by the FSP. The dispute considers whether the FSP has any additional liability under the claim and whether the FSP was entitled to cash settle rectification repairs. 1.2 Issues and key findings Was the roof damaged by an event covered under the policy? Save for the near left corner of the metal roof, the available material establishes the metal roof and tiled roof were not damaged by an event to which the policy responds. As such the FSP was entitled to decline cover for this aspect of the claim and is not required to pay anything further to the applicants. Is the FSP required to expand its scope for rectification repairs? The FSP is required to expand the scope of rectifications to include the paintworks to the family room ceiling, the paintworks to a cupboard wall in the family room, the recurring blistering to the veranda‟s soffit lining and any other internal damage sustained in these areas as a result of the FSP‟s inadequate repairs and inadequate initial assessment of the cause of damage. Was the FSP entitled to cash settlement additional rectification works? The FSP is entitled to cash settle additional rectification works and is to promptly proceed to resolve the cash settlement for rectification repairs, as outlined in Section 2.3 of this determination. Have the FSP’s repairs exposed the applicants to asbestos? The FSP‟s report does not address the applicants‟ concerns about the 2013 work undertaken by the FSP‟s repairer. At the FSP‟s expense, a further report is to be prepared by an asbestos expert about the 2013 work. Case No: 449151 Determination Page 2 of 15 Are the applicants entitled to compensation? The applicants are entitled to compensation as the FSP‟s conduct regarding the serious matter of concerns about asbestos have interfered with the applicants‟ expectation of enjoyment or peace of mind and there has been an unusual amount of time taken to resolve the matter. 1.3 Determination This determination is substantially in favour of the applicants. If the applicants accept this determination, then within seven days of acceptance, the FSP is to:  pay to the applicants $3,000 compensation  instruct its contractor (J) to prepare a revised estimate of additional rectifications and cash settle these works as outlined in Section 2.3 of the determination  arrange (at its expense) a further report by an asbestos expert about the 2013 work as outlined in the determination. Case No: 449151 Determination Page 3 of 15 2 Reasons for determination 2.1 Was the roof damaged by an event covered under the policy? Policy covers damage caused by specific events The applicants must establish, on the balance of probabilities, they have suffered a loss caused by a risk insured under the terms of the policy. This is called a prima facie claim. Once the applicants establish a prima facie claim, the onus shifts to the FSP to establish an exclusion applies to defeat the claim. The applicants‟ policy provides cover for 14 specific events, including storm, subject to terms, conditions and exclusions. The applicants say the roof was damaged as a result of a storm. The onus is therefore on the applicants to establish, on the balance of probabilities, any roof damage was caused by a storm. Circumstances of the loss and claim The FSP appointed a builder (A) to inspect the applicants‟ property, and to establish the cause of damage and water entry. A says water damage was visible to the ceiling, wall cupboard and flooring in the lounge room. A also noted damage to the TV antenna and the soffit linings to the front entrance. A inspected the skillion roof above the lounge room. He found guttering at the end was blocked and this blockage was directly above the internal damage. He said leaf debris from the gable roof contributed to the damage. He noted previous temporary repairs had been carried out to the flashings above the damaged area. A also inspected the soffit linings. He noted inadequate downpipes to the front and left-hand side of the property. He said this enabled water to escape the back of the guttering and enter the ceiling area resulting in damage. He said the lights and air-conditioning units were working when he inspected them. The material provided indicates discussion continued between the applicants and the FSP about rectification repairs for a rattling window and a sp lit system air conditioner during January 2014. The material provided also indicates these issues were eventually resolved. A noted no storm damage to the roof. As A indicated there were maintenance issues not related to the storm event, he recommended roof repairs be made by the applicants before internal repairs were undertaken. The applicants engaged R (a roofing specialist). The material provided indicates R provided a quote on 6 March 2013. An extract from the quote is provided in a letter from the FSP dated 22 March 2016. In relation to the leak to the front corner of the flat metal roof over the garage, the extract shows R was to install a new downpipe to cope with volume, remove rusted Case No: 449151 Determination Page 4 of 15 