Text of the determination
Determination
Case No: 448324 Determination Page 1 of 12
Case number: 448324 30 March 2017
1 Overview
1.1 Dispute
The applicant lodged a claim under his home insurance policy with the financial
services provider (FSP) after the roof of his home was blown off by strong winds in
August 2014.
The FSP accepted the applicant’s claim and sought to arrange for the repair of the
property. However, after various issues arose, the FSP decided to cash settle the
applicant’s claim rather than undertake the neces sary repairs.
The FSP cash settled the applicant for $187,307.04, based on the estimated cost of
the building repairs. The FSP had previously paid the applicant approximately
$60,000 in temporary accommodation costs for himself and his pets. The FSP cash
settled the applicant for the loss of his contents by paying him the total sum insured
of $53,550 (less applicable deductions).
The applicant says the cash settlement paid by the FSP is not sufficient to enable
him to carry out the necessary repairs to the property, which he says needs to be
demolished and rebuilt.
The applicant also seeks additional payment for temporary accommodation and
damage to contents items as a result of the manner in which the FSP handled his
claim, as well as compensation for various additional losses incurred.
1.2 Issues and key findings
Is the FSP entitled to cash settle the claim for the cost of repairs?
The FSP acted reasonably in deciding to cash settle the claim, given the reported
threats of violence by the applicant against its contractors. The FSP was required to
treat any reported threats of violence seriously, even though the applicant denies
making any such threats.
Is the cash settlement amount fair and reasonable?
The cash settlement amount for the building repairs should be increased by
$28,096.06 to reflect additional costs associated with the property’s bushfire rating,
together with an allowance for further deterioration of the property between February
and August 2015 and any unforeseen variations in the scope of works.
The cash settlement amount for the contents should be increased by $28,384.50 to
reflect the additional damage caused by the failure of the FSP’s contractors to
Case No: 448324 Determination Page 2 of 12
arrange for the undamaged contents to be removed from the property. Given this
failure occ urred due to the FSP’s actions, it is unable to rely on the contents sum
insured to limit its liability to the applicant.
The applicant is not entitled to any further payment in respect of temporary
accommodation.
Is the applicant entitled to compensation?
The applicant is entitled to compensation of $1,500 for non-financial loss due to the
manner in which the FSP handled his claim.
1.3 Determination
This determination is partly in favour of the applicant.
The FSP is to pay the applicant the following amounts:
$28,096.06, plus interest calculated in accordance with section 57 of the
Insurance Contracts Act 1984 (the ‘Act’) from 25 August 2015 until the payment
date;
$28,384.50, plus interest calculated in accordance with the Act from 22
September 2014 until the payment date; and
$1,500 as compensation for non-financial loss.
Case No: 448324 Determination Page 3 of 12
2 Reasons for determination
2.1 Is the FSP entitled to cash settle the claim for the cost of repairs ?
Insurer is generally bound by election to repair
Under the terms of the policy, the FSP may settle a claim for damage to the
applicant’s property caused by an insured event by:
arranging for its contractors to repair the damage;
paying the applicant the reasonable cost of the repairs; or
paying him the building sum insured ($393,750), where the FSP considers the
building to be a total loss or otherwise chooses to do so .
It is clear from the terms of the policy that the FSP has the discretion to decide which
settlement method to adopt.
In the present case, the FSP elected to repair the damage to the building caused by
the strong winds in August 2014. Accordingly, the FSP arranged for its contractors to
attend the property and prepare a scope of works, and sought quotations from
builders to carry out the repairs set out in the scope of works.
Once an insurer makes an election to repair the insured property (rather than to cash
settle the policyholder for the cost of the repairs), it is generally obliged to complete
the repairs in accordance with the terms of the policy.
However, particular circumstances may arise which make the conduct of repairs by
an insurer untenable.
In such cases, it is reasonable for the insurer to seek to settle the claim by way of a
cash settlement, provided that the cash settlement amount is sufficient to allow the
policyholder to engage a builder directly to complete the necessary repairs.
FSP cash settled claim following reported threats of violence
The claim history reflects that the FSP and the applicant worked together over an
extended period of time to identify an appropriate repair method and agree on a
scope of works for the repair of the property so that works could commence.
This process was delayed by various factors, including the rural setting of the
applicant’s property and communication difficulties exa cerbated by the fact that the
applicant had limited telephone reception.
