Determination 448727
Extent of hail damage liability for shared roof replacement
Summary
The body corporate's strata policy covered November 2014 hail damage to a shared roof. The FSP accepted liability for 58% of the roof, and the applicant sought full replacement; AFCA found the FSP liable for further damage to roof 15, two gutters and one panel each on roofs 2 and 3, but not the rest of the roof.
The policy requires reinstating only the damaged portions to substantially the same condition as when new, so undamaged roof sections are not covered.
Issues
- Claim amount dispute primary · upheld
“I am satisfied that in addition to liability already the FSP is liable to: replace the damaged gutters on roof 9 and 14, replace roof 15.”
- Repairs or contractors secondary · not upheld
“The FSP is otherwise entitled to refuse liability to replace the remainder of the roof as I am satisfied based on the available information that it remains undamaged.”
Subjects and remedies
home or building damagenatural disasterrepair or rectify
Text of the determination
Determination
Case No: 448727 Determination Page 1 of 9
Case number: 448727 9 August 2017
1 Overview
1.1 Dispute
The applicant held a Residential Strata Insurance Plan in the name of the body
corporate underwritten by the financial services provider (FSP).
The shared roof of the property was damaged during the Brisbane hail storms in
November 2014.
The FSP accepted liability for the hail damage and agreed to replace 58 per cent of
the roof.
The applicant disputes the FSP’s decision and requests a full roof replacement.
1.2 Issue and key findings
What is the extent of the FSP’s liability?
I am satisfied that in addition to liability already the FSP is liable to:
replace the damaged gutters on roof 9 and 14
replace roof 15
replace only the damaged panels on roof 2 and 3
The FSP is otherwise entitled to refuse liability to replace the remainder of the roof as
I am satisfied based on the available information that it remains undamaged.
1.3 Determination
This determination is partially in favour of the applicant.
In addition to the damage already accepted the FSP is liable to replace the damaged
gutters on roof 9 and 14, replace roof 15 and replace the damaged panels on roof 2
and 3.
The FSP is otherwise entitled to refuse the balance of the applicant’s claim in
accordance with the terms and conditions of the policy.
Case No: 448727 Determination Page 2 of 9
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the information
exchanged.
This determination follows consideration of all of the information exchanged and is
based on what is fair in all the circumstances, having regard to the relevant legal
principles, terms of the policy, good industry practice including codes of practice and
prior determinations where applicable.
2.1 What is the extent of the FSP’s liability ?
Applicant has established a claim under the terms of the policy
The applicant ’ s policy is a broad form accidental loss and damage policy that
provides cover for accidental loss and damage which occurs during the period of
insurance. There is no dispute that the applicant ’ s property sustained damage from
the hail storm in November 2014.
FSP liable to either rebuild, replace or repair damaged property
The policy provides that where an insured property is damaged the FSP will choose
to either rebuild, replace or repair or pay that amount that it would cost to rebuild,
replace or repair the property. The relevant provisions are set out under Section 3.1
of this determination.
Essentially the policy provides that the FSP will pay the reasonable cost of rebuilding,
replacing or repairing to a condition in which is the equivalent to or substantially the
same as but not better nor more extensive than it was when new. In addition it will
pay any necessary extra costs incurred to comply with public, statutory or
environmental protection authority requirements.
The policy does not cover the cost to rebuild or replace undamaged portions of the
insured property.
The FSP has accepted liability for the equivalent of 58% of the damaged roof. The
applicant says that 80% of the roof was damaged and therefore it is appropriate to
replace the entire roof. Further the applicant says that:
it cannot obtain insurance with another insurance due to the damage
the unrepaired portion of the roof is susceptible to rust and corrosion
the value of the property will depreciate
the roof is not being returned to the condition it was in prior to the event
FSP liable only to repair the damaged portion of the roof
I am satisfied that the policy provides that the FSP is only liable to meet the
reasonable costs of rebuilding, replacing or repairing the damaged sections of the
roof.
Case No: 448727 Determination Page 3 of 9
The FSP has already accepted liability with respect to damage to roof 1, 6, 7, 8, 10,
11, 12, 13, 16, 17 (south side). There is no dispute with respect to this damage.
Both parties have obtained expert reports with respect to the balance of the damage.
The FSP has relied upon a report from MC.
MC has attended the property on a number of occasions and provided three reports.
In addition to the damaged areas already accepted MC identified the following
damage:
roof 2 – impact one panel on the north end of the roof
roof 3 – impact damage to one sheet
roof 4 – symmetrical damage but not hail related but due to impact
roof 15 – multiple minor dents across all 26 panels
The applicant also obtained expert reports from B and AH.