gable flashing, fold back the leaf guard at corner and investigate, and lift sheets if possible to ease water flow to the gutter. R also provided a report to the applicant stated 16 March 2013 in which he indicated: „…. during the storms of recent weeks that the strength of wind uplift and the volume of rainfall deposited on this roof was responsible for the damage at the near left corner. ‟ A provided a scope of works which included repair work and painting in the lounge room, removal of the TV antenna, and preparation and painting the soffit linings to the front and right hand side of the property. The material shows not long after the painting work was completed, there were complaints about the internal and external painting work. Particularly, the applicants complained the paintwork on the front porch bubbled when it rained. Due to the applicants‟ ongoing concerns with A, the FSP appointed a further builder (J) to report on and conduct rectification repairs. In August 2014, J provided a scope of works to rectify the work in the family room, (referred by A as the living room), front entry and front eaves lining. The material provided indicates this work was carried out in late 2014. The applicants continued to complain about issues particularly after rain and particularly to the painting at the front of the house. In early December 2014, the applicants arranged for the repair of cracked tiles above this area. The applicants contend this damage was caused in the February storm event. They say the cracked roof tiles were near where tree branches had damaged the TV antenna in the February storm. The FSP reviewed the applicants‟ photographs and considered the cracks were recent and not related to the 2014 event. The applicants asked J continue to be involved and undertake repairs as J should be responsible for work done. Complaints included repairs to the eaves as well as paint marks on brickwork. J appointed a roofing specialist (D) to provide a report on the condition of the roof above the eaves. D inspected and pho tographed the tiled roof only in January 2016. His report focuses particularly on the leak to the front patio roof. D said the roof leaked due to blocked water courses, additionally noting: „ There is significant debris built up in the water courses at the tiles and especially in heavy rain water can not flow correctly and is overflowing the sides of the tile. This is a maintenance issue and there is no storm or impact damage to this roof.‟ [sic] The FSP also appointed a building consultant (IT) to provide an opinion. IT inspected and photographed the applicants‟ property including the roof in April 2016. IT inspected the applicants‟ tiled and metal roofs, and was unable to locate any damage to the roofs caused by storm. He says the tile and metal roof covers are susceptible to rain water penetration because of tile side lap blockage caused by the many nearby trees, the poor condition of sarking and valley gutter overflow. Case No: 449151 Determination Page 5 of 15 He also identified the metal skillion roof above the family room was under pitched, there was a concentration of rain water run-off and some of the fastener fixing holes are exposed to rain water ingress. He saw no damage to the tile roof caused by the 2013 antenna damage. He also reported: „ My inspection of the terracotta tile roof cover, above the formal living room, revealed no broken, no crac ked and no displaced roof tiles.‟ As set out earlier, the applicants provided a report from their roofing specialist (R) in support of their claim. Correspondence from the applicants indicates R inspected the tiled roof, but if R did so, there is no report of this inspection. Rather, the applicants have only provided a report from R about the March 2013 inspection of the metal roof on the left-hand side of the home. R said the storm was responsible for the damage at the near left corner and repairs there should be done. Material provided establishes R provided a quote in March 2013 to repair the metal skillion section of the roof in the amount of $1,386 and repairs were made soon thereafter. In its letter dated 14 July 2016, the FSP said it had provided a cash settlement of $636 for some of this work. The applicants also provided a report from (E). The report was obtained prior to purchasing the home in December 2012. The applicants say these two reports establish the condition of the roof prior to the storm event, and the resultant damage to the roof was caused by the storm. Evidence establishes roof not damaged by an insured event The applicants‟ expert E said the overall condition of the roof was acceptable and the overall condition of the roof coverings is fair. However, I consider E‟s statement must be qualified as E did not actually access the roof but reports the roofing materials were viewed from a distance only. He recommended further investigation should be carried out prior to purchase. Relevantly, E states it: „…cannot and does not offer an opinion or warranty as to whether the roof leaks or may be subject to future leakage… If any sections of the roof were inaccessible … further invest igations should be carried out prior to purchase… It should be noted that when roofing cannot be inspected in detail, other associated aspects of the roofing are often not inspected in detail. These may include items such as gutters, eaves, flashings, chimneys and other items that would require a detailed and close inspection of the roof surface… A roofing expert should further evaluate the roof area.