An initial scope of works for the repair of the property was prepared by the FSP’s
building consultant in September 2014. After the parties were unable to agree on the
scope of works, the FSP arranged a site meeting in February 2015.
Following this meeting, the scope of works was amended to include additional works
required as a result of the further deterioration of the property during the intervening
period, and to address some of the specific concerns raised by the applicant.
Case No: 448324 Determination Page 4 of 12
By June 2015, the parties had reached agreement on most issues and the FSP’s
builder (AJ) was ready to commence repairs, subject to obtaining the necessary
council approvals.
However, before the approval process was finalised, the FSP’s builder appointed a
new supervisor, who attended the property in August 2015.
Following his attendance, M reported that the applicant had threatened violence
against himself and others of the F SP’s contractors. Based on the threats reported by
M, the FSP decided to cash settle the claim.
FSP acted reasonably in cash settling claim
The applicant acknowledges that he was stressed and upset by the delay in resolving
his claim, which by August 2015 was more than twelve months old. However, he
unequivocally denies making threats of physical violence against M or anyone else.
Based on the limited information available, it is not possible for the panel to
determine with any certainty what occurred during M’s attendance at the applicant’s
property.
However, the panel accepts that the FSP was required to treat any reported threats
of violence seriously, in accordance with its legal obligations to its employees and
contractors.
Accordingly, in this ins tance, in the panel’s view, it was reasonable for the FSP to
depart from its original election to arrange for the repair of the property.
However, in doing so, the FSP left the applicant with the responsibility for arranging a
building project of some significant size and complexity, exacerbated by the rural
location of the property.
Further, the FSP’s decision to cash settle left the applicant fully exposed to the risks
associated with the repair process, without the benefit of the life time guarantee
( which would have applied had the repairs been carried out by the FSP’s builder ).
The FSP was aware that the applicant was living on a disability pension, was already
severely distressed by the claim process and had limited personal and emotional
support following the breakdown of his relationship.
In these circumstances, it was particularly important for the FSP to ensure that the
amount of the cash settlement was sufficient to enable the applicant to repair the
damage to the property caused by the storm in August 2014.
2.2 Is the cash settlement amount fair and reasonable?
Applicant says property needs to be demolished and rebuilt
As outlined above, the FSP cash settled the applicant for $187,307.04, being the
estimated cost of the building repairs.
Case No: 448324 Determination Page 5 of 12
The cash settlement amount was based on an updated quotation provided by the
FSP’s builder (AJ) in March 2015 for the repairs set out in a scope of works prepared
by the FSP’s building consultant (IT).
The applicant disputes the amount of the cash settlement for b uilding repairs. He
says the property has significantly deteriorated during the claim process, such that it
is no longer capable of being repaired.
FSP was entitled to cash settle claim for reasonable cost of repairs
Having carefully reviewed the available material, the panel is not satisfied that, as at
the date the FSP cash settled the claim, the property was not capable of being
repaired.
The initial damage to the property caused by the strong winds in August 2014
primarily comprised damage resulting from the metal roof being blown off, including
damage to the timber roof framing and the internal walls and ceilings. There was also
damage to a garage roller door, two aluminium windows and the roof-mounted solar
system.
The FSP acknowledges that the condition of the property deteriorated in the following
months, while the FSP sought to arrange the repairs. The FSP says the roof could
not be effectively tarped due to the strong winds which affected the area, and
therefore the property remained open to the e lements.
Following the site visit in February 2015 , the FSP’s builder (AJ) prepared an updated
quotation which included provision for the repair of additional damage including:
the rendering of internal masonry walls from floor to ceiling;
the replacement of the kitchen cabinetry and various fixtures at an estimated
cost of $8,035; and
extensive repairs to the bathroom (as reflected in the allowance for tiling and
waterproofing).
The FSP accepted that it was liable for repairing these additional items of damage,
which had occurred as a result of rainwater entering the property during the six
month period between August 2014 and February 2015.
The site meeting in February 2015 was attended by the applicant, as well as the
FSP’s assessor, builder (AJ), building consultant (IT) and engineer (TE).
While the experts who attended the site meeting agreed that the scope of works
required amendment, there is no information to suggest that any of them formed the
view that the property could no longer be successfully repaired.