The report from B whilst identifying a number of roof dents created by hail as well as
damage to the ridge caps does not outline where the damage is located. B
comments that 80% of the roof is damaged.
AH provided a second report which is largely consistent with the report of MC. AH
identified damage to both roof 2 and roof 15 and damage to gutters of roof 9 and 14.
I accept that the reports of AH and MC are to be preferred over the reports of B. I
accept based on the reports that additional damage has been identified to roof 2, 3,
15 and to the gutters of roof 9 and 14.
FSP is liable for the additional damage identified in the reports of MC and AH
The reports from MC and AH identify dents to parts of roof 2, 3 and 15.
The FSP says that whilst there is damage, it is not extensive enough to warrant the
replacement of these areas.
The FSP refers to a technical bulletin (32) published by the manufacturer of the
sheeting which indicates the indentations from hail stones would not affect the life of
the roof and potentially areas of concern.
Insofar as there may have been a loss of paint from the surface due to the hail such
would only cause an aesthetic issue and have no impact on the corrosion
performance on the roof. The FSP maintains the roof is structurally robust in the
sections identified.
I accept the comments made in the technical bulletin and accept that the roof may
have been structurally robust. The policy wording however requires that the FSP
reinstate the applicant to a condition which is the equivalent to or substantially the
same as but not better than nor more extensive than when the roof was new.
The applicant ’ s roof was 13 years old at the time. Whilst there were some signs of
aging it was in good functioning condition prior to the event with no obvious signs of
hail damage.
Case No: 448727 Determination Page 4 of 9
The fact that the roof or some of the indentations could not be viewed from the
ground does not deter from the fact that the roof is damaged.
The applicant provided an email from the manufacturer noting the warranty would be
voided if hail damage to the roof could not be rectified. That was because corrosion
could form.
Whilst the FSP disputes this, the FSP’s assessor did not specifically rule out the
possibility of corrosion.
The relevant consideration is what is required to repair the roof to a condition which
is the equivalent to or substantially the same as but not better than nor more
extensive than when it was new.
FSP is liable to repair roof 15
Roof 15 consists of 26 panels all of which were damaged by a large number of minor
hails dents. Whilst the dents may not have caused significant deformation there is no
doubt that the dents were present in the roof.
I accept based on the available information that all panels on roof 15 sustained
damage and that in order to repair the roof to a condition which was equivalent to or
substantially the same as but not better than when new it is appropriate that the FSP
replace all of the panels on roof 15.
FSP to replace damaged panels on roof 2 and 3
The reports identify that both roof 2 and 3 consist of five separate panels.
On each roof only one panel has been damaged.
I do not accept that the FSP should have to replace all five panels on each roof. I am
satisfied in order to return the applicant to substantially the same position as it would
have been in it is only necessary that the FSP replace the damaged roof panels that
is one panel on each of roof 2 and 3.
FSP liable for damage to gutters on roof 9 and 14
AH identifies a number of dents to the inside section of the gutters on roof 9 and 14.
MC considered there were no dents to the sheeting of roof 14 but agrees there were
dents located on the vertical edge of the flashing. MC did not comment on the
damage to the gutters on roof 9.
Whilst I accept that the dents were not readily identifiable from the ground and that
water would not pond to cause deterioration, I do not accept the FSP’s argument that
this justifies their decision not to replace the gutters.
I am satisfied that in order to repair the gutters to a condition which is the equivalent
to a substantially the same as they were prior to the event that it is necessary for the
FSP to replace the gutters on roof 9 and 14.
Case No: 448727 Determination Page 5 of 9
FSP is not liable for replacement of roof 4, 5, 17 (north side) and 18
The reports from MC and AH do not identify any damage to roofs 4, 5, 17 (north side)
and 18.
Whilst the applicant ’ s report from B states that there is hail damage to 80% of the
roof it does not identify which areas of the roof the damage relates to.
The FSP’s liability is limited to the damage portion of the roof. It is not liable under
the terms of the policy for the cost to repair any undamaged portion of the property
subject to extra costs necessarily incurred to comply with public, statutory or
environmental protection authority requirements. There is no evidence that any such
extra necessary costs would be incurred in the circumstances. I accept that the FSP
is not liable to repair or replace roofs 4, 5, 17 (north side) and 18.
Matching
The requirement under the terms of the policy is that the FSP will replace with the
same material or where the materials are not available will use the nearest available
materials to repair or replace the damaged portions of the property. Subject to the
FSP using either the same material or if not available the nearest available material
to repair the roof then it will have met its liability under the terms of the policy.