‟ Although E recommended further inspection of the roof area, there is no material to establish this occurre d. I am satisfied E‟s report sufficiently demonstrates the roof was not inspected closely on or behalf of the applicants prior to the storm event. In the circumstances, I do not accept E‟s report is sufficiently persuasive about the condition of the roof prior to the February 2013 storm event. Case No: 449151 Determination Page 6 of 15 I have considered the other submissions, reports and photographs. I note the other inspections of the roof of the applicants‟ home. None of them note storm damage to the roof. The contemporaneous reports by A and by R note no storm damage to the tiled roof. R only notes relatively minor storm damage to the near left corner of the metal roof. D says he did not observe any impact or storm related damage. His focus was on the tiled roof only and the leak to the front pa tio roof. IT states he did not observe any damaged tiles nor did he note any storm caused damage to the “external fabric.” IT suggests the cause of water entry to the home was because of maintenance and structural issues not storm damage to the roof. Both D and IT inspected the roof in 2016. The metal roof repairs recommended by R were already done. R makes no comment about the tiled roof. R inspected the metal roof a short time after the storm event and only identified storm damage at the near left corner of the metal roof. R does not describe the storm damage specifically nor is there a photograph of the roof from him at the time of his inspection. While the applicants make other submissions about R‟s opinion, these submissions are not sufficiently persuasive compared to the only written report provided by R which refers to relatively minor storm damage to the near left corner of the metal roof only. In the circumstances, I am not satisfied the material from R establishes there was storm damage to the tiled roof. A also inspected the roof a short time after the storm event. A describes a skillion roof. A describes a number of reasons for water ingress but does not identify the damage at the near left corner of the metal roof as identified by R. I have considered the submissions made by the applicants concerning other rainfall events before the pre-purchase inspection and before the rain event of 23 February 2013. However, in view of the inspections of the roof by the various experts, this submission is insufficiently compelling. In the absence of other independent expert evidence, and taking into account the observations made by those experts who have examined the roof, I am not persuaded from the material provided that on the balance of probabilities the tiles above the eaves, the gutter or the fascia board suffered impact damage in the storm. Further, contentions made about the lack of independence by IT are insufficiently compelling. The criticisms made by the applicants of the IT‟s report are either not supported by independent expert evidence or do not detract from the overall preponderance of the expert evidence. Having carefully considered the available material, I am not satisfied the applicants have established on the balance of probabilities the tiled roof was damaged by storm or by impact damage in the storm. Case No: 449151 Determination Page 7 of 15 On the information provided, the FSP is entitled to decline cover for storm damage to the tiled roof. As R is a roofing professional, I prefer his opinion over the opinion of A and I am satisfied there was damage to the left corner of the metal roof caused by the storm event in February 2013. The FSP has paid already $636 for damage to the near left corner of the metal roof. The material provided indicates the remaining part of R‟s quote referred to the installation of a downpipe to cope with volume. This is not storm damage. In all the circumstances, on the material provided, I am not satisfied on the balance of probabilities the applicants have established there was any other storm damage to the metal roof or the tiled roof. On the information provided, and for the reasons stated, the FSP is not obliged to make any further payment to the applicants for storm damage to the tiled or metal roof. 2.2 Is the FSP required to expand its scope for rectification repairs? Applicants must establish entitlement to repair guarantee The parties accept internal repairs were conducted by A and J, under the instruction of the FSP. The terms of the applicants‟ policy states repairs conducted in this manner are subject to a lifetime repair guarantee. Consistent with previous determinations, the