Home / Financial Firm (Unknown - Insurer) / Determination 444614

Determination 444614

Commercial building damage claim declined in full

FirmFinancial Firm (Unknown - Insurer)
Decided2017-11-08
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$2,893
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant claimed for commercial building damage from wind, water and a telecoms pit, and the FSP declined it. AFCA found the FSP could not decline but reduced its liability to 50% of reasonable costs and ordered expert and legal costs of $2,893 paid.

Exclusions were not established and the wind and water event was triggered, but concurrent drainage causes justified reducing the FSP's liability to 50%.

Issues

Subjects and remedies

home or building damagesmall businesspay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 444614 Determination Page 1 of 10 Case number: 444614 8 November 2017 1 Overview 1.1 Dispute The applicant made a claim under the business insurance policy held with the financial services provider (FSP), for damage to a commercial building. The claim arose after the tenant noticed water entering through gaps in the roof, as well as finding a crack in a brick wall. The FSP declined the claim on the basis that the damage was not the direct result of a single insured ‘wind and water’ event. It also said that cover for ‘accidental damage’ did not apply because the damage was progressive and long-term. It raised a number of exclusions, including gradual deterioration, error in design and faulty workmanship. The applicant has attended to repairs and wants the FSP to pay the claim and cover the associated costs. 1.2 Issues and key findings What was the cause of the damage? The damage was caused by a combination of factors: the installation (by a third party) of a telecoms pit close to the building, drainage issues, lack of lateral restraints at roof level, adverse soil conditions and limited footing strength. Is the FSP entitled to decline the claim? The policy cov ers ‘accidental damage’, which the Panel considers applies in respect of the impact of the telecoms pit ; and ‘wind and water’, which applies to the roof . The FSP has not established that exclusions apply, and so it is not entitled to decline the claim. However, given the concurrent contribution to the damage by, most significantly, the drainage issues, it is fair in the circumstances that the FSP’s liability for the claim be reduced. 1.3 Determination This determination is partly in favour of the applicant. The FSP is required to indemnify the applicant to the extent of 50% of the applicant’s reasonable costs incurred for the claim-related damage, subject to the applicable policy terms, conditions and limits; to pay the full cost of the applicant’s experts’ r eports and solicitor’s fees ; and to pay statutory interest on the settlement amount, calculated from the date the respective costs were incurred, to the date of settlement. Case No: 444614 Determination Page 2 of 10 2 Reasons for determination Due to the complexities involved in this dispute, it has been referred to a Panel for determination. There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues arising from the information exchanged. This determination follows consideration of all the information exchanged and is based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and, where appropriate, previous FOS decisions. 2.1 What was the cause of the damage? Applicant must establish a prima facie claim The applicant has the onus of establishing, on balance, that there is a valid claim under the policy. The tenant of the insured building was reported as saying that approximately 12 months before the FSP’s building consultant, CRD, inspected the property in December 2014, he noticed water coming into the internal face of the eastern gable end roof of the building, and this had happened because of separation of the roof flashings from the gable end wall. There was also cracking and movement in the east wall of the building. The tenant is said to have advised CRD that the movement had worsened over the 6 months before the inspection, and so the issue had been reported to the applicant. The claim was made in early December 2014. Investigations identified further water-related problems, as well as other unforeseen issues (involving the building footings) at gro und and underground level. Policy covers insured events, including ‘wind and water’ The policy covers loss or damage caused directly by ‘wind and water’ , subject to certain exclusions. This insured event can reasonably be interpreted to allow for the eff ect of ‘wind’ or ‘water’. Here, the evidence indicates wind directly contributed to the damage at roof level, even though it was not the result of a single identifiable event. The policy does not define ‘event’, nor does it explicitly limit the application of cover by reference to an individual occurrence. In the particular circumstances of this case, the Panel is not persuaded it would be fair to impose that limitation in respect of the roof damage. The evidence also shows that there was water discharging from the downpipe/stormwater drain and that this had affected the building below ground level. The Panel is satisfied the applicant has shown, on balance, there is a prima facie claim for damage caused by ‘wind and water’. Case No: 444614 Determination Page 3 of 10 Policy covers ‘accidental damage’ The policy also covers ‘ accidental damage ’: that is, loss or damage caused by any accident, where the loss does not otherwise fit within any of the specified insured events. The policy does not define ‘accidental’ or ‘accident’ , and so the Panel is satisfied the ordinary or usual meaning of ‘unintended’ and ‘unforeseen’ should apply. Certain exclusions also apply to this cover. In the course of investigations into the claim, it was found that a telecoms pit had been installed by a third party on land immediately abutting the insured premises, and that this too had contributed to the damage by its impact on footing stability, and associated movement. The applicant was not responsible for the installation of the pit, nor does the Panel consider