Case No: 448727 Determination Page 6 of 9
3 Supporting information
3.1 Relevant Policy
Page 19:
Page 27:
Case No: 448727 Determination Page 7 of 9
Page 12:
3.2 Reports
Report Findings
FSP expert
MC
September 2015
The roof contains 18 parts, each referred to as a separate ‘roof’
Roof 1 on the lower level (north end, block 1, unit 1)
Hail impacts were locat ed to the barge roll and the two roof
sheets
Roof 2 on the lower level (block 1, unit 2)
No evidence of impact (phot o 8)
Roof 3 on the lower level (block 1, unit 3)
No evidence of impact (phot o 9)
Roof 4 on the lower level (block 2, unit 4)
No evidence of impact (phot o 10)
Roof 5 on lower level (block 2, unit 5)
Evidence of a pre - existing score mark or impact was located to
this roof. No evidence of impact damage related to the claimed
event (photo 11,12)
Case No: 448727 Determination Page 8 of 9
Roof 6 – upper level west side section of hip roof to the rear
(south block) above unit 5
Multiple small and larger impacts to the majority of the roof
sheets as well as the roof sheet laps to this sector (13,14,15, 16)
Roof 7 – upper level south side section of hip roof to the rear of
unit 4 and 5
Multiple small and larger impacts were located to the roof sheets
and sector of roof (22,23,24,25, 26,27)
Roof 8 – upper level east side to the rear south block above u 4
Multiple small and larger impacts on r oof sheets (34, 35,36,37)
Roof 9 – upper level north side to rear south above u 4 +5
No impacts located to roof sheets, skylight recently replaced
(42,43)
Roof 10 – upper level north facing gable roof to rear south block
above unit 5
Multiple small and lar ger impacts were located to the roof sheets
as well to the roof sheet laps (44 - 47)
Roof 11 – west side of the upper level north facing gable roof to
the rear south block above unit 4
Multiple small and larger impacts were located to the roof sheets
and l aps
Roof 12 – upper level south side section of the hip roof to the
front north block above unit 3
Multiple small and larger impacts located (55 - 59)
Folded metal hip cap (60 - 61)
Roof 13 – upper level west side section above unit 3,2,1
Multiple small and larger impacts located to roof sheets 62 - 66
Roof 14 – upper level north side section of hip roof
No impacts were loc ated to the roof sheets, folded metal hip cap
to both hips
Sewer vent cap has been impacted
Roof 15 – upper level east side section of hi p roof to the north
block above unit 3,2,1
Multiple small impacts located to roo f sheets 77 - 79
Roof 16 – upper level east facing gable rood to the front north
block above 1
Multiple small and larger impacts were located to the roof sheets
(82 - 86)
Roof 17 – upper level east facing gable roof to the front north
block above unit 2
Multiple small and larger impacts were located to the roof sheets
on the south side (87 - 89)
Roof 18 – north side upper level east facing to the front
No impacts to the roof sheets
Scope accepted by FSP:
Case No: 448727 Determination Page 9 of 9
Removal and replacement - Roof 1, 6, 7, 8, 10, 11, 12, 13, 16 (south
face), 17(south face)
Remove and replace vent cap on roof 14
Scope not accepted by FSP:
Replacement of roof 2,3,4, 5,9,14,15,16(north face), 17(north face),
18
MC 2
February 2016
Roof 2 – no evidence of impact to 4/5 panels – the impact to 1
panel is located on the nort h end of the roof
Roof 4 – no evidence of hail damage to any 5 of the panels –
there is some pre - existing damage to this roof
Roof 5 – no evide nce of hail damage to any 5 panels – a score
mark not related to the event is evident on the roof
Roof 14 – 13 panels – no evidence of damage to any hail
damage to this roof
Roof 15 – 26 panels – small impacts to 8 panels (photo 50 - 70)
minor small impacts to 9 panels (photo 71 – 100) also damage to
the remaining 9 (photos 101 - 129)
B The report outlines a number of photos of the dents to the roof,
including small, medium and large dents created by hail.
It is unclear where the damage is located
The report also outlines hail damage to the ridge caps – the
replacement of all ridge caps has been accept ed by the FSP
The report days that 80% of the roof is damaged from the event,
however doesn’t really assist to outline where the damage is
located.
Applicant’ s report
AH
The report outlines a number of photos showing damage mainly
to roof 2 and 15 – this is largely consistent with the FSP’s report
and not disputed that the damage is there
The extra photos of the damage to these portions of the roof are
helpful
The report outlines some damage to the ridge capping but these
have been accepted by the FSP
MC report 3 (9/6/16) Comments in response to aushail report
Roof 15 – aushail recommended full replacement of roof due to
extent of damage. In res ponse, M says their position is based on
Technical Bulletin 32 section 1