Text of the determination
Determination
Case No: 446027 Determination Page 1 of 10
Case number: 446027 25 October 2017
1 Overview
1.1 Dispute
The applicants lodged a claim under their household building policy held with the
financial services provider (FSP) after a fire at their investment property in December
2015.
The FSP accepted the claim and agreed to demolish and rebuild the damaged
section of the property. During the course of repairs, deficiencies were identified with
the concrete slab which were unrelated to the fire event. The FSP ceased work and
offered to cash settle the applicants for the balance of the claim.
The applicants are dissatisfied with the FSP‟s settlement offer. The applicants also
seek reimbursement for loss of rent from the period the repair works ceased until the
home is reinstated, consequential losses and compensation for stress and
inconvenience suffered due to the FSP‟s handling of the claim.
1.2 Issues and key findings
Is the FSP’s offer sufficient to finalise its obligations under the term s and
conditions of the policy?
The FSP‟s offer is not sufficient to meet its obligations under the terms and
conditions of the policy. The FSP must increase the cash settlement offer of
$212,162.07 by $184,852.15 to $397,014.22 and pay interest on the total settlement
amount pursuant to section 57 of the Insurance Contracts Act 1984 (the Act).
Are the applicants entitled to loss of rent?
The FSP has paid the applicants loss of rent until 3 October 2016. It is fair in the
circumstances given the issues involved in this dispute that the FSP continue to pay
loss of rent from 3 October 2016 until such time as the repairs are complete or 30
June 2018, whichever comes first.
Are the applicants entitled to compensation for non-financial loss?
The applicants are entitled to compensation for undue stress and inconvenience
caused by the FSP‟s approach to settlement of the claim of $3,000.
Case No: 446027 Determination Page 2 of 10
1.3 Determination
This determination is in favour of the applicants.
The FSP is required to:
increase its cash settlement offer to the applicants for the balance of the
outstanding repairs at the property by $184,852.15 to $397,014.22
pay interest on the total reinstatement cost of $397,014.22 from 13 March 2017
until the date of payment
cash settle the applicants for the cost of works associated with removal of
staining from the driveway and replacement of the lead light in the front door
upon production of reasonable quotations for the cost of these items
indemnify the applicants for loss of rent from 1 October 2016 until the repairs are
completed or 30 June 2018, whichever comes first
pay compensation of $3,000.
Case No: 446027 Determination Page 3 of 10
2 Reasons for Determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the material exchanged.
Due to the complexities involved in this dispute, it has been referred to a Panel for
determination.
This determination follows consideration of all of the information exchanged and is
based on what is fair in the circumstances, ha ving regard to the relevant legal
principles, terms of the policy, good industry practice and where applicable, prior
determinations.
Whilst the Panel has considered all of the material exchanged, only that material
relevant to the final outcome will be referred to within the determination.
2.1 Is the FSP’s offer sufficient to meet its obligations under the terms
and conditions of the policy?
Coverage of the policy
There is no dispute that the policy covers the damage to the property caused during
the fire in December of 2015.
The FSP accepted the applicants‟ claim and agreed to repair the kitchen and living
area and to demolish and replace a garage and bedroom area damaged by fire.
Builder “L” was appointed to carry out the works which commenced on or after 24
February 2016.
After the demolition works were completed it was identified by L that the slab (which
was not damaged by fire) may have been improperly constructed when the home
was first built in 1997. Due to the issues with the slab, L was unprepared to continue
with the rebuilding works, which ceased on or around 21 March 2016.
The applicants dispute there are deficiencies with the slab and sought the FSP to
compel L to complete the repairs and restore the property to its pre -fire condition.
The FSP proposed resolution of the balance of the claim via cash settlement to the
applicants of the balance of the repair costs.
Proposed settlement of the claim
The FSP offered the applicants a cash settlement to meet its obligations for the
balance of the loss and damage at the home, under the terms and conditions of the
policy. The applicants rejected the cash settlement offer as they did not accept it was
sufficient to complete the necessary repairs
The cash settlement amount offered was $212,162.07. The offer consisted of a
number of matters which include:
L repair/rebuild quote (excluding demolition) $190,365.42
Repair variation 1 $ 2,632.30
Repair variation 2 $ 46,686.23
Case No: 446027 Determination Page 4 of 10
Restoration quote “W” $ 25,686.23
Less L costs incurred $ 43,900.90
Less W costs incurred $ 16,379.00
TOTAL $212,162.07
The applicants asked for specific information from the FSP regarding the costs
incurred and itemised works completed to date however the FSP has declined to
provide this information.
