Liability for storm roof damage declined except for FSP's own substandard repairs; cash settlement amount disputed
Text of the determination
Determination
Case No: 445267 Determination Page 1 of 8
Case number: 445267 30 January 2018
1 Overview
1.1 Dispute
The applicant holds a home building insurance policy with the financial services
provider (FSP). The applicant made a claim for storm damage to the roof and internal
areas of her property in January 2016.
The FSP agreed it was liable for certain internal and skylight repairs it had previously
completed, but declined to accept liability for any other damage because it says the
rest of the damage is not covered under the policy. The FSP offered to cash settle
the applicant for the rectification work on its previous repairs, however she wants the
FSP to attend to the work itself.
The case analyst recommended that the FSP cash settle the repairs arising from
previous work it had undertaken, but was not required to do anything further. The
applicant did not accept the recommendation.
1.2 Issues and key findings
Is the FSP liable for repairs to the roof?
The FSP is only responsible for repairs arising from its own earlier substandard work
on the property. It is not liable for any other damage. This is because the remainder
of the damage arose from excluded causes: building defects, design faults and
maintenance issues, rather than the 2016 storm event.
Is the FSP entitled to cash settle the applicant rather than repair the roof?
The terms of the policy allow the FSP to cash settle the applicant, and this is fair and
reasonable in the circumstances. That is because there is other work, for which the
FSP is not responsible, which also needs to be carried out to parts of the building
affected by the FSP’s previous repairs.
1.3 Determination
This determination is substantially in favour of the FSP.
The FSP is required to cash settle $6,000 for repairs to internal damage, the
skylights and roof required because of its previous unsatisfactory work. It is also
required to pay the applicant $200 compensation for non-financial loss. It is not
required to do anything further.
Case No: 445267 Determination Page 2 of 8
2 Reasons for determination
I have decided this case on the basis of what I consider fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous FOS decisions.
I have taken into account all the material submitted by the parties, both before and
after the recommendation. I am satisfied that the documentation I have relied on has
been provided to both parties. For the purposes of this determination, I will deal with
only those points considered relevant.
2.1 Is the FSP liable for repairs to the roof?
The policy covers ‘storm’ but excludes certain building defects and faults
The applicant’s policy is a home insurance policy. The policy responds to loss or
damage which arises from insured events listed in the policy. Cover is subject to both
specific and general exclusions.
Relevant to this dispute the policy provides cover for loss or damage caused by a
‘ storm ’ . However, the policy excludes cover for ‘ loss or damage caused directly or
indirectly by or in any way connected with … defects, structural or design faults, faulty
workmanship or faulty design …’.
It is for the applicant to prove, on the balance of probabilities, the roof damage for
which she is now claiming was caused by a storm event.
If that is established, the FSP must show, on balance, that an exclusion applies or
that it is otherwise entitled to decline the claim.
Claims history indicates previous repairs by FSP
The applicant has had a number of claims in relation to storm and water damage at
her property. A summary of the claims shows:
Date of claim Claim details Outcome
4 June 2010 Claim for water damage following a
storm event:
kitchen ceiling stained
surrounds of skylight damaged
tile grout of bathroom and laundry
FSP advised damage caused by
combination of excessive
rainwater and structural defects
to roof
Claim partially declined. FSP
accepted internal damage and
cash settled applicant
27 April 2015 Claim for storm damage. Applicant
says damage to skylight, kitchen,
bathroom and living room.
FSP’s assessor identified
defects in previous roof repairs
however also identified cracking
to skylight from hail damage
FSP accepted internal damage
as well as replacing skylight
polycarbonate sheeting, replace
Case No: 445267 Determination Page 3 of 8
kliplok sheeting and
replace/extend storm water
pipe . The repairer invoic ed the
FSP for $3,586.00
31 January 2016
(current claim)
The applicant lodged a claim for water
leaking from the previousl y replaced
skylight after a recent storm event.
