Home / Financial Firm (Unknown - Credit) / Determination 447146

Determination 447146

incorrect_fees_or_charges

FirmFinancial Firm (Unknown - Credit)
Decided2017-02-27
ProductCredit · Car loan
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed—
SourceAFCA PDF

Summary

The applicant's vehicle finance debt, after repossession and sale, was assigned to the FSP, which charged compounding interest at 9.10%. AFCA partly upheld the complaint, reducing the principal by $500 for non-financial loss and limiting interest to simple 8%.

The contract permits only simple interest at 8% per annum on overdue amounts, and the credit provider failed to give notices required under the UCCC, leading to a non-financial loss award.

Issues

Subjects and remedies

debt waiver or reductionpay non financial loss

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 447146 Determination Page 1 of 3 Case number: 447146 2 4 January 2017 1 Overview 1.1 Dispute The applicant obtained a credit facility from a vehicle finance company (the credit provider). The facility fell into arrears and the vehicle was repossessed and sold by the credit provider. The residual debt was later sold to the Financial Services Provider (FSP). The applicant says:  the credit provider did not notify him of the outstanding debt, and  the FSP is now “harassing” him and charging interest on the outstanding amount. The Case Manager provided the parties with a recommendation on the issues in dispute. The recommendation was partially in favour of the applicant and awarded the applicant $500 in consideration of his non-financial loss and a reduction of the interest charged by the FSP. A copy of the recommendation is attached to this determination. The applicant rejected the recommendation as he felt the recommended award for non-financial loss was insufficient in the circumstances. 1.2 Issues and key findings Were the findings of the recommendation correct? The findings contained in the recommendation were correct and are adopted in this determination . Further submissions provided after the recommendation have been considered. Does the applicant’s rejection change the outcome? The applicant’s rejection of the recommendation does not change the outcome. The Case Manager’s recommended outcome is fair in al l the circumstances. 1.3 Determination This determination is partially in favour of the applicant. I agree with the case manager’s reasons for the recommendation and the recommended outcome. Case No: 447146 Determination Page 2 of 3 Within 14 days of the acceptance of this determination by the applicant, the FSP should reduce the principal debt to $15,813.57. The FSP is also entitled to collect $1,516.04 in simple interest as at 28 November 2016. This makes the total amount payable as at 28 November 2016 $17,329.61. Simple interest of 8% pa accrues on the amount of $15,813.57 from 28 November 2016 until the debt is repaid, unless the FSP agrees to not charge interest. Within the same 14 days, the applicant should provide the FSP with details of his current financial position along with a repayment proposal which would see the outstanding balance repaid within a reasonable amount of time. The FSP should consider the proposed repayment arrangement taking into account the applicant’s financial position but is not requ ired to accept it if it does not consider it reasonable. If the applicant does not keep to the arrangement, or no arrangement is reached, the FSP will be entitled to recommence action to recover the outstanding amount in accordance with the terms and conditions of the facility including the application of overdue interest. Case No: 447146 Determination Page 3 of 3 2 Reasons for determination 2.1 Were the findings in the recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the Case M anager’s recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. 2.2 Does the applicant’s rejection change the outcome? The applicant did not try to contact the finance company While the applicant says he attempted to organise a payment arrangement directly with the finance company, no information has been provided to support this claim. In addition, the applicant says he was not aware of the outstanding debt. It would not be reasonable to accept the applicant’s claims that he attempted to repay the outstanding amount at the same time as claiming he was unaware of it. The award for non-financial loss is fair in the circumstances FOS takes a conservative approach to non-financial loss. The recommendation awarded the applicant $500 in consideration of his non-financial loss due to the finance company’s failure to accurately respond to his request for information. The applicant says the amount recommended is insufficient because he would have been paying incorrect interest to the FSP had he not contacted FOS. FOS does not award compensation because an applicant was required to lodge a dispute with FOS. I am satisfied that the award for non-financial loss is fair in the circumstances because:  any potential loss due to the incorrect interest rate being charged will be rectified by the outcome of this determination, and  the applicant has not yet made any payments to the FSP