Builder home indemnity insurance accepted at $100,000 for $800,000 construction contract

FirmFinancial Firm (Unknown - Credit)
Decided2017-03-10
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The Mr and Mrs Y complained about construction loan progress payments, loan classification, builder insurance and a refinancing statement. AFCA found the FSP acted correctly and ordered no compensation, the builder insurance point being the only issue considered further.

The FSP acted as lender for its own security purposes and owed no duty to the applicants to verify the builder's insurance beyond the lending terms.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 449024 Determination Page 1 of 4 Case number: 449024 10 March 2017 1 Overview 1.1 Dispute On 17 October 2013, the applicants (Mr and Mrs Y) obtained a home loan, construction loan and business loan (the loans) with the financial services provider (FSP). The applicants say the FSP:  released progress payments seven and eight under the construction loan to the builder before he had completed the work  incorrectly created the construction loan as an investment loan instead of a residential home loan  accepted a home indemnity insurance policy from the builder for $100,000 when the value of the construction contract was $800,000 and  told them in 2015 that if they refinanced the home loan to another bank, it would not lend them more money to complete the construction. On 19 December 2016, a Financial Ombudsman Service (FOS) case manager provided the parties with a recommendation on the issues in dispute. The recommendation was in favour of the FSP. A copy of the recommendation is attached to this determination. The applicants have rejected the recommendation. They say the FSP should not have allowed the builder to only obtain insurance for $100,000 when the value of the construction contract was $800,000. 1.2 Issues and key findings Were the findings of the recommendation correct? The findings contained in the recommendation were correct and are adopted in this determination . Further submissions provided after the recommendation have been considered. Based on all the available information I agree with the findings in the recommendation and I am satisfied that the Case Manager adequately dealt with the issues in dispute. The applicants have only provided reasons for rejecting the recommendation in relat ion to the issue of the builder‟s insurance. Accordingly that is the only issue I will consider further in this determination. Case No: 449024 Determination Page 2 of 4 Should the FSP have obtained further evidence of insurance? The FSP requested evidence of insurance from the builder for its own security purposes, not on behalf of the borrower. The indemnity insurance provided was up to the limit allowed of $100,000. If the applicants required further insurance or wanted to ensure the builder to have further insurance, it was for them to organise in association with the builder and was not the responsibility of the FSP. 1.3 Determination This determination is in favour of the FSP. The applicants are not entitled to any compensation. I agree with the case manager‟s reasons for the recommendation and the recommended outcome. Case No: 449024 Determination Page 3 of 4 2 Reasons for determination 2.1 Were the findings in the recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the case manager‟s recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. Based on all the available information I agree with the findings in the recommendation and I am satisfied that the Case Manager adequately dealt with the issues in dispute. As the applicants only provided reasons for rejecting the recommendation in relation to the issue of the builder‟s insurance , that is the only issue I will consider further in this determination. 2.2 Should the FSP have obtained further evidence of insurance? The FSP requests evidence of insurance for its own purposes The applicants say that the FSP accepted evidence of home indemnity insurance cover of only $100,000. They say the FSP should have insisted on further cover for the value of the construction contract of $800,000. A builder in Western Australia is required by law to obtain home indemnity insurance at their own cost to protect the owner of the property against financial loss. As set out in section 3 below, the maximum home indemnity insurance that can be obtained (or paid out) is $100,000. The builder is required to give a copy to the owner before commencing work. The home indemnity insurance does not limit a builder‟s liability to the owner. When the FSP requested evidence of home indemnity insurance, it did so for its own security and prudential purposes and not on behalf of the applicants. The applicants should have already received a copy of the indemnity insurance from the builder and ensured they and the builder otherwise had sufficient insurance. Generally it will be up to the customer and their builder as to what level of further insurance they require beyond the home indemnity insurance. Although there is no information to show the FSP obtained evidence of any further insurance, there is no loss to the applicants that flows from this. If the applicants required further insurance at the time, then that was a matter they should have attended to or raised with the builder. It was not the responsibility of the FSP to review their insurance position on their behalf. Case No: 449024 Determination Page 4 of 4 3 Supporting information  Western Australia Government Department of Commerce, Home indemnity insurance www.commerce.wa.gov.au/publications/home -indemnity-insurance .  