onus is on the applicants to establish an entitlement under the repair guarantee. This means there must be evidence which establishes the repairs have failed, or are otherwise unsatisfactory, as a result of the FSP‟s tradespersons‟ work or the FSP‟s conduct. FSP paid $3,053 to the applicants for rectification repairs The applicants told IT there were five areas require rectification, being:  quality of paintworks to the family room ceiling  quality of paintworks to a cupboard wall in the family room  recurring blistering t o the veranda‟s soffit lining  discolouration to the ceiling around smoke alarm in the living room  paint marks on external brickwork following repainting of the soffit lining. The FSP paid to the applicants $3,053 for rectification. Although the FSP refers to various estimates from J the actual estimate from J was not provided. FSP’s expert criticises original assessment of the FSP’s assessor In relation to rectification repairs, the FSP relies on the report from IT who inspected the family room, formal living room and front veranda soffit and surrounds. IT noted recent water stains in the ceiling of the family room and said this was because the roof was under pitched, received concentrated rainwater run-off from the Case No: 449151 Determination Page 8 of 15 tile roof valley gutters and had exposed fastener fixing holes in the roof sheet pans which had previously secured the tree leaf gutter guard. IT said the latter accounts for the paint degradation to the back wall within the family room cupboard. Because A‟s report made no mention of these three roof defects, IT said A‟s assessment was flawed. As for the complaint about recurring blistering paint to the front veranda‟s soffit lining, IT noted the front veranda roof drainage was inadequate in that there was excessive spacing between the downpipes. Again IT criticised A‟s assessment. IT said contrary to the advice of A, the excessive spacing between downpipes was not the cause of gutter overflow onto the back of the soffit. Rather, IT said improper installation was the cause because the top of the gutter was not low enough but was finished flush with the top of the fascia board. IT says had it been properly installed, water overflowing from the gutter would have discharged to the exterior rather than onto the back of the soffit linings (as it still is). In summary, IT says the cause of first three items of the resultant damage is not because of the storm. Generally speaking, IT says the cause of the resultant damage are design flaws or maintenance issues which are excluded from cover. IT says the damage in the cupboard in the family room was caused by water entering holes in roof sheet pans. These holes are said to have been in place to affix a leaf gutter guard which was missing when IT inspected. The applicants provided a photograph of the leaf gutter guard, said to have come from A‟s report. The photograph, while in monochrome, appears to show a leaf gutter guard. The applicant contends the leaf gutter guard was re moved during A‟s repair. The FSP has not responded to this contention. Fair the FSP make contribution to some further rectification repairs I have carefully considered the available material, and note A does not identify any missing mesh or issues with the leaf guard, or holes in the roof sheeting proximate to the leaf guard. If such an issue of missing mesh, and holes in the roof were present at the time of the initial claim, and contributing to water ingress as proposed in the IT report, it would be reasonable to expect such issues to be raised as maintenance concerns, such as the maintenance concerns raised by A at that time. Rather, the available evidence suggests issues arising from the missing leaf guard occurred sometime after A‟s assessment and during or after A‟s repairs. Taking all matters into account, while I consider the available expert material indicates issues with the applicants‟ roof to which the policy does not respond, I also consider it is fair in all the circumstances the FSP make some contribution to the applicants‟ claim for rectification repairs to the following:  the paintworks to the family room ceiling  the paintworks to a cupboard wall in the family room  the recurring blistering to the veranda‟s soffit lining Case No: 449151 Determination Page 9 of 15 This is because the FSP undertook the repairs which are still not satisfactory and, while there were ongoing complaints by the applicants to the FSP about the quality of repairs, the FSP has not rectified its repairs and did not identify the reason why its repairs required rectification until the report from IT. This report clearly criticises the assessment made by A about the cause of damage. Had the FSP properly repaired and properly assessed and identified the initial cause of the damage and cause of the continuing damage the applicants would have had opportunity to rectify all the issues with the roof before repairs were commenced. The material indicates the applicants have had the roof inspected both by R and by a roofer who repaired