The applicant has provided a quotation dated 29 December 2015 for the demolition
and repair of the property prepared by his builder (HV). In his quotation, HV states
that, in his opinion, whatever remains of the damaged house needs to be demolished
to floor level and rebuilt.
However, HV does not provide any further details as to the basis for his conclusion
that the property needs to be demolished and/or why the repairs contained in the
FSP’s updated scope of works and quotation would not be effective to restore the
property to its condition prior to the damage.
Case No: 448324 Determination Page 6 of 12
The panel acknowledges that the property may have deteriorated further between the
date of the site inspection (in February 2015) and the date the FSP decided to cash
settle the claim (in August 2015).
However, given the extent of the repairs already included in AJ’s updated quotation
(and the nature of the ongoing exposure), the panel is not satisfied that any
additional damage to the property during this period is such as to render it no longer
capable of being repaired.
The FSP is not liable for any further deterioration since August 2015. Once the
applicant received the cash settlement of $187,307.04, he was responsible for taking
any steps necessary to protect the property from further damage.
For the reasons outlined above, the p anel is not satisfied that the applicant’s property
needs to be demolished and rebuilt. Accordingly, the FSP is entitled to settle his
claim for the reasonable cost of repairs.
FSP’s scope of works and quotation are generally appropriate
As outlined above, the cash settlement amount was based on the updated scope of
works and quotation prepared by the FSP’s contractors.
Having reviewed the available information, the panel is satisfied that these
documents generally provide an accurate breakdown of the works required to repair
the damage to the property caused by the strong winds in August 2014 and the
ongoing exposure to the elements over the following twelve month period.
Among other matters, the panel is satisfied that AJ’s updated quotation:
appropriately addresses the bulk of the queries about the scope of works raised
by the applicant during the claim process; and
includes all of the additional damage for which the FSP accepted liability
following the site visit in February 2015 (despite the amended scope of works
prepared by IT being dated two months later).
The applicant has identified a number of additional costs which he considers should
be included in the cash settlement amount.
Some of these costs reflect works which are not required (or would be less
expensive) in the event that the property can be repaired and does not need to be
rebuilt. Examples include costs for the demolition of the property and the removal of
debris.
Other costs identified by the applicant reflect items which are already included in AJ’s
quotation, albeit for a lower amount (such as the cost of replacing the solar energy
system). The fact that the ap plicant’s contractors have quoted higher amounts for
these items does not of itself establish that AJ’s quotation is inadequate.
Cash settlement amount for repairs should be increased by $28,096.06
The quotations provided by the applicant are generally based on the assumption that
the property needs to be demolished and rebuilt.
Case No: 448324 Determination Page 7 of 12
Accordingly, these quotations are of little assistance in determining whether the cash
settlement of $187,307.04 paid by the FSP for the building repairs is fair and
reasonable.
However, having carefully reviewed the information provided, the panel is not
satisfied that the cash settlement amount reflects the reasonable cost of repairing the
damage to the property at the time the claim was cash settled in August 2015.
Among other matters, the panel considers the cash settlement amount should be
increased to reflect the reasonable cost of upgrading the property to reflect the
bushfire rating.
The FSP’s builder was in the process of obtaining a bushfire assessment report
confirming the additional works required as part of the repairs, when the FSP decided
to cash settle the claim. Accordingly, the final report was never completed.
Nevertheless, it is apparent from the comments made by the FSP’s contractors
throughout the claim process that the property would most likely be classified as
having a bushfire rating of BAL 40 or BAL FZ (as the applicant contends).
The FSP says that AJ’s quotation includes an allowance of $1,200 for additional
bushfire compliance costs. However, it appears that this amount refers to the costs of
obtaining the initial assessment only, rather than any additional costs required as a
result of the recommendations arising from the report.
The applicant has estimated the additional bushfire compliance costs at $40,000.
However, given the nature of the repairs required, the panel is not satisfied that the
costs would necessarily be this high.