Relevantly, the publication states: “[ Home indemnity insurance] protects owners against financial loss if a builder cannot complete residential building work or meet a valid claim for faulty or unsatis factory building work becaus e of death, disappearance or insolvency…. The policy must require the insurer to pay up to $100,000 or the value of the contract work (if it is less than that amount) and no more than $20,000 for loss of deposit. This is the maximum amount that the insurer must agree to pay out while the policy is in force ….” Recommendation Case No: 449024 Recommendation Page 1 of 8 Case number: 449024 19 December 2016 4 Overview 4.1 Dispute On 17 October 2013, the applicants obtained a home loan, construction loan and business loan (the loans) with the Financial Services Provider (FSP). The applicants say the FSP:  released progress payments seven and eight under the construction loan to the builder before he had completed the work  incorrectly created the construction loan as an investment loan instead of a residential home loan  accepted a home indemnity insurance policy from the builder for $100,000 when the value of the construction contract was $800,000  told them in 2015 if they refinanced the home loan to another bank, it would not lend them more money to complete the construction. They wanted to refinance the home loan to obtain additional finance to open a second shop for their business. The FSP‟s actions caused them to miss the opportunity to do so. 4.2 Issues and key findings Should the FSP have released progress payments to the builder? The FSP released progress payments after the applicants signed the relevant forms and acknowledgements. There is no information to show the FSP misled the a pplicants or told them the construction “looks all good”. Should the FSP have created the construction loan as a residential loan? The FSP‟s lending submission shows the applicants were going to rent the property for the foreseeable future before moving in themselves. The available information suggests the FSP correctly established the construction loan as an investment. Did the FSP accept a home indemnity insurance policy for $100,000? Home indemnity insurance in Western Australia covers completion of the residential building work and defective workmanship up to $100,000. The FSP‟s policy required it to obtain a copy of the builder‟s all risk insurance. It is not clear if it did. However, even if it did, it did for its own purposes to cover its interest in the security property. Did the FSP tell the applicants it would not lend them additional money if they refinanced the home loan to another bank? There is no information to establish this claim. However, even if the FSP did, it is likely that would have been a correct statement of fact at the time. This is because Case No: 449024 Recommendation Page 2 of 8 the applicants would have reduced the equity they had available with the FSP. The applicants chose to cancel settlement and keep the home loan with the FSP. 4.3 Recommendation This recommendation is in favour of the FSP. The FSP has not made an error or breached a duty or obligation it owed to the applicants. As such, the FSP is not required to award them any compensation. If the applicants are experiencing financial difficulty, then, within 14 days of both parties accepting this recommendation:  the applicants should provide a completed statement of financial position to the FSP (with supporting documents) and a repayment proposal to see them overcome their financial difficulty within a reasonable period  the FSP should give genuine consideration to the proposal  if the parties cannot agree upon a reasonable arrangement within 14 days of the applicants submitting their proposal (or if they do not submit a proposal) and if they are in default under the terms of the loans, the FSP can commence recovery action against them. Case No: 449024 Recommendation Page 3 of 8 5 Reasons for recommendation 5.1 Should the FSP have released progress payments to the builder? The applicants signed and authorised the FSP to release the payments The a pplicants‟ contract with their builder required them to make nine payments totalling $800,000. The FSP was to make these payments on their behalf and debit them to the construction loan account. Before the FSP released each payment to the builder it asked the applicants to sign and return a progress payment authority (the authority). The authority said, amongst other things: I/we advise that the building being constructed for me/us by the Builder has been completed to the said construction stage to my/our satisfaction according to the builder‟s certificate and building contract. I/we authorise the Bank‟s agent to inspect the building work. I/we acknowledge tha t any inspection made on behalf of the Bank is done solely at the Bank‟s discretion, for the Bank‟s security purposes only and is not construed as an inspection for or on behalf of me/us or the builder. The applicants confirm they signed each of the authorities before