so was at no stage out of pocket or inconvenienced due to this error. No further information has been provided which would warrant an increase in compensation. Recommendation Case No: 447146 Recommendation Page 1 of 6 Case number: 447146 29 November 2016 3 Overview 3.1 Dispute The applicant applied and was approved for a facility with a vehicle finance company (the credit provider). The facility was provided to purchase a vehicle by instalments. The facility fell into arrears and as a result, the applicant returned the vehicle to the credit provider to be sold. After the sale, there was a residual debt of $16,313.57. The outstanding debt has been sold to the FSP who is pursuing the applicant for payment. The applicant says:  the credit provider did not notify him of any outstanding debt after the sale of the vehicle, and  the FSP is now “harassing” him and charging interest on the outstanding amount. The applicant says, had he known there was an outstanding amount, he would have come to an arrangement with the credit provider to pay it. 3.2 Issues and key findings Did the credit provider fail to contact the applicant? In the absence of information to show otherwise, the facility was regulated by the Uniform Consumer Credit Code (UCCC). Therefore, the credit provider had obligations to send notices to the applicant after the vehicle was repossessed which it failed to do. While the credit provider did not sa tisfy its obligations, the information shows it did try to contact him by other means to discuss the outstanding amount. Should the FSP compensate the applicant for any loss? The applicant has not incurred a financial loss as a result of the credit provid er’s failure to provide the required notices under the UCCC. However, he is entitled to $500 compensation for the non-financial loss experienced. This amount should be applied to reduce the principal debt. In addition, the FSP has been charging an incorrect rate of interest since the debt was sold. The FSP should therefore adjust the outstanding amount to reflect the correct rate of interest. Case No: 447146 Recommendation Page 2 of 6 3.3 Recommendation This recommendation is partially in favour of the applicant. Within 14 days of the acceptance of this recommendation by both parties, the FSP should reduce the outstanding principal amount to $15,813.57 ($16,313.57 minus $500 for non-financial loss). The FSP is also entitled to collect $1,516.04 in simple interest accrued on the principal amount since it was assigned to the FSP. This makes the total amount payable as at 28 November 2016 $17,329.61. Within the same 14 days, the applicant should provide the FSP with details of his current financial position along with a repayment proposal which would see the outstanding balance repaid within a reasonable amount of time. The FSP should consider the proposed repayment arrangement taking into account the applicant’s financial position but is not required to accept it if it does not consider it reasonable. The FSP should not charge interest while the proposal is being considered. If an arrangement is reached and the applicant maintains that arrangement, as this is effectively a variation of the contract, overdue interest s hould not be applied. If the applicant does not keep to the arrangement, or no arrangement is reached, the FSP will be entitled to recommence action to recover the outstanding amount in accordance with the terms and conditions of the facility including the application of overdue interest. Case No: 447146 Recommendation Page 3 of 6 4 Reasons for recommendation 4.1 Did the credit provider fail to contact the applicant? The contract was regulated by the UCCC At the time the facility was entered into, consumer credit was regulated by the UCCC. Under section 10(1) of the UCCC, a contract for the hire of goods where the hirer has a right to purchase the goods, is considered a contract for the sale of goods by instalments. This type of contract is regulated by the provisions of the UCCC. Given, there is no evidence to show the credit was provided to the applicant for anything other than domestic purposes, on face value, the contract is considered to be regulated by the provisions of the UCCC. The credit provider had obligations under the UCCC Section 78(3) of the UCCC provides, if the debtor returns the goods to the credit provider, the credit provider must provide a notice to the debtor containing the estimated value of the goods. In addition, section 78(9) of the UCCC requires a credit provider to provide notice of the gross amount realised after the sale of the goods and the amount required to pay out the credit contract. The credit provider did not satisfy its obligations In support of the events which occurred after the vehicle was surrendered, the following information has been provided:  the contact notes from the FSP’s system  a copy of a demand letter allegedly sent to the applicant, and  the applicant’s recollections of events. The information available provides no indication of any notice provided to the applicant in accordance with section 78(3) of the UCCC. According to the contact notes provided, on 21 November 2013, the credit provider issued