the cracked tiles at the front of the house. However, the issues identified by IT were not identified by the applicants‟ own trades either. Therefore, taking this into account, I am satisfied it is fair in the circumstances the FSP make a 50% contribution to the applicants‟ claim for rectificat ion repairs to the paintworks to the family room ceiling, the paintworks to a cupboard wall in the family room and the recurring blistering to the veranda‟s soffit lining. The applicants have indicated concern there may be other internal damage such as the insulation in the ceiling in the family room. I am also satisfied it is fair in the circumstances the FSP contribute 50% of the cost of any other internal damage sustained in the areas of the family room ceiling, the cupboard wall and the veranda soffit lining as a result of the FSP‟s inadequate repairs and initial assessment of the cause of damage. The FSP is not obliged to make any contribution to discolouration to the ceiling around smoke alarm in the living room. This is because I am satisfied the available information establishes there are no broken tiles above this area of damage and the damage is caused by obstruction of the valley gutter which is a maintenance issue and excluded from cover. The applicants also claim the sarking is in poor condition. However, I am satisfied the available information establishes on the balance of probabilities this is caused by the debris from the numerous surrounding trees causing blockage of the roof tiles side lap channels through accumulated sediment. This is a maintenance issue and not covered by the policy. The parties agree the FSP will remove the paint marks. However, the parties do not agree on the cost of the removal of paint marks. This will be discussed in greater detail in section 2.3 below. 2.3 Was the FSP entitled to cash settlement additional rectification works? Cash settlement is appropriate to finalise dispute The FSP says it agreed to accept the applicants‟ resultant damages, in circumstances where it was otherwise entitled to deny the claim. The FSP says it has discharged its obligations in this instance. Case No: 449151 Determination Page 10 of 15 FOS has drawn FSP‟s attention to the proposition that an insurer cannot arbitrarily change its election once it has chosen to carry out repairs. This means, if an insurer elects to carry out repairs, it is bound by that election until completion. In line with that well established proposition, FOS will not readily accept a change of election by an insurer. However, in the circumstances of this claim, having considered the policy terms, repairs undertaken, the status of the dispute, and the available evidence in relation to the condition of the roof, I consider cash settlement is the most appropriate way to bring finality to the dispute. Notably, the available material suggests there are ongoing issues with the roof. Therefore, should additional rectification works be undertaken by the FSP, the available material suggests the works will not be successful. FSP has not established cash settlement is sufficient The applicants provided no independent expert material about the cost of the rectification repairs. The FSP says it offered $3,053 for the rectification works, comprising $2,553.42 from a verbal estimate from J, and $499.58 as a good will gesture. FOS requested a copy of J‟s estimate or costings f or consideration. This was not provided. In any event, given the findings further rectification works are to be attended to, J‟s estimate is no longer reflective of the required works. In order to resolve the dispute, and subject to the applicants‟ accepta nce of this determination, the FSP is to instruct J to prepare a revised estimate, which includes the additional rectification works of the paintworks to the family room ceiling, the paintworks to a cupboard wall in the family room and the rectification of the recurring blistering to the veranda‟s soffit lining. J is also to address the cost of any other internal damage sustained in the areas of the family room ceiling, the cupboard wall and the veranda soffit lining as a result of the FSP‟s inadequate rep airs and inadequate assessment of the cause of damage. The FSP is liable to pay to the applicants 100% of the cost to rectify the paint marks on the brickwork following repainting of the soffit linings and 50% of the cost of the additional rectification works to the paintworks to the family room ceiling, the paintworks to a cupboard wall in the family room and the rectification of the recurring blistering to the veranda‟s soffit lining and any other internal damage identified by J. Should J‟s revised estima te exceed $3,053, the FSP is to pay interest on the difference from 14 July 2016, being the date the original cheque was issued. However, it is fair in all the circumstances that should the revised estimate be lower than $3,053, the FSP is not entitled to recoup its losses and need pay nothing further in relation to the rectification work. Case No: 449151 Determination Page 11 of 15 2.4 Have the