Claim for replacement of bed base declined after water damage

FirmFinancial Firm (Unknown - Insurer)
Decided2017-03-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$4,349
SourceAFCA PDF

Summary

The applicants claimed the cost of a bed base after water damage, which the insurer declined. AFCA found the bed base was damaged by repositioning in storage, not by an insured event, and that the applicants were misled but not prejudiced, so it ordered nothing further.

The damage occurred from an uninsured event, and the applicants would have bought a new base regardless of the misleading statement.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 443327 Determination Page 1 of 4 Case number: 443327 16 March 2017 1 Overview 1.1 Dispute The applicants hold a home and contents insurance policy (Policy). The policy was issued by the financial services provider (FSP). The Policy started on 15 December 2013 and renews annually. On 12 January 2016 the applicants lodged a claim for water damage to their home and contents. The FSP has settled the claim save for a bed ensemble. The FSP cash settled the applicant for the mattress, however it has denied the applicants claim for the replacement of the base of the ensemble. It says that the damage to the base was not caused by an insured event and was salvageable. Further it says that it had not confirmed cover of the bed base until after the applicant’s purchased it. The applicants dispute this and say that the FSP told them the bed base would be covered. They relied on the FSP’s representation and purchased a bed base. They applicants are seeking reimbursement of the cost of the bed base in the amount of $4,349.00. 1.2 Issues and key findings Does the Policy respond to the claim for the bed base? Based on the information available the bed base was not damaged by an insured event. Rather any damage to the bed base was caused by it being repositioned in the storage container by the applicants. Did the FSP mislead the applicants? The FSP did tell the applicants that the bed base was beyond salvage and would be replaced. However, the applicants were not prejudiced as at the time they purchased the bed base they were aware that a final decision for cover had not been made. Are the applicants entitled to further compensation? As the FSP has already paid compensation of $1,100, no further award is warranted. 1.3 Determination This determination is in favour of the FSP. The FSP need not take any further action. Case No: 443327 Determination Page 2 of 4 2 Reasons for determination 2.1 Does the Policy respond to the claim for the bed base? The Policy covers loss or damage caused by insured events There is no dispu te that the applicants’ home and contents sustained water damage due to a fridge leak. The applicants were away at the time and returned on 12 January 2016 at which time the damage was discovered and the claim lodged. The Policy provides cover for damage caused by the escape of liquid. The Product Disclosure Statement (PDS) says the Policy will cover: “Loss or damage to your contents caused by liquid leaking, overflowing or bursting from any of the following: • refrigerators, freezers, dishwashers and wash ing mac hines;” The claim was accepted and assessment of the damage commenced. The master bed ensemble was not included on original non-salvageable report An assessor attended on 13 January 2016. A report of that attendance dated 19 January 2016 says: “Flooding in bedrooms 1, 2, 3, hallway, entry, lounge room, kitchen, garage & downstairs storage room” The carpet was removed from the bedrooms. The assessor then undertook to inspect all damaged contents items in order to compile a beyond salvage list. This list includes items from all of the affected rooms including bedroom 1,2 and 3. On 4 March 2016 the applicants confirmed that they had a copy of list. The master bed ensemble does not appear on this list. Based on the information available I am satisfied that the master bed ensemble was not placed on the beyond salvage list at or around the time the damage occurred. On 18 May 2016 another assessor attended the insured address to inspect the contents that had been in put storage. In the report of this site visit dated 25 May 2016 says: “IO advised the mattress will remain onsite in which has been cash settled until the bed base has been replaced/settled. [Assessor] technicians have advised the bed bases were in a salvageable condition along with the mattress and [assessor] have not recommended the replacement as the items remained in a salvageable condition relating to the insured event.” On the balance of probabilities the master bed suite was in a salvageable condition when it was removed from the bedroom in order for the building repairs to be undertaken. The bed base sustained damage when repositioned in the storage container Photographs of the storage container were taken at the time the contents were put into the container. The container was locked b y the assessor. The applicants accessed the storage container and removed some items and repositioned others. Based on the assessor’s report the items in storage were moved by the applicants , and the repositioning of the bed base within the storage area caused some damage to the bed base including scuff marks. Photographs of the bed base and the Case No: 443327 Determination Page 3 of 4 assessor’s comments confirm no micro bacterial activity on the bed base. The report says: “[Assessor] advises the bas es were in a salvageable condition at the tim e of positioning and following IO’s access to the container have since sustained markings from the repositioning.” I am satisfied that the bed base sustained damage as a result of an event that is not an insured event. The applicants are not entitled to cover under the Policy for the bed base. 2.2 Did the FSP mislead the applicants? The FSP agreed to replace the bed base and then reversed the decision The applicants say that the FSP should reimburse them for the cost of the bed base because it agreed to do so on numerous occasions. Based on the information available the FSP did agree to cover the bed base on several occasions in April and May 2016. I am satisfied that on 22 April 2016 the FSP confirmed in writing that it would cover the cost of the king bed ensemble. It maintained this position until on or around 4 May 2016. The FSP reversed the decision to cover the base on 13 May 2016 and the applicants were told the final claim decision had been made to decline cover for the base on 16 May 2016. However on 6 May 2016 (the day before the applicants ordered the bed base) the FSP told the applicant’s that a final decision on the bed base had not been made and that it may not be covered. Applicants were not prejudiced by the misleading information I accept and the FSP acknowledges that the applicants were misled when they were told the bed base would be covered. However I am not satisfied that the applicants were prejudiced by this because:  the bed base was not on the original beyond salvage list and was put into storage while the building repairs were done  the applicants were told the day before they ordered the bed base that it had not been accepted  the applicants told the FSP that they did not want to lay a new mattress on an old ensemble. Based on the information available and on the balance of probabilities I am satisfied that the applicants did not rely on the FSP ’s representation that the bed base would be covered as they would have purchased a new base in any case. Further the FSP’s final decision tha t the bed base would not be covered was made on 16 May 2016. Had the applicants decided that they would not purchase a new base without insurance cover the order could have been cancelled as the bed base had not been paid for in full. Case No: 443327 Determination Page 4 of 4 2.3 Are the applicants entitled to further compensation? FOS has a limited jurisdiction for the award of non-financial loss Under the Terms of Reference, FOS may award compensation (capped at $3,000) for non-financial loss where an applicant has suffered an unusual degree or exte nt of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. However, FOS takes a conservative approach to the award of compensation for non- financial loss. FOS expects applicants to be moderately robust and bear the usual stress and inconvenience associated with an insurance claim. The FSP has compensated the applicants for claims experience The FSP agreed to cover the cost of an inflatable mattress worth $200 outside of the Policy terms and conditions. Further the FSP authorised an additional payment of $900 in recognition that the applicants did not receive the level of service expected during the claim. Having reviewed all of the information provided to FOS by the parties I am sa tisfied that no further award of compensation is warranted.