Home / Financial Firm (Unknown - Insurer) / Determination 448790

Determination 448790

claim_handling

FirmFinancial Firm (Unknown - Insurer)
Decided2017-06-19
ProductGeneral Insurance · Landlord
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$250
Amount claimed$500
SourceAFCA PDF

Summary

The landlord claimed for storm damage to a tenanted property, which the FSP accepted and repaired over six months. AFCA found the FSP erred in its longer-term claim management and withdrew its apology, and ordered $250 for non-financial loss without waiving the excess.

Initial delays were unavoidable given the widespread weather event, but the FSP's later claim management was deficient and its withdrawn apology left no adequate remedy, justifying a small conservative award.

Issues

Subjects and remedies

pay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 448790 Determination Page 1 of 6 Case number: 448790 16 June 2017 1 Overview 1.1 Dispute The applicant lodged a claim under his landlord insurance policy held with financial services provider (FSP) for storm damage to his tenanted property. The FSP accepted the claim and the damage has now been repaired. However, the applicant expects the FSP to waive the $500 policy excess and/or provide compensation for non-financial loss in light of its management of the claim. Whilst in itially apologising for the applicant’s claim experience (although not offering any compensation) by way of its IDR letter, the FSP appears to have withdrawn this apology and now maintains it did not err in its management of the claim. 1.2 Issue and key findings Is the applicant entitled to compensation for non-financial loss? The applicant is entitled to a small award of compensation for non-financial loss because the FSP appears to have withdrawn its initial apology for the applicant’s claim experience which otherwise would have been a sufficient remedy. On this basis, and in light of the conservative approach taken by FOS towards compensation for non-financial loss, the applicant is entitled to compensation in the amount of $250. 1.3 Determination This determination is partially in favour of the applicant. The FSP is to provide the applicant with compensation for non-financial loss in the amount of $250 within 14 days of any acceptance of this determination by the applicant. Case No: 448790 Determination Page 2 of 6 2 Reasons for determination 2.1 Is the applicant entitled to compensation for non-financial loss? Applicant dissatisfied with the FSP’s handling of the claim The applicant says he is very disappointed with the FSP’s handling of the claim on the following grounds:  the claim took over six months to be finalised  his elderly tenant remained without a kitchen light for the duration of this period  the tenant’s furniture was not removed and re -instated as quoted for  there were too many staff members dealing with the claim and this involved extended periods of time on the telephone  he is a loyal long term gold member who holds multiple policies with the FSP. For these reasons, the applicant expects the FSP to waive the policy excess and/or provide compensation for non-financial loss. The associated timeline of events is summarised in section 3 of this determination. FOS awards compensation for non-financial loss conservatively FOS can award up to $3,000 for non-financial loss if the FSP caused the applicant to suffer an unusual degree or extent of inconvenience, delay or interference. It is important to note that an award is based on an unusual degree or extent. This would not encompass the normal degree of inconvenience a person would suffer when lodging an insurance claim or in a dispute with their insurer. FOS takes a very conservative approach when considering any award of compensation. FSP initially apologised for the applicant’s claim experience The FSP initially acknowledged by way of its IDR letter the followi ng with regards to the applicant’s claim experience:  the timeframe to finalise the claim  the applicant feeling he was not listened to  the applicant being placed on hold for extended periods of time. The FSP apologised in this letter for the applicant’s cla im experience, although it did not deem any such issues as justifying an award of compensation. FSP appears to have retracted the initial apology In its subsequent response to the applicant and FOS, the FSP appears to have withdrawn any such apology saying: “these repairs were actioned in an appropriate manner … his repairs were organised efficiently as requested” The FSP also omits any reference to the other concerns raised by the applicant, in particular the time spent on the telephone with different claims staff. Instead, the FSP Case No: 448790 Determination Page 3 of 6 now suggests the nature of some telephone calls and contradictory instructions by the applicant hindered progression of the claim. Initial delays likely unavoidable due to nature of the weather event There is no dispute a significant weather event occurred in the vicinity of the applicant’s property causing the damage claimed and affecting many other properties in the area. Considering good industry practice is to prioritise claims involving significant property damage and/or issues relating to health and safety, I accept any delays in the initial weeks following the applicant’s claim were likely unavoidable. The damage to the applicant’s property appears to have been primarily cosmetic in the form of painting and replacement of a light, although there is contradictory information as to whether a temporary light was installed prior to its replacement taking place in March. However, the applicant’s claim was not finalised until some six months after original lodgement. Therefore, it needs to be considered whether the FSP’s on -going claim management was appropriate in the circumstances. FSP did err to a certain degree in its longer term