FSP’s repairs exposed the applicants to asbestos? Applicants’ concerns regarding exposure to asbestos first raised in 2014 Both before and after the dispute came to FOS, the applicants expressed concern about potential asbestos exposure from repairs. The applicants contend the repairs were not carried out properly in relation to the asbestos eaves linings. They say A did not i dentify asbestos in the eaves. Therefore, they have concerns A‟s work was not carried out to best practice guidelines as the eaves were scraped and sanded back next to bedrooms and a living area. They contend the eaves should not been repaired this way. They say the work commenced while they were at home and so they have concerns the likelihood of exposure to asbestos is high. The applicants say it supports their contention the FSP has not carried out correct repairs and cut corners. They also say the FSP has not adequately addressed this issue. The FSP referred to the Notice of Response and said the concerns were unrelated to the issues in dispute before FOS and asked FOS proceed to determination. In the meantime, the FSP said it noted the asbestos concerns which it would treat with care and correspond with the applicants directly. Environmental assessment arranged by FSP in 2017 The FSP arranged for an environmental assessment from BE. The instructions to BE indicated the eaves were initially prepared and painted but after additional damage the eaves linings were too damaged to repaint and were replaced. The instructions indicated the affected area would have been around 10m2. Scopes of work, photographs, and reports were provided to BE from the FSP. BE reviewed the documentation and concluded the works performed did not disturb a significant amount of asbestos bearing materials in a manner that would cause harm to the applicants or to their family. But he also said it was not best practice to cut, grind or sand asbestos materials without careful containment except if working with less than 10m² material and in any event, to avoid sanding with power tools. In making his decision, BE made the following observations:  it was likely but not certain the original eaves were asbestos bearing  the reports did not indicate visibly friable asbestos  the eaves would not have been friable as if friable, the eaves would have been too soft for painting and would not have had enough integrity to act as sheets hanging under the eaves  the eaves are not in an habitable part of the house  a test for asbestos would have been helpful in 2013 prior to the later removal of the original eaves  the report from J of 14 April 2016 describe the paintwork is blistered and proposed a scope for sanding back an area of about 5m² Case No: 449151 Determination Page 12 of 15  as the area was less than 10m² it would lawful for an unlicensed person to remove the non-friable asbestos sheets  nonetheless, work procedures should minimise the release of dust or fibres using only non-powered hand tools and avoiding scraping or scrubbing the surface. Upon receipt of the report, the FSP provided a copy to the applicants. The FSP further advised the applicants the scope of works to J in August 2014 included a scope about the front eaves work in an area of about 5m². The FSP agrees that in October 2014, J discovered asbestos behind the paint which needed to be scraped back and a variation for additional work was submitted. In November 2014, the FSP says J completed the work removing the front eaves and veranda sheets. It says the eaves were covered and once certificates arranged, the eaves were removed approximately five days later. The FSP acknowledges it did not address concerns raised by the applicant in 2014 and apologised the concerns were not previously addressed. Applicants submit FSP’s report does not address their concerns The applicants challenged BE‟s report noting mistakes such as the date of the removal of the eaves. Further, they allege the report does not address their concern about the work done by A in 2013. The applicants also rely on the original scope of work from A in 2013 which contained an estimate of 27 m² for scraping blistered paint work. And, unlike J‟s 2014 scope of works, A‟s scope of works make no reference to asbestos. The applicants say J had the eave linings tested/inspected by an asbestos professional and they were correctly removed under asbestos guidelines. The applicants agree a test for asbestos would have been helpful in 2013 and asserts because this was not done A put the applicants and their family at great risk performing work on the asbestos eaves. Asbestos issue relates to dispute about unsatisfactory repairs I acknowledge this issue was not referred to in the applicants‟ referral to FOS and was therefore not referred to in the Notice of Response. I accept there was no deliberate intention to exclude information in these circumstances. However, I do not accept the issue is unrelated to the issues in dispute. This is because this is a dispute about the unsatisfactory repairs by the FSP. Furthermore, I am satisfied from the