the applicant can reasonably be regarded as having intended or foreseen any damage to the building arising from it. The Panel is therefore satisfied the applicant has shown, on balance, there is also a prima facie claim for ‘ accidental damage ’ . Expert s’ reports identify a combination of factors contributing to the damage CRD Building consultant, CRD, inspected the property in December 2014 and identified the primary cause of the damage as ‘ long-term and ongoing foundation movement ’ , combined with inadequate lateral restraint of the top of the gable end wall and the roof. CRD noted the damage to the building was likely the ‘cumulative effect of many wind storms’, rather than a single storm event. CRD’s report is stated as specifically excluding any assessment of plumbing or drainage. HCE The applicant then engaged HCE, consulting engineers, to report on the cause of the damage, specifically having regard to the presence of what was found to be a large telecommunications pit in the footpath next to the front north-east corner of the building. The inspection showed that rotation to the east had occurred in the front wall, including towards the south-east corner away from the location of the pit. HCE were of the opinion that the pit was installed after the building was constructed (this is consistent with the finding of FE, in their report referred to below, who also said they strongly suspected the pit was installed well after the building was constructed: it was ‘ a large pit for complex telecommunications installation, such as were not in use until later in the 1970s’). HCE ’s conclusions were consistent with those of CRD, in identifying the lack of lateral restraint at roof level as a cause of the movement in the front east wall of the building. HCE said th e outwards rotation at the front of the building ‘is typical of problems that can occur due to the wall being inadequately restrained at roof level’. Case No: 444614 Determination Page 4 of 10 However, HCE also identified a further cause of the movement (and the cracking of the front north-east corner) as the undermining and settling of the footing below the wall due to the installation of the pit and the many conduits below ground level running from it. It noted that the movement of the wall was most severe adjacent to the pit, and concluded: ‘In our opinion, the crack that has occurred in the brickwork of the east wall is a result of settlement of the footing due to undermining of the footing as a result of the installation of the pit.’ FE Following the report of HCE, FE was engaged by the FSP to undertake a geotechnical investigation to assess the building footings. As part of the investigation, as reported in April 2015, a borehole was dug to check soil moisture. This identified ‘very moist to wet conditions at shallow depth’. FE found a nearby stormwater drain, leading from the north side of the building and discharging into the street gutter; but noted that the discharge point into the gutter was blocked with debris and the drain did not flow. FE concluded that leakage from the drain ‘caused the foundation soil to become wet and loose [sic] strength’, and this contributed to footing movement and the damage to the building. A further contributing factor was said to be the adverse soil profile of the area, although it is not clear that any comparison of the impact of that on other undamaged parts of the building was made. FE also found no underpinning of the building footings along the front east wall and adjacent to the pit. FE identified the location of the pit as contributing to the footing subsidence and rotation, observing that the depth of the pit floor below ground level was approximately 1.7m, while the footings were founded at only 420mm. FE made the following ‘ estimate ’ of the proportionate contribution to the damage by the factors it had identified as being involved in the ‘differential footing movement only’:  drainage/plumbing faults 50%  proximity of telecoms pit 30%  adverse soil conditions 10%  limited footing strength 10%. FE’s report made no allowance for the likely impact on the damage of the lack of lateral restraints at the roof level (and the effect of wind on that part of the building). It specifically says it ‘does not cover aspects associated with the superst ructure of the building that may also have contributed to the development of the damage’. FSP says damage not covered, or is caused by excluded factors It is for the FSP to show, on balance, that an exclusion applies, or that it is otherwise entitled to decline the claim. Impact of ‘water’ at g round level and below was indirect The FSP maintains that water escaping from the stormwater drain caused the foundation soil to become wet and lose strength; that in turn caused the footing Case No: 444614 Determination Page 5 of 10 movement, which resulted in the damage to the wall. It submits the influence of the water was indirect, and that the ‘wind and water’ event is therefore not triggered in that context. It also submits the exclusion for ‘water seeping from outside the premises’ would apply because the water was coming from the stormwater drain, and the subsidence/settling occurred at least in part because of the water from the drain. A photograph shows that the downpipe (and the join to the stormwater drain) from which the water leaked is on the external wall of the building, but it is attached to and part of the building. So while the water was strictly discharging from outside, it was from a source which was effectively part of the premises. It was also not the case that the water was seeping from the outside into the inside of the building; and the Panel considers that is likely to be the scenario which the exclusion (given its wording) is intended to address. Here, the water was discharging from the join between the downpipe and the stormwater drain and saturating the surrounding ground. FE, engaged by the FSP to undertake a geotechnical investigation, uses the words ‘defective’ and ‘faulty’ to refer to the stormwater drain. It says there was ‘a plumbing fault’, but is not specific as to the nature of the fault, apart from a