FSP accepted its 2015 repairs
were substandard. However
FSP’s assessor identified
structural defects and faulty
repairs the FSP was not
responsible for. FSP therefore
offered to cash settle $2,336.40
As can be seen from the above summary, the FSP accepted storm damage to parts
of the applicant’s property for the April 2015 claim. It was evident the skylight and
some roof sheeting had been cracked due to hail on that occasion. The FSP
accepted liability for the 2015 repairs of the skylight, kliplock sheeting and storm
water pipe. It also repaired the internal damage, including to the kitchen, lounge and
bathroom ceilings.
The applicant has not, however, established that the current 2016 claim arose from
storm damage.
The information indicates the current damage was not caused by storm
The FSP says the applicant has not established that the damage subject of the
January 2016 claim, the current claim, was caused by the insured event of ‘ storm ’ .
The FSP says this because it has a number of reports which identify the main cause
of the damage as defects in repairs and design faults.
After the applicant lodged the current claim, the FSP organised an inspection by its
building service (Report A). The report identifies a number of previous repair
attempts across the roof, and ongoing issues with the skylight. (It should be noted
that the applicant has two skylights: one above the kitchen and one above the lounge
room.) Report A concluded that the main issue was design fault, however further
inspection was required.
The FSP then engaged a different building consultant (Report B) to inspect the cause
of the water ingress. Report B identified the FSP’s previous repairs to the ceilings of
the living room, kitchen and bathroom to be below industry standards. Report B also
advised the polycarbonate skylight sheeting the FSP had repaired was not installed
properly. Neither was the kliplok sheeting also replaced by the FSP.
However Report B also identified a number of issues that would be causing water
ingress, which are due to problems with the roof other than the FSP ’s repairs or
storm. These included:
the roof pitch was not in accordance with manufacturer’s minimum which would
cause water to pool in the roof void and enter ceiling cavity
the down pipe spreader and gutter had not been fixed by the applicant in
accordance with the recommendations from the 2010 claim
Case No: 445267 Determination Page 4 of 8
the roof junction between the applicant’s roof and neighbou r’s roof has poor
flashings and signs of ongoing issues
the fiberglass sheeting not repaired by the FSP was also installed incorrectly
several attempts have been made to waterproof the roof in various spots with
flashings and a large amount of sealant.
Throughout the various reports there is no indication of any damage caused by the
storm itself. As well, most of the identified damage, except for the poor repairs of the
FSP, are consistent with the repair and design faults identified in the applicant’s 2010
claim.
The FSP is liable for its own defective work but not that of others
It is evident there are structural defects and faulty workmanship on the roof , some
caused by the FSP and some by other third parties. I do not accept the storm itself
was the proximate (that is, the operative, dominant or effective) cause of the damage
for which the applicant is now claiming . While the actual water ingress may have
happened during the storm, I am satisfied the structural defects and faulty
workmanship on the roof were the reason the damage occurred. That is to say: had
the structural defects and faulty workmanship not been present, the rain from the
storm would not have entered and the damage would not have occurred.
As noted above, the policy excludes damage and loss caused directly or indirectly
by, or in any way connected with defects, structural or design faults, faulty
workmanship or faulty design. This means the FSP is not liable for structural defects
or faulty workmanship resulting from anything its contractors did not do.
The policy also excludes cover for wear and tear and lack of maintenance, including
rust, corrosion and deterioration. In the course of the 2010 claim, the applicant was
made aware of certain problems with the roof which were not covered under the
policy. That means she had the opportunity to attend to the recommended repairs or
rectification work before any further damage occurred. The applicant has not had all
that work carried out. So it is not reasonable to hold the FSP responsible for the
damage reasonably attributable to those outstanding issues, since it arose as a result
of deterioration and lack of maintenance.
