Determination 443217
Storm damage to retaining wall reversed after FSP said it was covered, plus claim handling delay
Summary
An applicant's storm-damaged retaining wall was initially accepted for accidental damage cover, then declined after months of work and a reversed cash settlement. AFCA found the policy excludes retaining walls but that the FSP's misrepresentation caused detriment, ordered $11,000 cash settlement with interest, and $2,000 non-financial loss.
The FSP's repeated assurances that the wall would be covered caused detriment to the applicant, so it must compensate the deterioration of the wall despite the policy exclusion.
Issues
- Misleading conduct primary · upheld
“From 13 November 2015 until 18 May 2016 the FSP misled the applicant by stating that the damage to the retaining wall would be covered”
- Claim denial secondary · not upheld
“The Policy does not respond to damage to retaining walls, regardless of whether the damage is caused by storm or flood or accidently”
- Poor claim handling secondary · upheld
“The handling of the claim fell below expected standards”
- Delay secondary · upheld
“the FSP unreasonably delayed settlement of claims”
Subjects and remedies
elderly or capacityhealth or medicalhome or building damagenatural disasterpay compensationpay interestpay non financial loss
Text of the determination
Determination
Case No: 443217 Determination Page 1 of 6
Case number: 443217 29 March 2017
1 Overview
1.1 Dispute
The applicant lodged a claim on her home insurance policy (Policy) held with the
financial services provider (FSP) following a storm on 21 April 2015. The FSP
accepted liability for the resultant damage other than damage to a retailing wall at the
rear of the property which is excluded from cover under the terms of the Policy. The
applicant disputes this decision and says she was misled to believe that the damage
to the retaining wall would be covered.
1.2 Issues and key findings?
Does the Policy provide cover for retaining walls?
There is no dispute that the retaining wall at the rear of the property was damaged.
The Policy is clear. It does not cover damage to retaining walls caused by storm,
flood or accidental damage.
Did the FSP mislead the applicant?
From 13 November 2105 until 18 May 2016 the FSP misled the applicant by stating
that the damage to the retaining wall would be covered under accidental damage. I
am satisfied that the applicant was prejudiced by the misrepresentation and that the
FSP is responsible for repairing the retaining wall but is not responsible for any of the
costs associated with upgrading the drainage.
Is the applicant entitled to compensation for delay and service issues?
The applicant is entitled to $2000 in non-financial loss due to the unreasonable delay
and serious failings in the handling of the claim.
1.3 Determination
This determination is in favour of the applicant. The FSP must within 14 days of the
applicant’s acceptance of this determination:
pay the applicant $2000 in non-financial loss
cash settle the applicant for the retaining wall in the amount of $11,000
pay interest on this amount ($11,000) in accordance with s.57 of the Insurance
Contracts Act from 13 November 2015 which is the date the FSP first accepted
the claim for the retaining wall until the date on which the cash settlement is
made.
Case No: 443217 Determination Page 2 of 6
2 Reasons for determination
2.1 Does the Policy provide cover for retaining walls?
The Policy excludes cover for damage to retaining walls
The Policy covers both insured events and accidental damage.
The terms and conditions of the Policy are set out in the Product Disclosure
Statement (PDS). There is no dispute that the Policy covers damage caused by
storm or flood. The PDS says:
“ If loss or damage is caused by a storm.
Covered
violent wind, cyclone or tornado thunderstorm, hail, rain or snow sudden, excessive run-off of
water as a direct res ult of a storm in your local area. ”
Both the cover for storm and flood damage is subject to exclusions:
“ Not covered under Buildings Insurance loss or damage to:
- retaining walls …”
The applicant also had accidental damage cover. This cover is also subject to
exclusions:
“ You can choose to cover your home and contents for accidental damage …
Not covered
damage to:
- retaining walls ”
There is no dispute that the wall in question is a retaining wall. I am satisfied that the
Policy does not respond to damage to retaining walls, regardless of whether the
damage is caused by storm or flood or accidently.
2.2 Did the FSP mislead the applicant?
The FSP agreed to cover the retaining wall under accidental damage
Based on the information available I am satisfied that the following occurred:
Date Event
21 April 2015 Storm event
22 April 2015 Claim lodged
13 November 2015 FSP tells applicant to make an a dditional c laim for accidental damage to
retaining wall at rear of property. Applicant advised by FSP that retaining
wall will be covered and FSP allocates job to builder to provide scope of
w orks and quote.
26 November 2015 FSP tells applicant still awaiting assessment but wall will be covered ,
however cost to replace/repair drainage will not be covered.
8 December 2015 FSP notes that it has received a cost update from the builders for the
r etaining wall of $8,360.00. FSP calls applicant who advises that she has
been told bui lder will repair wall but not drainage. FSP to confirm.
11 December 2015 FSP advises applicant repairs to retaining wall cost $8.360. Builder will not
Case No: 443217 Determination Page 3 of 6
warrant repair therefore will be cash settling claim.
14 December 2015 Claim file not e that FSP has released claim.
18 December 2015 Applicant advised FSP able to settle claim for wall for $8,360 . Applicant
advis es FSP that she has a quote to repair for $19,000. FSP re views claim
on which $8,360 has been paid and offers to increase this amount to
$10,640 (additional $2,280 to go towards retaining wall ).