reference to the fact that the drain ‘no longer flows’ and the discharge point is ‘obviously blocked with debris’. The applicant pointed out that in about June 2014 there had been work carried out in and around the telecoms pit which was immediately adjacent to the drain leading from the downpipe. He believes it is likely the work crews placed debris over the drain and caused it to block; this meant that because water could not flow through the drain from the downpipe, it then built up and had to discharge somewhere – namely, at the joint between the two pipes. The applicant says the drain was not blocked in March 2014, and a photo provided from that time appears to support that. The Panel is satisfied that the available evidence does not reasonably support the conclusion that this was a case of ‘faulty workmanship’ in the drainage. Instead, it is more likely than not that the drain only stopped functioning properly after it was bl ocked by debris. That exclusion does not apply, in any case, to damage from ‘wind and water’. However, the Panel is satisfied that even if the exclusions above do not apply, the evidence indicates the damage to the building was not ‘directly caused’ by t he water, and that means an insured event is not established in respect of the discharge of water from the pipe/drain. Exclusions do not apply to ‘accidental damage’ The available evidence indicates, and the FSP acknowledges, there has been long- term foundation movement. However, the evidence does not establish that the drainage/plumbing issues were long -standing, or even in existence when the damage was apparently first noticed by the tenant in about December 2013, and reported to the applicant in June 2014. The indications are that in March 2014, the stormwater drain was not blocked; in about June 2014 there was work done in the area of the Case No: 444614 Determination Page 6 of 10 drain by third parties which is likely to have been what caused the blockage; and the inspection by FE which identified the very moist soil conditions was only conducted in about March 2015, by which time it is to be expected there will have been a noticeable moisture build-up. It is not clear on the evidence that the discharge of water from the blocked pipe/drain was, in isolation, sufficient – either in terms of volume or duration – to have caused the damage; which was, in any case, already evident well before the blockage is likely to have occurred. However, the tenant apparently did report that the damage worsened over the following 6 months; and the Panel considers it reasonable to accept that this issue accelerated the rate and degree of damage. The telecoms pit, by contrast, was more likely than not installed in the 1970s (after the building was constructed), and both HCE and FE identify this as a significant contributing factor to the damage and long-term foundation movement. The Panel does not agree with the FSP’s submissions that exclusions for ‘errors in design’ and ‘faulty workmanship’ shoul d apply in relation to the installation of the pit, or to the building’s ‘limited footing strength’. That is because it is not fair or reasonable in the circumstances to hold the applicant responsible for the pit which was installed by a third party, or for the accidental impact of that on the insured building. Nor is there anything to indicate that the footings themselves were not appropriate and suitable at the time the building was constructed. They had apparently ‘not been underpinned in proximity to the telecommunications pit’ (as noted by FE), and subsequently appeared to be inadequate to properly support the building after the installation of the pit. However, again, that does not represent an error in design or any fault in workmanship for which the applicant is reasonably responsible, or on the basis of which the FSP should be entitled to decline the claim. The FSP has also suggested that the exclusions for ‘gradual deterioration’ and ‘normal settling, shrinkage or expansion in buildings, foundations or walls’ should apply. However, it is clear on the evidence that this was not a case of ‘normal’ settling: it was abnormal movement resulting from the impact of the telecoms pit, together with the influence of the drainage issues once they arose. HCE specifically referred to the settling as being due to ‘undermining’ because of the pit. Similarly, the deterioration was not the gradual deterioration that might reasonably be expected over time from the ordinary use of a building in the normal course of events: it was progressive deterioration in the strength and serviceability of the footings as a result of the impact of unforeseen and unintended external factors; which in turn led to movement and cracking in the wall. Exclusions do not apply to wind damage at roof level As already noted, the Panel accepts that the roof-related damage falls within the insured event of ‘wind and water’. T hat damage is acknowledged as having been exacerbated by the lack of lateral restraints in the roof. However, CRD acknowledged the construction of the building (while not consistent with current building standards) Case No: 444614 Determination Page 7 of 10 was typical of those built in the 1960s/1970s. That means it would not be fair to regard the lack of lateral restraints as an ‘error in design’, even if that e xclusion applied to the ‘wind and water’ insured event, which it does not. Nor does the exclusion for ‘gradual deterioration’ apply to the insured event of ‘wind and water’ . 