the FSP released the payments to the builder. As such, the FSP had the appropriate mandate from the applicants. The FSP acted appropriately and correctly when it released the payments to the builder, upon receipt of the signed authorities from the applicants. There is no information available to show that the FSP misled the applicants The applicants say they had issues with the builder and raised these issues with the FSP bank managers. They say they signed the authorities because the FSP:  told them their issues were no big deal and did not raise any concerns about releasing the payments  said it was not unusual for a builder to be slightly ahead of or behind work and there were no issues with releasing the payments  would drive past the new property and tell them it “looks all good” . The FSP says the relevant bank managers no longer work with the FSP so it is not able get a statement from them in response to these claims. However, under the terms and conditions of the loans the applicants were required to inform the FSP in writing if they were not satisfied with the builder‟s work. If they did not, then they authorised the FSP to make the payments. The applicants did not send anything in writing to the FSP. Instead, they say all o f the conversations were verbal. The applicants have not established their claim in this regard. The FSP did not owe any fiduciary duty to the applicants The applicants say the FSP breached its duty of care to them because it was not concerned about the issues they were having with the builder. Case No: 449024 Recommendation Page 4 of 8 In general, a financial services provider does not have a fiduciary duty or responsibility to its customer. In this case, the FSP‟s position is as a lender, not an adviser. There is no information to show the FSP‟ s role extended beyond that of a finance provider. Under the terms and conditions of the loans, the applicants alone were responsible for ensuring all plans were followed and the materials and workmanship were satisfactory. Even if the FSP was also monitoring the works, it would have done so in its capacity as a lender assessing its security. All information shows the FSP acted correctly and appropriately when it released payments to the builder. The a pplicants‟ dispute is more appropriately directed against the builder for allegedly failing to perform his obligations under the building contract. I note the applicants are currently engaged in legal action in court against the builder. 5.2 Should the FSP have created the construction loan as a residential loan? FOS provides more weight to contemporaneous documentary information The applicants say the FSP should have created the construction loan as a residential loan instead of an investment loan because they were going to live in the property. They have not provided any documents or information to support their claim. FOS is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess disputes, we consider available documents, the recollection of the parties, and all relevant circumstances. We give more weight to contemporaneous documentary information. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. The lending submission suggests the applicants intended to rent the property The FSP has provided a copy of its lending submission for the approval of the loans dated 1 October 2013. The relevant sections of the lending submission are set out in section 3.1 below. This is the only relevant document available that was created at the time the applicants applied for and obtained the loans. The FSP‟s lending submission says:  the a pplicants intended to rent the property for the “foreseeable future” and possibly use it as a family residence later depending on whether they sold their owner occupied home  landscaping works were included in the building contract so tenants could move in immediately upon completion. The available information shows the property was initially to be an investment The construction loan schedule informed the applicants that it was a loan for investment purposes. For example: Case No: 449024 Recommendation Page 5 of 8  at the top of page one in bold font it says „Variable Rate Home Loan Privileges Package Discount Variable Rate Investment Home loan Schedule‟  on page seven, next to where it says „Loan Type‟ , it says „Investment‟. By signing the construction loan contract they acknowledged they read and accepted the information in the schedule and the general terms and conditions. All information shows the FSP correctly created the construction loan as an investment. This means the FSP is not required to compensate the applicants for their claimed losses. 