In addition to the bushfire compliance costs, the panel considers the cash settlement
amount should be increased to reflect the following:
any increase in costs during the five month period between the date AJ’s
updated quotation was provided and the date the cash settlement was paid
(given the quotation was expressed to be valid for 30 days only);
the effect of any discounts or rebates which may have been available to the
FSP through the use of a panel builder (but were not necessarily available to
the applicant);
a sufficient buffer to provide for any additional damage which may become
apparent during the course of the repairs (given the FSP would have been liable
for any resulting increase in costs, had it carried out the repairs as initially
proposed); and
the cost of repairing any further deterioration of the property between the site
visit in February 2015 and payment of the cash settlement, as a result of
continued exposure to the elements.
On this basis, the panel considers it is fair in all the circumstances that the cash
settlement be increased by an additional amount of $28,096.06 to allow for the
issues identified above. This amount represents a 15% increase in the amount of
$ 187,307.04 quoted by the FSP’s builder (AJ) .
The FSP is required to pay interest on this amount at the rate set out in section 57 of
the Act 1984 from 25 August 2015 until the payment date.
Case No: 448324 Determination Page 8 of 12
Applicant is not entitled to any further payment for temporary accommodation
The policy provides for the payment of reasonable costs for temporary
accommodation for the applicant, his family and his pets, where the home becomes
uninhabitable due to an insured event.
The applicant is also entitled to any additional living expenses the FSP agrees are
appropriate, as well as the costs of removing and storing contents and retuning them
to his home.
However, the policy limits the payment of benefits to the period of twelve months
following the insured event. The policy also states that the FSP will not cover costs
caused by unreasonable delays in repairing the property.
The claim notes reflect that the FSP paid the applicant an initial amount of $29,500
(in place of six months temporary accommodation) in September 2015, after he
indicated that he wished to purchase a caravan or mobile home so he could remain
at the property.
The applicant says the FSP forced him to purchase a mobile home, which was not an
adequate solution as it left him without access to bathroom facilities, heating and
electricity.
However, the claim notes reflect that this option was first raised with the FSP by the
applicant’s ex -partner (who had authority to act on his behalf), after the applicant had
trouble finding a long-term rental property which could accommodate his four dogs.
The applicant (or his ex-partner) provided the FSP with an advertisement for the
specific item they intended to purchase.
The FSP subsequently paid the applicant a further amount of $29,962 in March 2015,
after the initial six month period expired. The FSP also paid further amounts totalling
$5,700 for kennelling for the applicant’s dogs and incidental living costs such as
petrol and generator fuel.
The panel is satisfied that the amount paid by the FSP for temporary accommodation
and associated expenses are reasonable in the circumstances.
The FSP has paid the applicant 12 months’ worth of temporary accommodation
benefits. These benefits were paid (at the applicant ’s request) in a manner which
allowed the applicant to remain at the property and retain the benefit of a capital
asset purchased with the FSP’s funds.
The applicant seeks payment of an additional $25,000 in temporary accommodation
costs, on the basis that the FSP has unreasonably delayed the settlement of his
claim.
While it has taken an extended period of time to resolve the applicant’s claim, I am
not satisfied that the FSP was solely responsible for these delays. To some extent,
these delays have been due to the unusual characteristics of the claim, including the
unusual features of the applicant’s house, the difficulties in accessing the property
and the communication challenges posed by the limited telephone reception.
Case No: 448324 Determination Page 9 of 12
Further, it is not clear to what extent the applicant has actually incurred temporary
accommodation costs during the claim period, based on his statements that he has
been living in a shed at the property.
For the reasons outlined above, the panel does not consider that the applicant is
entitled to any further benefits for temporary accommodation.
Contents settlement should be increased by $28,384.50
The applicant says the FSP’s contractors failed to act promptly to salvage his
contents from the property after the roof was blown off in August 2014. The
applicant’s contents suffered water damage during subsequent storms, which left
them largely unsalvageable.
The FSP’s claim records include a note by t he assessor (JG) which indicates that the
damage to the applicant’s contents items occurred due to the failure of the FSP’s
restoration contractors to remove the applicant’s undamaged contents from the
property in the week after the damage occurred.
While the restoration contractors attended the property the day after the claim was
lodged, they did not take any action to remove the contents items, despite the
assessor warning of the potential for future damage (and expressing concern that the
applicant was under-insured).
As outlined above, the FSP cash settled the applicant for the total contents sum
insured of $53,550 (less applicable deductions). However, the FSP’s claim notes
indicate that the restoration contractor valued the applicant’s damaged content items
at $77,934.50 (excluding carpets, which were also covered under the contents
policy).