2.2 Is the FSP entitled to decline the claim? There were several concurrent causes of the loss It is well-established law that a proximate cause is not necessarily the first or last or the sole cause of the loss. It is the effective, dominant or operative cause. The identification of the proximate cause is a question of fact that depends on the circumstances in each case. The courts have said that if one cause would have resulted in the harm in any case, and the other would not have done so in the absence of the first, then the first is the proximate cause. There may also be circumstances where it is reasonable to conclude that there were 2 or more causes which were equal or concurrent in their efficiency in bringing about the damage. Concurrent causes can occur where there are 2 or more events, each of which is independently capable of causing the loss; or where there are events, each of which without the other could not have caused the loss. Having regard to all the available evidence, the Panel considers, on balance, that the effective cause of the loss was the concurrent operation of the impact of the telecoms pit and the drainage issues. The Panel also considers there was a contribution to the damage by the impact of wind on the roof, with its lack of lateral restraints; as well as reciprocally to the roof damage because of the compromised stability of the wall. While noting the possible contribution to the damage of the limited footing strength and adverse soil conditions, as specifically raised by FE, the Panel is not persuaded the FSP has shown those elements should reasonably reduce the FSP’s liability for the damage. It is fair that the FSP’s liability for the claim be reduced The Panel considers it is therefore fair in the circumstances that the FSP’s liability be reduced to take account of the concurrent contribution of the drainage issues to the overall damage. On the applicant providing appropriate evidence of expenditure, the FSP should settle the claim by paying 50% of the costs reasonably incurred for the claim-related damage to the building, but subject to and in accordance with applicable policy terms, conditions and limits. The applicant has provided a list of costs, although it appears that much of that list is not related to the claimed damage, but instead is to do with subdivision of the property. The FSP is only responsible for those costs directly related to the claimed damage. That includes any relevant ‘additional benefits’ under the policy. Case No: 444614 Determination Page 8 of 10 The FSP is also required to pay interest at the statutory rate on the settlement amount, from the date the costs were incurred to the date of settlement. FSP is responsible for other associated costs The applicant is also seeking reimbursement of legal fees of $1,375, the costs of HC’s report s ($836 and $396), and the cost of the water leak test by AP ($286). The policy provides in the ‘Additional Benefits’ section 4.2 for such payments, as does 9.4 of the FOS Terms of Reference. The Panel is satisfied it is fair in the circumstances that those costs be paid in full by the FSP, since they were reasonably incurred and assisted in resolving the claim and dispute. Again, interest is payable on these amounts from the date they were paid, to the date of settlement. Case No: 444614 Determination Page 9 of 10 3 Supporting information 3.1 Policy terms and conditions Page Extract 5 Cover We will indemnify you ...in respect of physical loss of or damage to: (a) buildings… directly caused by the following insured events during the period of insurance. Insured events 3.3 Wind and water Wind and water including water and any other liquid discharged from mains, pipes, gutters, drains, tanks or fixed apparatus used to hold or carry liquids, but not loss or damage: … (c) b y water seeping from outside the premises… 6 - 7 3.11 Accidental damage (a) Loss or damage to buildings or contents caused by any accident except loss or damage caused by: (iv) wear and tear,….gradual deterioration… (vi) error or omission in design, plan or specification… (vii) faulty materials or faulty workmanship… (xiv) loss of or damage to property directly or indirectly caused by or contributed to by normal settling, seepage, shrinkage or expansion in buildings or foundati ons, walls, … 3.2 E xperts’ reports Reports Key points FSP’s expert (CRD) Report 16 December 2014  T he rotation and separation of the eastern gable end wall from the roof structure is primarily a result of foundation movement, combined with inadequate connection and lateral restraint of the top of the wall . Case No: 444614 Determination Page 10 of 10  The cumulative effect of wind events over a period of many years would have exacerbat ed the separation between the gable end wall and roof structure. FSP’s expert (FE) Report 21 April 2015  It is con sidered probably that the location of the pit adjacent to the front corner of this building has contributed to footing subsidence and rotation to the pit.  …the front east wall footings have not been underpinned in proximity to the telecommunications pit  …there is a plumbing fault…The stormwat er drain leading from the front north east corner of the building is defective. FSP’s expert (C) First supplementary report 13 May 2015  Noted the insured peril of ‘wind and water’, and that the policy covers damage caus ed by discharge from drains  Sought instructions from FSP as to whether the policy might respond to the proportion of damage caused by the stormwat er drain Applicant’s expert ( HC ) Report 4 February 2015  The outwards rot ation which has occurred [of] th e front wall of the building is typical of problems that can occur due to the wall being inadequately restrained at roof level….there does not appear to be any lateral restraint at this level to prevent movement…  …it is also our opinion that the movement o f the east wall could have been contributed by the installation of the pit, and the installation of the conduits below ground level outside of the front of the building, undermining the existing footing below the east wall. The movement of the wall is most severe adjacent to the pit…  The stepped diagonal crack that has occurred [of] the brickwork near the front north - east corner adjacent to…the pit…is typical of problems that can occur due to settlement of the footing below the wall.  …it is our opinion tha t the settlement of the footing has occurred from the likely undermining of the footing due to the installation of the pit. Applicant’s expert (AP) Report 16 January 2015  CCTV inspection on stormwater drain front right corner of building located partially blocked cast iron pipe and faulty connection from downpipe to drain. We could not prove the watertightness of this line.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.