Home / Financial Firm (Unknown - Credit) / Determination 445911
Determination 445911
Representations about construction funding led applicants to sign building contract
Summary
The applicants were told by an FSP manager that construction funding would be provided once a building contract was signed, but the FSP approved a smaller construction loan and they took a personal loan. AFCA ordered the FSP to pay the interest difference to 8 February 2017 and $2,000 for stress.
The FSP misled the applicants about the construction funding it would provide, so it must compensate the interest difference and the resulting stress, though not later costs of the works.
Subjects and remedies
financial hardshippay compensationpay non financial loss
Text of the determination
Determination
Case No: 445911 Determination Page 1 of 4
Case number: 445911 22 December 2016
1 Overview
1.1 Dispute
This dispute is about whether the Financial Services Provider (FSP) misled the
Applicants that it would provide them with all construction funds required to complete
a home.
1.2 Issues and key findings
Did the FSP mislead the Applicants?
It appears that the Applicants held a genuine belief that the FSP would provide full
construction funding to them based on representations made by Ms B, a manager of
the FSP.
Did the FSP cause the Applicants to suffer a loss?
The FSP should refund the difference between i nterest charged at the personal loan
rate and the home loan rate. The Applicants should receive non-financial loss.
1.3 Determination
This determination is partly in favour of the Applicants.
The FSP should pay the Applicants:
$7,285.72 calculated until 8 February 2017
$2,000 for stress and inconvenience suffered
These amounts should be paid into the personal loan account and the
remaining balance transferred to the home loan account by 8 February 2017.
Case No: 445911 Determination Page 2 of 4
2 Reasons for determination
2.1 Did the FSP mislead the Applicants?
The Applicants understood the FSP would lend them all funds required to build
The Applicants bought a block of land for $450,000 in September 2014. They
borrowed $451,851.86 from the FSP to finance the purchase of the land. The loan
included lenders mortgage insurance and credit protection insurance.
In 2015, after checking with the FSP ’s mortgage lender specialist , Ms B, that the FSP
would give them a loan for construction on the land, they entered into a building
contract for $448,147.87 with their builder. Ms B of the FSP had told them they could
go ahead and pay the deposit as the FSP would give them construction funding.
They then paid the builder an $8,000 deposit.
In April 2015, the FSP informed the Applicants that it could not approve the
construction loan for the amount required. It did offer a construction loan for a lesser
amount.
The Applicants say they would not have signed the building contract, and paid a
deposit, if the FSP had not:
told them that they needed to provide it, and
intimated that if they entered into a building contract, it would provide the loan
they needed.
The FSP needs to see the building contract as part of its loan assessment
In accordance with standard banking practice, the FSP will not approve a
construction loan until it has seen a building contract. The funding that the FSP
offered the Applicants was not as much as the Applicants thought it would be,
because the Applicants had misjudged the value of the finished home. The FSP’s
valuer gave it a value at far less than anticipated.
It is clear that the FSP told them they needed to provide a building contract, and it is
also clear that the Applicants believed the FSP had agreed to fund all amounts
needed to complete the construction of the building and finishes such as curtains,
flooring, fencing and the driveway. I am of the view that the Applicants were misled.
2.2 Did the FSP make an error by offering the personal loan?
As noted above, the FSP was unable to provide a construction loan for more than
$413,000 which included LMI. Ms B suggested that that they take out a personal
loan for $50,000 so they could complete the construction. The Applicants felt they
had no choice but to accept this as they did not want to lose the $8,000 deposit they
had already paid to the builder.
The Applicants say:
Case No: 445911 Determination Page 3 of 4
they would not have signed the building contract if the FSP had not misled them
by causing them to believe that if they provided a signed building contract, the
loan would be approved
when they signed the building contract they paid an $8,000 deposit to the
builder which they say was non-refundable
in order to pay the builder and complete construction, they had to borrow a
personal loan for $50,000 at high interest rates.
They want the FSP to compensate the m for the high interest they have had to pay on
those borrowings.
2.3 Did the FSP cause the Applicants to suffer a loss?
The Applicants chose to continue with the building contract
The FSP has provided FOS with a copy of the building contract. Under the terms of
the contract (clause 3), either party may terminate the contract if funding is not
obtained. If the builder terminates the contract because funding is not obtained, or
because it issues a notice to the Applicants to show that they had ability to pay the
contract price, and the Applicants do not comply, the Applicants forfeit the deposit.
The contract is silent as to what happens if the Applicants terminate the contract
because they did not obtain the required finance. It seems likely that the builder
would seek to retain the deposit. At the very least, the builder would be entitled to
keep and amount equivalent for the work done in preparing the contract, although it
may have involved legal proceedings to sort out what the correct amount was.
The Applicants are entitled to compensation
In my view, the FSP misled the Applicants to believe that they needed to sign a
building contract in order to get their loan approved. The FSP also misled them to
believe that they would get a construction loan without the need for a personal loan.
When they discovered that this was not the case, the Applicants could have
cancelled the building contract and if they lost their deposit, could have recovered it
from the FSP. This would have meant that the FSP would ha ve paid the Applicants
the $8,000.
The Applicants decided to proceed with the building contract and in my view it is fair
and reasonable that they be compensated for the difference between the home loan
rate and the personal loan rate. This totals $7,285.72 calculated until 8 February
2017. A copy of the calculation is enclosed with this Determination.
The FSP has offered to fold the personal loan to the home loan and this is
appropriate. The parties have until 8 February 2017 to arrange for this to occur.
Non-financial loss
It is clear that the stress the Applicants are suffering is due to having borrowed
$50,000 at high interest rates in order to pay the builder and pay for other works. As
explained above, the FSP is not responsible for the Applicants:
Case No: 445911 Determination Page 4 of 4
making payments under the building contract or
borrowing money to make those payments.
It appears the Applicants genuinely believed that the FSP would provide the
construction loan if they entered into a building contract, and they believed this
because of what Ms B told them. It is partly responsible for the stress suffered by the
Applicants, because if they had not misled the Applicants, they might not have signed
the building contract. If they had not signed the building contract, they might not have
formed the view that they were obliged to continue with the contract.
In the circumstances, the FSP should compensate the Applicants by crediting $2,000
to the personal loan account.
It was the Applicants’ responsibility ensure they had sufficient fun ds
It appears that there are still insufficient funds to complete all works required at the
property, even though the construction loan and personal loan ought to have covered
the building contract and quotations provided to the FSP in March 2015.
Construction is nearly complete and the Applicants do not have enough money to
complete items such as the driveway and fencing. They believe the FSP should
cover those expenses.
There is no obligation on the FSP to offer to lend the borrowers further funds to
complete the construction of the home, or to fund the further works themselves.
This is a commercial decision for the FSP.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.