However, the FSP is responsible for its own defective repairs and workmanship. That
means it is liable for the cost of repairing the living room, kitchen and bathroom
ceilings, the incorrectly installed polycarbonate sheeting for the skylight and the
problems with the replaced kliplok sheeting.
2.2 Is the FSP entitled to cash settle rather than repair the roof?
The policy allows the FSP to decide whether to cash settle or repair
The policy allows the FSP, in settling a claim, to decide whether to:
repair or rebuild
replace
provide a store credit for the amount the FSP determines to be reasonable
Case No: 445267 Determination Page 5 of 8
pay the applicant the amount the FSP determines to be the reasonable cost of
repairing or rebuilding the lost or damaged part.
The applicant says she wants the FSP to repair the damage rather than cash settle.
The FSP decided to repair the damage from the applicant’s 2015 claim. However,
that damage was not repaired properly and gave rise to this current claim. As well,
the applicant herself needs to attend to certain work on the property (principally, the
roof pitch), and there is some overlap in terms of the location and impact of that work
on the rectification for which the FSP is responsible.
Under the circumstances, it is reasonable that the FSP should make a cash
settlement, as it is entitled to do, rather than attend to the repairs itself. That will allow
the applicant the opportunity to attend to all inter-related repair work in an efficient,
effective and comprehensive way.
The FSP needs to pay the reasonable cost of repairs
To deal with its liability for substandard repairs, the FSP originally offered to pay the
applicant $2,336.40 on the basis of a quote/scope of works dated 31 October 2016.
That was to cover painting in the living room and kitchen, and ‘all works pertaining to
the reinstatement of the skylight, exhaust ducting, vent pipe cowls and vent pipes’.
The FSP has since increased the offer to $2,453.22 to broadly take into account
consumer price index from the date of the quote up to January 2018.
That scope of works does not, however, include other work identified in Report B as
requiring rectification:
the bathroom ceiling which was repaired by the FSP and identified as below
industry standards
upper kliplok sheeting repaired by the FSP and later identified as ‘defective
building work’
clarification as to whether the quote includes materials.
It is also not cle ar what exactly is included in the component of the FSP’s quote
($708 excluding GST) described as being for ‘all works pertaining to the
reinstatement of the skylight’. It would need to include replacement and
reinstatement of the lower skillion polycarbonate roof sheet and skylight fibreglass
sheet. The 31 August 2015 quote obtained by the FSP for the removal and
replacement of polycarbonate sheeting and damaged kiplock fibreglass sheeting was
substantially more than that in terms of labour ($2,160 excl GST) and materials
($1,100 excl GST), although that quote did include replacement of storm water piping
as well. So, I am not persuaded that the amount now offered is likely to be sufficient
to deal with all skylight-related works.
Relevant too, is the 6 August 2015 quote received by the FSP for the internal work to
the kitchen, bathroom and living room alone, which then already amounted to
$2,619.60.
It is fair that a reasonable and realistic allowance be made for the additional costs of
all the repair/reinstatement elements for which the FSP is responsible, and not just
those identified in its settlement offer.
Case No: 445267 Determination Page 6 of 8
It is also important to note that it appears the quotes obtained by the FSP were
prepared on the basis that it would be the FSP attending to the repair work, rather
than the applicant having to source her own repairer. That means she, as a retail
customer, may not be able to have the work done for the same price (such as any
trade discounts available to the FSP).
So, in calculating an appropriate and fair cash settlement amount, it is necessary to
consider all reasonable factors, including the nature of the repairs required and
whether the cash settlement will adequately ensure the applicant is able to properly
complete the repairs and cover all reasonable possibilities (including cleaning and
debris removal at completion of repairs). The amount should also take account of the
fact that the applicant loses the benefit of the lifetime guarantee available if the FSP
carries out the work.
There is no specific, complete and current quote for all the work for which the FSP is
responsible. So it is not possible to know exactly how much the necessary work will
cost. Under the circumstances, and taking account of the matters referred to above, I
consider it fair that the FSP pays the applicant $6,000 by way of cash settlement to
discharge its liability for the poor repairs previously carried out.
