The applicants claimed under their landlord insurance after a 2014 weather event damaged a pool area, retaining wall, granny flat and tiling. The FSP accepted the claim but limited its liability to the scope of works from its consultant report.

The policy covers only damage caused by the insured event and pays only for damaged parts, so the FSP may rely on the consultant's report and scope of works.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 445239 Determination Page 1 of 5 Case number: 445239 17 March 2017 1 Overview 1.1 Dispute This matter involves a claim by the applicants under their Landlord Cover Insurance Policy, held with the financial service provider (FSP), following damage at the premises. The F SP has accepted the applicants’ claim but a dispute has arisen as to the extent of the FSP’s liability under the terms and conditions of the policy. 1.2 Issues and key findings What is the extent of the FSP’s liabi lity under the terms and conditions of the policy? The FSP is entitled to rely upon the report prepared by building consultants and engineers CRD and the scope of works provided with that report. The FSP is not required to replace tiles which were not damaged in the flood event or to attend to the cracks the applicants say are outside the granny flat. 1.3 Determination This determination is in favour of the FSP. The FSP is entitled to rely upon the report from the building consultant and engineers CRD and the scope of works to meet its obligations under the terms and conditions of the policy. Case No: 445239 Determination Page 2 of 5 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the material exchanged. This determination follows consideration of all of the information exchanged and is based on what is fair in the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice and where applicable, prior determinations. 2.1 What is the extent of the FSP’s obligations under the terms and conditions of the policy? Coverage of the policy The coverage provided by the applicants’ Landlord Cover Insurance Policy is in relation to loss or damage caused by an insured event listed in the policy. This means that not all loss and damage is automatically covered, but rather only loss and damage caused by an insured event listed in the policy. The coverage provided by the policy is detailed within the Product Disclosure Statement (PDS). The PDS details: ‘… … … …’ The PDS also details how the FSP will settle a claim: … Case No: 445239 Determination Page 3 of 5 … ... ’ It is settled insurance law that the insured carries the onus to establish that the loss and damage at the premises is covered by the terms and conditions of the policy. Circumstances of the loss and the claim The premises were impacted by a significant weather event in October of 2014. As stated, the FSP has accepted the applica nts’ claim but a dispute has arisen as to the extent of the FSP’s obligations under the terms and conditions of the policy. The parties have provided reports to support their respective positions. Following discussions the FSP engaged building consultant a nd engineers CRD who provided a report dated 10 November 2016, together with a scope of works. The report from CRD is logical and thorough and its conclusions are compelling. The report is supported by helpful photographs. The applicants have provided a report from a pool specialist, which supports the need for further review and work in the pool area. The FSP seeks to meet its obligations under the terms and conditions of the policy, on the basis of the report from CRD. By letter dated 20 January 2017, the FSP advised the applicants that CRD had been instructed to obtain remediation quotations with a view to undertaking the stabilising of the pool and the surround, including repairing the tiling and concrete as required. The work to be undertaken includes a full inspection by a builder in accordance with the scope of works provided by CRD, with the applicants being provided with a copy of the inspection, for review. The FSP confirms that the scope of works also allows for additional works should, in the course of rectification, it be identified that such additional works be required to satisfactorily reinstate the damage. Having reviewed all of the exchanged material, I am satisfied that the FSP is entitled to meet its obligations under the policy, by reference its letter to the applicants of 20 January 2017 and to the report and the scope of works provided by CRD, which includes works to the pool area. Case No: 445239 Determination Page 4 of 5 Retaining wall The applicants made a claim in relation to a retaining wall at the front of the property but have since said that they reluctantly accept the FSP’s position that it is entitled to rely on an exclusion within the policy for retaining walls. Having reviewed the exchanged material I am satisfied not only does the exchanged material confirm that the retaining wall was not damaged as part of the significant weather event in October 2014, but also the exclusion within the policy and detailed above, entitled the FSP to deny the applicants’ claim in regard to the retaining wall. The cracks on the outside of the granny flat The applicants have made a claim in regard to the cracks on the outside of the granny flat. Having reviewed all of the exchanged material I am no t satisfied that the applicants have established that any damage to the granny flat is caused by the significant weather event from October 2014. The FSP is entitled to deny the applicants’ claim in this regard. Tiling in the area of the southern patio and the front street access stairs The applicants have made a claim in relation to tiling in these areas so as to match the tiles that are required to be replaced around the front porch area and the pool. The policy provisions are clear and unambiguous (detailed above) and provide that the FSP is only required to pay for the part of the building that has been damaged and the FSP is not required to pay for undamaged parts of the building in order to achieve a uniform appearance. Where building materials are unavailable or it is not possible to match them, the FSP has the right to pay for the nearest equivalent or similar materials. Whilst this is partially a subjective assessment, I accept that the FSP must make reasonable efforts to match the materials with the nearest equivalent where the original is not available. Further, it is appropriate that the applicants’ participate in the tile selection to ensure quality and matching as far as possible. Further discussion Finally, the FSP advised the applicants that upon evaluation of a timeline for remediation, compensation and loss of rent in accordance with the provisions of the policy would be estimated. In this regard, the FSP seeks to record that it has previously offered a settlement for 24 weeks loss of rent to finalise its obligations under the policy. I am satisfied it is appropriate that the FSP makes a final decision regarding the question of compensation and loss of rent, once a final timeline for remediation has been prepared. Case No: 445239 Determination Page 5 of 5 Conclusion Upon acceptance by the applicants of this determination, the applicants are required to provide the FSP with permission to proceed with the scope of works as detailed by CRD.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.