The FSP says as works had been carried out under a fixed price contract with L for
demolition, rebuild and restoration specific/itemised, such detailed information was
not available.
In the Panel‟s view, the FSP should have provided the applicant with a more detailed
itemised list of works conducted and offered the applicant, at that time, the
opportunity to obtain further quotes for the cost to rebuild the building (without
replacing the slab).
The applicants provided certification from engineers
The FSP initially raised concern that the property had been built without Council
approval or engineering certification. The applicants have supplied that certification to
the FSP.
Despite this, the FSP maintains that the concrete slab and infill did not meet the
required Australian building code at the time of construction. The FSP relied on
advice from its L and engineer JTC to refuse to complete the construction of the
building and to cash settle the dispute.
Applicants ’ engineering report indicates property can be rebuilt on existing
slab
The applicants have supplied their own engineering report from SC.
SC was first approached on 28 July 2016 and recommended that work proceed with
the rebuilding of the fire damaged section of the residence without further delay.
SC considered the recommendations that the slab needed to be replaced were
extreme. Whilst there were some issues, SC confirmed there was no observable
damage from the fire or past deficiency in the structural performance of the slab or
sub-structure.
Whilst the FSP disagrees with this view, there is no dispute that the applicant was
prepared to proceed with the reconstruction of the building on the existing concrete
slab.
FSP must exercise discretion to cash settle a claim fairly
The Panel accepts that the FSP has a discretion to cash settle a claim under the
terms of the policy. That discretion however must be used fairly and consistent with
the principles of good faith.
Case No: 446027 Determination Page 5 of 10
In determining whether to exercise the discretion the FSP must take into account all
reasonable factors including the promise to place the applicants back in the position
they would have been if not for the fire. Factors including the nature of the repairs
required and whether a cash settlement would adequately ensure the applicants are
able to properly complete all repairs must be considered. In addition to the known
expenses, any cash settlement should take a reasonable account for unknown
required repairs and variations.
By cash settlement of the claim, all of the risks associated with the repair and/or
rebuild at the property, transfer from the FSP to the applicants. Given the extent of
unknown repairs which may be required to complete all of the repairs in this claim
such as potential damage to the kitchen, which is not currently discernible in its
dismantled state, the risk is likely to be significant. Further, by cash-settling the
applicants the FSP is relieved of its obligation to guarantee the work carried out.
FSP’s offer based on lowest quotation
The initial quotes obtained by the FSP range from $216,219.02 to $349,675.00 to
complete the repairs.
The applicants confirmed that they agreed to the lowest quote from L and signed
relevant contracts in the knowledge that the FSP would continue to supervise this
work and provided a lifetime guarantee.
The Panel accepts that this was reasonable in the circumstances. The Panel also
accepts that it is fair in the circumstances that once the FSP chose to cash settle the
balance of the claim, further quotes could be obtained for the completion of the work.
Applicants’ contractor quotations
The applicants initially sought settlement on the basis of a quotations obtained from
their preferred repairer “A” dated 7 June 2016, as follows:
cost to rebuild demolished bedroom & garage wing $217,679.00
repair fire and smoke damage to main living area $ 95,621.00
Total inc. GST $313,300.00
The FSP was invited by FOS to obtain a quotation from L (or an alternative
contractor of its choice) for the same scope of works proposed by A so a meaningf ul
comparison could be made between the parties‟ respective positions . It declined to
do so.
Due to the passage of time, and A‟s quote no longer being valid , the applicants
obtained a number of further quotations for the balance of the works:
A second quotation dated 13 March 2017 $397,014.22
Builder “D” $413,050.00
Builder “J” $501,896.00
Case No: 446027 Determination Page 6 of 10
A number of items have been included in above quotations which had not been
included at the time of the original tender process and contract with L. These include:
curtains/blinds
carpets/tiles
light fixtures
bathroom fixtures and fittings
security screens
The applicants have provided quotations from their preferred suppliers for these
fixtures which values have been incorporated into each of the quotations above.
FSP failed to obtain revised quotations
The FSP did not arrange for further quotes but had an assessor review and report on
the applicants‟ further quotations . The assessor noted:
“Thes e quot es appear to be excessive and unsure what scope of work is being carried out.