The applicant is entitled to compensation for non-financial loss
Under 9.3 of our Terms of Reference (TOR), FOS may award compensation for non-
financial loss in certain limited circumstances.
That includes for situations where there has been an unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with the
applicant’s expectation of enjoyment or peace of mind.
In this case, the applicant was reasonably entitled to expect that work undertaken by
the FSP in meeting its obligations under the policy, would be carried out in a
professional and reliable manner. Although there were matters which required action
by the applicant herself, she still had the avoidable additional upset and concern
caused by the FSP’s poor repairs and the way in which this was dealt with.
I consider it fair in the circumstances that the FSP pays the applicant $200 as
compensation for this.
Case No: 445267 Determination Page 7 of 8
3 Supporting information
3.1 Expert reports
Date of report Summary of assessment
25 February 2015
Report A
Insured advised the skylight has recently been replaced after
storm damage .
Leak appears to be related to base of upper sky light sheet and
gutter junction.
There have been a lo t of attempts at repairing roof.
Due to ongoing issues recommended to perform invasive search
to identify cause of water ingress .
The main issues are basically d esign faults however the skylights
were damaged during the storm and subsequent leaks have not
been rectified .
12 May 2016
Report B
The paintwork on the ceiling recently paint ed is ‘patchy’ and of
poor quality.
The adjoining kitchen paintwork is of similar quality with
insufficient paint co verage on the walls and ceiling.
Several cracks in the plasterboard lined ceiling of bot h rooms
have not been repaired prior to painting.
In the rear bathroom adjacent to the kitchen the centre of the
plasterboard lined ceiling joint has been unevenly filled with
plaster and the ceiling has not been painted.
The roof pitch of 4.1 degrees on the lower skillion roof does not
comply with the minimum pitch requirement of 5 degrees
(applicable since 1963) .
The low roof pitch will allow wat er to pond on the roof surfaces .
The inadequate guttering system is exacerbated by a downpipe
from the upper story roof discharging into the same area .
A building consultant recommended that a new downpipe
spreader be installed at the s outhern end of the gutter and for the
rainwater to be dispersed onto the lower adjacent roof covering
the side walk way. This had not been done .
Work undertaken by the applicant’s contractor on the gutter and
downpipe of the upper skillion roof does not com ply with
recommendations suggested by S in June 2010 .
Polycarbonate roof sheet which was replaced in late 2015 has
been incorrectly installed over, rather than under, the adjoining
northern roof sheet .
The upturned edge of the polycarbonate sheet has been roughly
cut off, and the edge of the sheet has been bedded in flexible
sealant on the adjoining roof sheet .
Polycarbonate roof sheet on the lower roof has been incorrectly
installed and has been damaged in the process .
The underside of the fiberglass sheet a flexible sealant drip edge
has been poorly installed .
I observed that all of the Klip - Lok® roof sheet ends, except for the
fibreglass sheet, have been folded down into the quad gutter. I
Case No: 445267 Determination Page 8 of 8
noted that on the underside of the fibreglass sheet a flexible
sealant drip edge has been poorly installed. I observed notable
gaps in the continuity of the flexible sealant drip edge whic h, I
consider, will allow water to backflow. I als o observed that the rib
ends of the roof sheets have not been s ealed off which will also
permit driving rain to penetrate the interior of the building in
certain weather conditions.
3.2 Relevant policy terms
Extract
General exclusions Under this policy there is no cover provided for any loss, damage or
liability caused directly or indirectly by or in any way connected with :
defects, structural or design faults, faulty workmanship or faulty design
wear and tear and lack of maint enance including rust, corrosion and
deterioration
damage to your building or part of yo ur building that at the time it was
built, renovated or installed was not compliant with the relevant local
government regulations, or the requirements of any statutory authority .