a demand notice to the applicant which set out the amounts owing after the sale of the vehicle. The FSP has provided a copy of the demand notice allegedly sent which shows an outstanding amount of $30,525.05. However, the FSP has also provided a transaction history which shows the outstanding amount at that time to be $16,313.57 which is the amount which was assigned to the FSP. The applicant says he did not receive this demand letter. However, given the amount listed in the demand letter was incorrect, even if it had been received, the letter did not satisfy the credit provider’s obligations under the UCCC. Therefore, the credit provider did not satisfy its obligations under 78(3) nor 78(9) of the UCCC. The credit provider did attempt to contact the applicant When forming a view, FOS will consider the information provided and decide what is most likely to have occurred based on that information. In doing so, as we cannot take evidence on oath, we place more weight on documentary information. Case No: 447146 Recommendation Page 4 of 6 While the applicant says the credit provider made no attempt to contact him after the vehicle was sold, the documentation available indicates otherwise. The FSP has provided records to show the credit provider:  sent a demand notice (although it contained incorrect information), and  attempted to contact the applicant via telephone and SMS. Therefore, the information shows it is more likely than not the credit provider did attempt to contact the applicant. However, the applicant did not respond to these attempts. 4.2 What is an appropriate outcome to the dispute? The credit provider’s actions have not caused the applicant financial loss As explained in section 2.1 of this recommendation, the information available suggests the credit provider failed to send notices to the applicant in accordance with the UCCC. However, the credit provider did attempt to contact the applicant to discuss the outstanding amount. The applicant did not respond to the credit provider’s attempts to contact him and the account history shows broken arrangements documented in the contact notes On this basis, it would not be reasonable to conclude the applicant would have entered into an arrangement with the credit provider had the correct notices been sent. Therefore, even if the correct notices were issued, the applicant would be in no better financial position. The applicant is entitled to $500 compensation for non-financial loss While the applicant has not incurred a financial loss as a result of the credit provider’s actions, he is entitled to compensation for the non-financial loss he would have experienced having not been aware of the correct outstanding amount. The FSP should reduce the outstanding principal amount by $500 in consideration of this. The FSP has been charging an incorrect interest rate After the debt was sold to the FSP, it began charging interest on the outstanding amount. The FSP says it has applied an interest rate of 9.10% as advised by the credit provider. While this is the contract rate (or internal rate of return based on the rental amounts), this interest was already applied to the outstanding amount at the inception of the contract (referred to as Term Charges on the contract). Relevantly, clause 9(1)(a) of the contract says: “The Hirer shall…pay interest at the rate of eight percentum (8%) per annum simple calculated on a daily basis on any moneys payable hereunder which may from time to time be overdue and unpaid such interest to be comput ed from the date upon whic h such moneys become payable to the date of actual payment. ” Therefore, the FSP has been incorrectly charging compounding interest at 9.10% when it was only entitled to charge simple interest at 8% on overdue amounts. When the facility was assigned to the FSP, the full balance was payable and overdue. Case No: 447146 Recommendation Page 5 of 6 Therefore, under the contract, it was entitled to charge simple interest on the outstanding amount at 8% per annum. The FSP should reduce the outstanding amount The facility was assigned to the FSP on 1 October 2015. Therefore, as at 28 November 2016, the correct interest accrued on the overdue amount is $1,516.04 (8%p.a. × 424 days × $16,313.57). Therefore, the total amount payable as at 28 November 2016 should be $17,329.61. This consists of:  a principal debt of $15,813.57 (after the reduction of the principal amount by $500 in consideration of th e applicant’s non -financial loss), plus  accrued simple interest of $1,516.04. If an arrangement is reached to repay the outstanding amount, as per the terms of the contract, the FSP will not be entitled to charge overdue interest unless any of the agreed payments become overdue. If this occurs, the FSP will be entitled to charge simple interest on the overdue payment amount at 8% per annum. Case No: 447146 Recommendation Page 6 of 6 5 Supporting information 5.1 Key references Key documents referenced Contact notes and transaction list provided by the FSP Demand letter dated 21 November 2013 Purchase agreement dated 1 April 2010 Purchase agreement standard terms and conditions.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.