These three builders have quoted the job with the conc rete slab in its current state in full view. I
am unsure if these builders have allowed for the required slab repairs in their quotes or not to
be able to warrant any works.
…
Normally insurance builders will allow for approximately $1500/M2 for complete rebuilds
excluding demolition. Project builders in the private sector are currently working at
approximately $750m2 for new dwellings.”
In the Panel‟s view it is not sufficient for the FSP‟s assessor to state without
qualification that the applicant‟s quotes are „excessive‟. The further quotation
provided by A is comprehensive and provides an outline of the proposed scope. The
quotation from J also includes a detailed outline of the proposed works.
If further information was required by the assessor there is no reason contact could
not have been made with the applicants‟ three contractors to clarify matters, including
whether the slab repairs were included in the repair figures or the square meterage
rate relied upon in calculating the repair estimate.
The Panel notes that the FSP‟s assessor concedes there can be a variation in repair
quotes. The FSP‟s original quotations varied by over $130 ,000.
The applicants have confirmed that each of the builders were prepared to build on
the existing slab, as is. There is no suggestion in the estimates that they include an
allowance for the replacement of the slab.
In the Panel‟s view it would have be en good practice and consistent with the
principles of good faith for the FSP to have obtained further quotations from its
builders to determine a fair figure for the cash settlement of the balance of the
reinstatement of the property. If this had occurred this claim may have been resolved
by July 2016.
FSP’s offer fails to take into account all relevant risks
The FSP has not provided sufficient particulars for the calculation of its cash
settlement offer of $212,162.07. It has also refused to assist the applicants by
providing particulars of works carried out to date to enable the applicants to give
meaningful consideration to its offer.
Case No: 446027 Determination Page 7 of 10
As stated above, any offer from the FSP must account for the transfer of risk in
respect to the repairs, from the FSP to the applicants. The applicants‟ consistent
concern has been whether the settlement amount is sufficient to rebuild/restore the
home to quality of the existing finish, as provided for by the policy.
The applicants are satisfied the above quotations have been provided on this basis.
Neither the FSP nor its assessor have commented on the quality of finishes allowed
for in the quotations provided by its panel builders at tender stage, nor subsequently
provided any reassurance in this regard.
In the absence of evidence to the contrary the Panel accepts the quotations provided
by the applicants represent a fair estimate of the cost to complete the works at the
applicants‟ property to the standard of the existing finishes.
The Panel considers that the reasona ble cost to reinstate the applicants‟ property
can be fairly assessed under the second quotation of A as at 13 March 2017 at
$397,014.22 including GST.
As outlined above, the FSP has previously offered to cash settle the claim in the sum
of $212,162.07. Accordingly, the Panel determines the FSP is to pay an additional
$184,832.15, bringing the total payment to $397,014.22.
The FSP is required to pay interest on the cash settlement amount pursuant to
section 57 of the Act from 13 March 2017 being the date that the applicants provided
their updated quotations until payment of the claim. The addition of interest is to
account for any variations in the costs of the quoted works since that time.
2.2 Are the applicants entitled to loss of rent?
The policy allows for the payment of loss of rent where tenants are required to move
out of the property because of an insured event.
At the time of the fire the applicants‟ property was tenanted for $840 per week.
The policy provides that it will pay the net rental income while your home is being
rebuilt or repaired for up to 12 months from when the insured event happens until the
home is fit to live in so long as the FSP agrees to pay for the insured event.
The FSP has paid the applicants for the loss of rent until 3 October 2016. This was
the anticipated completion date of works to be carried out by its builder.
In the Panel‟s view, the FSP has failed to provide sufficient information to justify its
decision to not review its original settlement offer. It has failed to provide sufficient
information to justify the rejection the applicants‟ original repair quotation or
subsequent repair quotations. In t he Panel‟s view, the inadequacy of the FSP‟s
original settlement offer and its failure to engage further with the applicant is not only
poor industry practice but shows a lack of good faith. It has meant the 12 month
limitation for loss of rent payments has well and truly elapsed.
Under the policy provisions loss of rent would be payable until December 2016. The
Panel notes that the maximum loss of rent payable is up to 10% of the home sum
insured which in this case would be $85,400.