material provided this issue was the subject of correspondence between the parties in 2014 and yet not addressed by the FSP until the dispute came to FOS. The FSP acknowledges this oversight and has apologised. The FSP’s report does not address the applicants’ concerns about 2013 work I have carefully considered the material provided. I am satisfied of the following:  the eaves were lined with asbestos fibre sheeting Case No: 449151 Determination Page 13 of 15  A assessed the damage and did not identify asbestos  Item 9 of A‟s scope of works says: “scrape blistered paint work and prepare and paint soffit linings to the front and RHS of the property. Approx 27 m² (painter)  in a letter of 28 March 2014, the applicants referred to concerns regarding the paint on the asbestos eaves at the front of the house  on 5 August 2014, the applicants first raised the concern the painters were allowed to paint and scrape back asbestos eaves  on 6 August 2014, the FSP indicated it would allocate the matter to J to attend and review the workmanship and it would address the asbestos concern  J‟s scope of works was after this complaint  J‟s scope refers to seal and paint the eaves with the area being approximately 5m² and addresses the issue of the care required when handling asbestos  the asbestos concern does not appear to have been addressed until after the matter came to FOS. Having considered the material provided, I am satisfied the report from BE does not address the applicant s‟ concerns about the work done in 2013 with sufficient particularity. It agrees a test for asbestos in 2013 would have been helpful yet this is this was not done until 2014. The report says when working with less than 10 m² of bonded asbestos a specific license is not required. However, A‟s material from 2013 indicates work was undertaken to up to 27 m². Further, even when working with less than 10 m², BE says work procedure should minimise the release of dust or fibres including using only non-powered hand tools. It is not known how the work was done in 2013. Further report to be prepared by an asbestos expert about 2013 work Having considered the material provided, I am satisfied it is fair in all the circumstances the FSP arrange, at its expense, for a further report to be prepared by BE or by an asbestos expert to be agreed by the parties. Both parties can make written submissions to the expert, if required. The report is to focus on what work was done to the asbestos eaves by A in 2013 and exactly how that work was carried out. The report is to determine whether the work was carried out in accordance with regulations. The report is also to determine whether the work was carried out safely and thoroughly analyse and report on the risk of asbestos exposure (if any) to the applicants and their family. 2.5 Are the applicants entitled to com pensation? Compensation paid in some circumstances FOS‟s Terms of Reference allow the payment of compensation (capped at $3,000) for non-financial loss. FOS may decide an FSP should compensate an applicant for such loss only where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the applicant‟s expectation of enjoyment or peace of mind. FOS takes a conservative approach to compensation for non-financial loss. Case No: 449151 Determination Page 14 of 15 The applicants make a number of complaints about the FSP‟s claims handling. The applicants also complain the FSP wrongfully tried to force the applicants to accept money offered for paint damage rectification works as a full and final settlement of the dispute. FSP to pay the applicant $3,000 compensation However, whatever the approach taken to the applicants‟ other complaints, I have particular concern about the FSP‟s response to the applicants‟ concerns regarding asbestos exposure. I consider the FSP‟s conduct in this regard has interfered with the applicants‟ expectation of enjoyment or peace of mind and there has been an unusual amount of time taken to resolve the situation. The concerns regarding asbestos were serious. They were not addressed in 2014. They were still not properly addressed recently. While acknowledging the apology from the FSP, I am satisfied it is fair in the circumstances the FSP pay to the applicants $3,000 compensation. Case No: 449151 Determination Page 15 of 15 3 Supporting information 3.1 FOS Approach As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS recommendation and has proceeded directly to determination. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. It is an accepted principle of general insurance law that an insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. 3.2 Relevant policy extracts The relevant policy extracts are referred to in the FSP‟s Notice of Response dated 2 September 2016. Both the policy document and the Notice have been exchanged with the applicants. 3.3 Other relevant material considered and relied on  Parties‟ submissions, emails, photographs, reports and all attachments to all submissions.  Correspondence between the parties.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.