5.3 Did the FSP accept a home indemnity insurance policy for $100,000? If FSP got information about the builder’s insurance it did for its own purposes The applicants say the FSP made an error by accepting a home indemnity insurance policy from the builder for $100,000 when the value of the construction contract was $800,000. They say the FSP should have obtained documents showing the builder also had other insurance in place. In Western Australia, home indemnity insurance covers the completion of the residential building work at no additional cost to a limit of $100,000. The policy must cover potential claims for defective workmanship made up to six years from practical completion up to a maximum of $100,000. However, the applicants are only entitled to claim under a home indemnity insurance policy if the builder dies, disappears or becomes insolvent. None of these have occurred. The FSP‟s policy also required it to obtain a copy of the builder‟s all risk insurance cover inclusive of the specific property under construction with the FSP listed as an interested party. It is not clear if the FSP obtained this information. However, even if it did, it would have done so for its own purposes as mortgagee to protect its interest in the security property. It owed no duty to the applicants to obtain this information. That obligation rests with the applicants. 5.4 Did the FSP tell the applicants it would not lend them additional money if they refinanced the home loan to another bank? If the FSP provided this information, it was likely a correct statement of fact In April 2015, the applicants obtained approval for a business loan with another bank to purchase a second shop for their business. They say, just before settlement, the FSP told them it would not lend additional money to complete the construction if they refinanced the home loan. As a result, they cancelled settlement and kept the home loan with the FSP. There is no information to show the FSP made this statement to the applicants. However, even if it did, it is likely that would have been a correct statement of fact at the time. If the applicants were to refinance their home loan to another bank along with their owner occupied property, they would have reduced the amount of equity available with the FSP. This means the $245,000 business loan and $800,000 construction loan would have been secured solely by the new property. The FSP‟s most recent valuation provided an „as if complete‟ value of $1,310,000. Case No: 449024 Recommendation Page 6 of 8 In general, a financial services provider will approve lending up to 80% of the value of its security without lenders mortgage insurance (LMI). This means without LMI the applicants could have borrowed $1,048,000 from the FSP. As the y had existing debts totalling $1,045,000, the applicants had already reached their borrowing capacity. The FSP is not required to compensate the applicants The a pplicants say the FSP‟s actions caused them to miss out on the opportunity to buy the second shop and the associated income. However, as outlined above, the FSP did not mislead the applicants. If a representation was made, it is more likely than not the FSP provided a correct statement of fact about their potential future lending. This cannot be construed as misleading conduct. The decision to refinance or to keep the home loan with the FSP rests with the applicants. Ultimately, they decided to keep the home loan with the FSP. The FSP has not made an error and is not required to compensate the applicants for this. Case No: 449024 Recommendation Page 7 of 8 6 Supporting information 6.1 Relevant sections of the FSP’s lending submission for the loans Purpose: The clients would like to refinance their existing facilities with [two other banks] over to [the FSP]. They would also like a loan to build a house on a block of land in [I], there is no fixed price contract as of yet as the customers would like to be conditionally approved first before signing anything. They will be renting out the newly built house for the foreseeable future, and possibly in the long term use it as a family residence depending on whether they sell [their current primary place of residence]. … 4) The clients have about $30K in the bank to cover any shortfall during the construction period until tenants move in… 5) After conversation with customers, the contract will include landscaping so property will be ready to be leased when construction concludes. … 6.2 Relevant sections of the general terms and conditions 2. Our additional requirements if you have a construction loan … General requirements for construction loans 2.3 If you have a construction loan: … (b) you alone are responsible for ensuring that all plans are followed and that materials and workmanship are satisfactory even if we also monitor the works. (If we do so, it is only for our own purposes, and even if we make a loan advance, it does not mean the works are necessarily satisfactory). We are not liable for the quality of, or any delays in, the works; … (f) notwithstanding clause 2.5 of this Part B, you are responsible for any payments made to your builder. We have no contractual relationship or obligations to your builder; … (h) you must tell us in writing if you are not satisfied with the works. If you do not tell us, you authorise us to make payments to your builder. … Case No: 449024 Recommendation Page 8 of 8 2.9 The making of any advance shall not be construed as proof or admission that the works or any part of the works have been undertaken in accordance with this contract. … Inspections under a construction loan 2.10 We may require an inspection of the works at any time. The inspection may be conducted by us or a consultant that we nominate. If we monitor works (such as inspecting or accepting any part of the works construction or approving plans), we will be doing so for our own purposes. We do not owe you any duty to exercise care or skill in doing so and we need not tell you the results of any inspection.