claim management I accept the relationship between the parties broke down as the claim progressed which likely resulted in some level of miscommunication. I also accept the applicant was overseas for a period in April and May which delayed an on-site reinspection. However, I do not accept the FSP managed the claim as well as it could have. For example, it appears it was only on 14 March 2016 (following contact being made by the applicant) that the FSP identified that replacement of the strip light had yet to be completed. Further, there appears to have been little claim activity from mid-February to early March, and again from mid-March to mid-April. I also note rectification works regarding some paint work was required. This suggests some issue with quality control (also raised by the applicant during the course of the claim) and likely further inconvenience in arranging these rectification works to be completed. A small award of compensation appropriate in the circumstances As stated above, FOS takes a conservative approach towards any compensation for non-financial loss. In circumstances such as these, if it had not already done so, I would ordinarily take the view that the FSP should provide a letter of apology to the applicant. However, as discussed above, the FSP appears to have withdrawn its original written apology by way of its subsequent formal response to the applicant and FOS. Therefore, I am not satisfied the applicant would deem any further written apology as being genuine on the part of the FSP. Case No: 448790 Determination Page 4 of 6 For this reason and as an alternative, I am satisfied the FSP should pay a small award of compensation to the applicant. In my view, an amount of $250 is fair in all the circumstances. If the applicant accepts this determination, this amount should be paid within 14 days of such acceptance. Case No: 448790 Determination Page 5 of 6 3 Supporting information 3.1 Timeline of events Date Action 12 Dec 2015  Applicant lodges the claim. 17 Dec 2015  The FSP’s repairer (HR) contacts the applicant to obtain contact details for the tenant and managing agent. The applicant directs HR to the FSP to whom he had already given these details to. 23 Dec 2015  Make safe works undertaken to the roof of the property. 29 Dec 2015  The applicant expresses a desire for a different repairer to be appointed. The FSP appointed a second repairer (RC) and requests contact be made to arrange for an assessment. The request notes the real estate agent and tenant should be contacted to arrange a site visit and the applicant kept up to date on progress. 19 Jan 2016  The applicant raises a complaint with the FSP saying not hing is happening with the claim and requests the excess be waived. FSP contacts RC to make urgent contact. 29 Jan 2016  RC cont acts the applicant to advise an assessment has been organised with the tenant for 1 February 2016, but the applicant not appreciative of being contacted directly. 8 Feb 2016  The appl icant contacts the FSP to raise issue with the fact he is being contacted by RC when the real estate agent is the main contact. 9 Feb 2016  RC advis e the applicant was not appreciative of a call to try and arrange an assessment. RC advise its appointed paint er also contacted the applicant by mistake. RC says it will arrange for repairs with the tenant and provide a roof report regarding condition and m ake - safe works completed. During this week, the internal painting is also completed. 7 Mar 2016  The applicant calls to follow up on progress of the claim. The FSP advises it is waiting on the roof report from RC. The FSP agrees an on - site assessment with the applicant can then be undertaken. The applicant also advises if he thought it was just painting required, he would have withdrawn the claim and organised this himself.  The FSP contacts RC for an update as to works completed to date and an associated sc ope of works. 9 Mar 2016  The FSP receives the roof report. 11 Mar 2016  The real estate agent attends the property and provided a report to the applicant. The FSP also forwards RC reports to the applicant. 14 Mar 2016  The applicant raises issue with the fact the FSP does not know what repairs have been complet ed, and it is relying on the real estate agent to provide associated advic e. The applicant believes the fluorescent light has yet to be replaced (RC advis e a single strip light was installed as a tem porary measure and a double strip light due to be installed). The applicant requests an on - site meeting to review Case No: 448790 Determination Page 6 of 6 repairs to date. The applicant again requests the excess be waived due to claim handling and the fact he could have arranged for re - painting h imself.  The FSP follows up with RC regarding the light replacement which is excluded from the scope of works. 15 Mar 2016  RC confirm arrangements have been made to replace the light. 21 Mar 2016  RC replaces the temporary light with a permanent one. 18 Apr 2016  The applicant suggests a re - inspection date of 27 May 2016. 5 May 2016  RC confirm all repairs have been completed. 26 May 2016  The re - inspection is cancelled as the applicant has been uncontactable. 1 Jun 2016  The re - inspection takes place.  An issue with the paintwork to the ceiling is identified and requiring rectification. 6 Jun 2016  The applicant raises issue with the service level for which the FSP apologises. 11 Jun 2016  All rectification works are completed. 30 Jun 2016  The applicant contacts the FSP to raise issues with the service levels. 1 Jul 2016  The applicant raises issue with the fact the repairs should have been completed within two weeks and for less than the excess. The applicant says an on - site assessment did not take place until June despite repeated requests prior (the FSP says the applicant was overseas).

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.