Representations about construction funding led applicants to sign building contract

FirmFinancial Firm (Unknown - Credit)
Decided2017-01-03
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded$7,286
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

The applicants were told by an FSP manager that construction funding would be provided once a building contract was signed, but the FSP approved a smaller construction loan and they took a personal loan. AFCA ordered the FSP to pay the interest difference to 8 February 2017 and $2,000 for stress.

The FSP misled the applicants about the construction funding it would provide, so it must compensate the interest difference and the resulting stress, though not later costs of the works.

Issues

Subjects and remedies

financial hardshippay compensationpay non financial loss

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 445911 Determination Page 1 of 4 Case number: 445911 22 December 2016 1 Overview 1.1 Dispute This dispute is about whether the Financial Services Provider (FSP) misled the Applicants that it would provide them with all construction funds required to complete a home. 1.2 Issues and key findings Did the FSP mislead the Applicants? It appears that the Applicants held a genuine belief that the FSP would provide full construction funding to them based on representations made by Ms B, a manager of the FSP. Did the FSP cause the Applicants to suffer a loss? The FSP should refund the difference between i nterest charged at the personal loan rate and the home loan rate. The Applicants should receive non-financial loss. 1.3 Determination This determination is partly in favour of the Applicants. The FSP should pay the Applicants:  $7,285.72 calculated until 8 February 2017  $2,000 for stress and inconvenience suffered  These amounts should be paid into the personal loan account and the remaining balance transferred to the home loan account by 8 February 2017. Case No: 445911 Determination Page 2 of 4 2 Reasons for determination 2.1 Did the FSP mislead the Applicants? The Applicants understood the FSP would lend them all funds required to build The Applicants bought a block of land for $450,000 in September 2014. They borrowed $451,851.86 from the FSP to finance the purchase of the land. The loan included lenders mortgage insurance and credit protection insurance. In 2015, after checking with the FSP ’s mortgage lender specialist , Ms B, that the FSP would give them a loan for construction on the land, they entered into a building contract for $448,147.87 with their builder. Ms B of the FSP had told them they could go ahead and pay the deposit as the FSP would give them construction funding. They then paid the builder an $8,000 deposit. In April 2015, the FSP informed the Applicants that it could not approve the construction loan for the amount required. It did offer a construction loan for a lesser amount. The Applicants say they would not have signed the building contract, and paid a deposit, if the FSP had not:  told them that they needed to provide it, and  intimated that if they entered into a building contract, it would provide the loan they needed. The FSP needs to see the building contract as part of its loan assessment In accordance with standard banking practice, the FSP will not approve a construction loan until it has seen a building contract. The funding that the FSP offered the Applicants was not as much as the Applicants thought it would be, because the Applicants had misjudged the value of the finished home. The FSP’s valuer gave it a value at far less than anticipated. It is clear that the FSP told them they needed to provide a building contract, and it is also clear that the Applicants believed the FSP had agreed to fund all amounts needed to complete the construction of the building and finishes such as curtains, flooring, fencing and the driveway. I am of the view that the Applicants were misled. 2.2 Did the FSP make an error by offering the personal loan? As noted above, the FSP was unable to provide a construction loan for more than $413,000 which included LMI. Ms B suggested that that they take out a personal loan for $50,000 so they could complete the construction. The Applicants felt they had no choice but to accept this as they did not want to lose the $8,000 deposit they had already paid to the builder. The Applicants say: Case No: 445911 Determination Page 3 of 4  they would not have signed the building contract if the FSP had not misled them by causing them to believe that if they provided a signed building contract, the loan would be approved  when they signed the building contract they paid an $8,000 deposit to the builder which they say was non-refundable  in order to pay the builder and complete construction, they had to borrow a personal loan for $50,000 at high interest rates. They want the FSP to compensate the m for the high interest they have had to pay on those borrowings. 2.3 Did the FSP cause the Applicants to suffer a loss? The Applicants chose to continue with the building contract The FSP has provided FOS with a copy of the building contract. Under the terms of the contract (clause 3), either party may terminate the contract if funding is not obtained. If the builder terminates the contract because funding is not obtained, or because it issues a notice to the Applicants to show that they had ability to pay the contract price, and the Applicants do not comply, the Applicants forfeit the deposit. The contract is silent as to what happens if the Applicants terminate the contract because they did not obtain the required finance. It seems likely that the builder would seek to retain the deposit. At the very least, the builder would be entitled to keep and amount equivalent for the work done in preparing the contract, although it may have involved legal proceedings to sort out what the correct amount was. The Applicants are entitled to compensation In my view, the FSP misled the Applicants to believe that they needed to sign a building contract in order to get their loan approved. The FSP also misled them to believe that they would get a construction loan without the need for a personal loan. When they discovered that this was not the case, the Applicants could have cancelled the building contract and if they lost their deposit, could have recovered it from the FSP. This would have meant that the FSP would ha ve paid the Applicants the $8,000. The Applicants decided to proceed with the building contract and in my view it is fair and reasonable that they be compensated for the difference between the home loan rate and the personal loan rate. This totals $7,285.72 calculated until 8 February 2017. A copy of the calculation is enclosed with this Determination. The FSP has offered to fold the personal loan to the home loan and this is appropriate. The parties have until 8 February 2017 to arrange for this to occur. Non-financial loss It is clear that the stress the Applicants are suffering is due to having borrowed $50,000 at high interest rates in order to pay the builder and pay for other works. As explained above, the FSP is not responsible for the Applicants: Case No: 445911 Determination Page 4 of 4  making payments under the building contract or  borrowing money to make those payments. It appears the Applicants genuinely believed that the FSP would provide the construction loan if they entered into a building contract, and they believed this because of what Ms B told them. It is partly responsible for the stress suffered by the Applicants, because if they had not misled the Applicants, they might not have signed the building contract. If they had not signed the building contract, they might not have formed the view that they were obliged to continue with the contract. In the circumstances, the FSP should compensate the Applicants by crediting $2,000 to the personal loan account. It was the Applicants’ responsibility ensure they had sufficient fun ds It appears that there are still insufficient funds to complete all works required at the property, even though the construction loan and personal loan ought to have covered the building contract and quotations provided to the FSP in March 2015. Construction is nearly complete and the Applicants do not have enough money to complete items such as the driveway and fencing. They believe the FSP should cover those expenses. There is no obligation on the FSP to offer to lend the borrowers further funds to complete the construction of the home, or to fund the further works themselves. This is a commercial decision for the FSP.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.