Case No: 446027 Determination Page 8 of 10
In the Panel‟s view, it is fair in the circumstances that the limitation on rental cover be
waived and that the FSP pay the applicant‟s loss of ren t at the rate of $840 per week
from 3 October 2016 until such time as the applicant has completed the repairs or the
30 June 2018 whichever comes first.
Legal costs
The applicants have also sought to recover legal costs which they say were incurred
in the course of the claim. The applicants‟ solicitors have not been involved directly in
the dispute being determined by FOS. In the circumstances the applicants have not
established an entitlement to recover legal costs.
2.3 Are the applicants entitled to compensation for non-financial loss?
FOS may award compensation for non-financial loss
Under paragraph 9.3(a) of the TOR, FOS may award an amount of compensation
(capped at $3,000) for non-financial loss where an applicant has suffered an unusual
degree or extent of physical inconvenience, time taken to resolve the situation or
interference with their expectation of enjoyment or peace of mind.
Applicants are entitled to compensation
For the reasons outlined above, the Panel considers it has been necessary for the
applicants to go to additional lengths to demonstrate their loss including obtaining
expert reports, multiple quotations and evidence from the local council to substantiate
their position.
As a consequence of delays in resolution of the claim, notwithstanding the applicants
providing comprehensive evidence in support of their claim, the applicants have been
unable to continue with the rebuilding of their home.
The Panel is satisfied that the manner in which the FSP has handled the claim and
resultant delay due to the matter being referred to FOS has caused the applicants
undue stress and inconvenience. In these circumstances, the Panel considers that
an award of compensation in the amount of $3,000 is appropriate.
2.4 Additional Matters
The applicants have raised a number of additional matters which the FSP has not
responded to in its submissions including:
replaced timber ceiling in kitchen not matching existing ceiling & replacement roof
area leaking
oil on driveway spilled by FSP‟s contractor during demo lition works
damage to lead light in front door.
Living room roof replacement
The applicants have raised concerns regarding the work carried out by the FSP‟s
repairer L, in particular that the panels do not match the existing roof panels and that
Case No: 446027 Determination Page 9 of 10
the works have been carried out prior to the roof being replaced and as a
consequence water damage is present on several sheets.
The FSP‟s policy excludes extra expenses to replace or match undamaged parts to
create a uniform appearance. It does not appear from the certificate of insurance that
the applicants have selected the extra benefit „matching repairs‟. In the absence of
further information as to the water damage the Panel is not satisfied that there is any
further liability with respect to this aspect of the claim.
Oil on driveway
The FSP has also not responded to the applicants‟ concerns regarding oil staining to
the driveway which they say was related to vehicles belonging to the FSP‟s
contractors during the demolition works.
Accordingly, the applicants are entitled to cash settlement for the costs associated
with removing these marks upon production of a reasonable quotation for these
works to the FSP.
Leadlight in the front door
Similarly, the FSP has not responded to this aspect of the applicants‟ clai m. The
quotations provided by the applicants do not appear to include the cost of replacing
the lead light glass damaged by emergency services personnel in gaining entry to the
home.
Subject to confirmation from the applicants that this item has not been allowed for in
their builders‟ quotes, the applicants are entitled to cash settlement for the cost to
repair the lead lighting upon production of a reasonable quote for this item to the
FSP.
Case No: 446027 Determination Page 10 of 10
3 Supporting information
3.1 Product Disclosure Statement
The policy coverage is detailed within the Product Disclosure Statement (PDS).
The PDS details:
“Settling your claim
Options to settle your claim
We may choose, at our option, one or more of the following ways to settle your claim:
1. Pay the cost to have your home rebuilt or repaired as new – that is, pay to rebuild or repair
it using the same materials if they are readily available in Australia or equivalent materials in
terms of quality, purpose and specifications.
2. Pay you the cost to us – that is, pay you what it would cost us to rebuild or repair your home
as new up to the:
- home sum insured
- sum insured that applies under the optional benefit „Landlord‟s fixtures and fittings‟.
We also pay any extra benefits that apply to your claim.
…
If only part of your home is affected
When only part of your home is damaged or destroyed, then we pay to repair or rebuild only
the area that was affected by the damage.
We don‟t pay for:
extra expenses to replace or match undamaged parts to create a uniform appearance
(but we do cover you for up to $500 under the Extra benefit „Matching repairs‟).
extra costs to rebuild or repair your home to a better condition than it was in before it
was damaged or destroyed (unless we need to meet current buildi ng standards ).”