The contents sum insured limits the FSP’s liability fo r damage to the applicant’s items
arising from an insured event. However, the FSP’s liability is not limited where the
damage arises from the conduct of the FSP or its contractors (rather than the insured
event itself).
In the present case, the panel considers that the FSP should have taken immediate
action to arrange for the removal of the applicant’s contents so as to prevent further
damage.
The panel acknowledges that the nature and location of the property may have made
it more difficult to arrange fo r the removal and safe storage of the applicant’s
contents.
However, in circumstances where the FSP was willing to extend cover to the
property, it was also obliged to ensure that an appropriate level of service was
provided once an insured event occurred .
Further, the panel is not satisfied that the factors identified are sufficient to justify the
failure by the FSP and its contractors to take action (for example, by implementing
interim measures to protect the applicant’s contents ).
Case No: 448324 Determination Page 10 of 12
In reaching this view, the panel notes the opinions expressed by the FSP’s assessor
(JG), who acknowledged that the restoration contractors missed a window of five
clear days to remove the applicant’s contents items.
JG considered that, had the restoration contractors done so, approximately 97% of
the applicant’s contents items would have been salvageable. On this basis, JG
recommended that the FSP cash settle the applicant for an amount in excess of the
contents sum insured. It is not clear why JG’s recommendation was not adopted.
For the reasons outlined above, the panel considers that the FSP should be required
to indemnify the applicant for the amount by which the value of his loss contents
exceed the sum insured ($24,384.50), plus an additional amount of $4,000 to allow
for the damaged carpets.
The FSP is required to pay interest on the total of $28,384.50 at the rate in section 57
of the Act from 22 September 2014 until the payment date.
The panel is satisfied that the generator which the applicant says was removed from
the site by the FSP’s contractors should be treated as part of the solar electric
system. On this basis, the applicant has been adequately compensated for this item
by the full replacement of the solar electric system under the approved scope of
works.
2.3 Is the applicant entitled to compensation?
FOS may award compensation for non-financial loss
Under the Terms of Reference, FOS may award compensation (capped at $3,000)
for non-financial loss where an applicant has suffered an unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
The fact that the applicant’s policy excludes cover for consequential losses does not
preclude the award of compensation where such losses have occurred as a result of
the way in which the FSP has handled their claim, rather than as a result of the
insured event itself.
However, FOS adopts a conservative approach to the award of compensation for
non-financial loss. FOS expects applicants to be moderately robust and bear the
usual stress and inconvenience associated with an insurance claim.
Applicant is entitled to compensation
The applicant is dissatisfied with the manner in which the FSP has managed his
claim. Among other things, the applicant says:
the FSP has unreasonably delayed the settlement of his claim;
the FSP’s consultants did not communicate with him promptly and he was
required to deal with a number of different people during the claim process; and
the FSP’s failure to protect his contents items (and prevent the further
deterioration of the property) has exacerbated the stress he experienced during
the claim process.
Case No: 448324 Determination Page 11 of 12
The panel accepts that there were several factors outside the FSP’s control which
complicated the resolution of the claim, including the features of the property, its rural
location and the absence of electricity and mobile phone reception. The nature of the
damage also meant that advice from several different contractors was required.
Never theless, the panel considers that the FSP failed to progress the applicant’s
claim with sufficient urgency, having regard to the circumstances in which he found
himself.
There were periods during the claim process where significant delays occurred,
notably the provision of an updated scope of works and quotation following the site
meeting.
Had these matters been progressed more expeditiously, it is quite likely the repairs
could have been completed by the FSP ’s contractors, minimising the stress and
inconvenience for the applicant.
Further, the panel is satisfied that the applicant has suffered significant additional
stress as a result of the FSP’s failure to arrange for its contractors to remove his
undamaged contents from the property after the initial i nsured event. This resulted in
the total loss of the applicant’s contents, in circumstances where they had suffered
minimal initial damage.
Having regard to the factors outlined above, the panel considers an award of
compensation for non-financial loss i n the amount of $1,500 is fair in all the
circumstances.
Case No: 448324 Determination Page 12 of 12
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS recommendation. Due to the nature
of the dispute, it has been referred directly to a panel for determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The panel has decided this dispute based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous Financial Ombudsman Service (FOS) decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, the panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.