29 February 2016 FSP leaves message for applicant. Claim not e that claim to be cash settled
for $8,360 and excess wai ved. Applicant advised that she will be cash
settled $8,360 for the retaining wall and the excess will not be charged.
Applicant accepts $8,360 for retaining wall but is dissatisfied with outcome.
1 March 2016 Payment of $8,360 to applicant.
2 March 201 6 Builder agrees to do works but with no guarant ee. (The FSP believes the
builder is referring to retaining wall when in fact he is referring to the front
masonry wall).
2 March 2016 Letter from FSP to a pplicant confirmin g would accept ret aining wall claim
as identified by the claim number , but no warranty due to ground
movement and drainage issues.
8 March 2016 FSP advises applicant that file to be referred to builder so payment to be
returned.
10 March 2016 Letter from FSP to applicant in relation to claim explaining that claim had
been cash settled , however repairs to be completed by builder therefore
request return of cash settlement.
15 March 2016 Letter from FSP to applicant in relation to claim explaining that claim had
been cash settled for $8, 360.00 however repairs to be completed by
builder request return of $8,360.00.
24 March 2016 FSP calls builder who says will not do work as retaining wall not built to
code and could cost another $30K so even if applicant waives warranty will
not do w ork.
28 March 2016 Claim note says builder has agreed SOW with insured. Builder advises
allocating trades to start work.
13 April 2016 Applicant ret urns money.
5 May 2016 Builder advises FSP will not repair retaining wall. Builder has completed
SOW for masonry wall and driveway gate. FSP calls applicant to advise
builder will not be repairing retaining wall as not covered in the SOW.
Claim note reflects that FSP now aware that there has been confusion
between repair of masonry wall at the front of the property and the retaining
wall at the back.
18 May 2016 Applicant is advised no cover for retaining wall.
The applicant says that the FSP should repair the retaining wall or pay for it to be
repaired because it agreed to do so.
Case No: 443217 Determination Page 4 of 6
The applicant has been prejudiced by the misrepresentation
The FSP says that as the applicant did not suffer any financial prejudice as a result of
the misrepresentation, it is not obligated to compensate the applicant or to repair the
retaining wall.
I accept that the applicant did not pay for the retaining wall to be repaired before the
decision to accept the claim was overturned. I am not satisfied, however, that the
applicant did not rely, to her detriment, on the misrepresentation.
The applicant says:
that she organized to have a quote for the work prepared
she has not been able to progress any work to rectify drainage issues or repair
the wall
she has had to follow up progress on the claim for the retaining wall on
numerous occasions at a time when her husband’s health was poor.
The applicant says on 18 December 2015 at the request of the FSP she received a
preliminary quote for repairs to the retaining wall for $19,000. Her contractor noted
that more work may be needed upon removal of the existing wall.
To date the FSP has never obtained a costing for the retaining wall. The quote of
$8,360 was in fact for the front masonry wall. However, the FSP’s builder advised
the FSP on 24 March 2016 that the repair of the retaining wall could cost “ another
$30,000 ” . The FSP then reversed its decision to cover the retaining wall and declined
the claim on 5 May 2016. It advised the applicant of this decision on 18 May 2016.
Based on the limited information available I am satisfied that the condition of the
retaining wall deteriorated during the period the FSP agreed to cover the retaining
wall. It is therefore fair in all the circumstances that the FSP cover the cost difference
of repairing the retaining wall to compensate the applicant for any additional damage
that has been caused by the delay in work commencing. Based on the verbal quotes
I am satisfied that this cost is $11,000.
The FSP is not responsible for the cost of any drainage work required.
2.3 Is the applicant entitled to compensation for delay and service
issues?
FOS may award compensation for non-financial losses
Under the Terms of Reference, FOS may award compensation (capped at $3,000)
for non-financial loss where an applicant has suffered an unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
Where an insurer has failed to promptly progress an applicant’s claim, FOS may
award compensation for non-financial loss. The applicant told FOS that she feels the
FSP have taken too long in settling the claim and inconvenienced her by requesting
she get a quote for the retaining wall.
Case No: 443217 Determination Page 5 of 6
Policy exclusion does not preclude award of compensation
The applicant’s policy excludes cover for stress. It says it will not pay:
“ compensation for distress, inconvenience or other non financial loss, except if
covered under liability cover”
However, this exclusion does not preclude the award of compensation where such
losses have occurred as a result of the way in which the FSP handled the applicant’s
claim, rather than having been caused by the insured event itself.
The FSP unreasonably delayed settlement of claims
All claims in respect of storm damage were lodged between April 2015 and
November 2015. Based on the claim notes the repairs that were authorised were not
completed until mid-2016. The exact dates of when the work covered by the scope
of works was completed are unknown.
Whilst I acknowledge that not all of the delays can be attributed to the FSP as there
appears to have been some delay in the manufacturing of the gates and organising
trades, I am satisfied that the applicant has suffered stress and inconvenience
caused by the unreasonable delays attributable to the FSP.
For example from the information provided it appears that the claim for the front
masonry wall and gate was lodged in November 2015. The work was not completed
until sometime between then and May 2016 as illustrated below:
Claim Cash Settled/Repaired Date
Fences Cash settled $1,625.00
($1,925.00 less $300 excess)
18 June 2015
Pergola
Clothes line
Rear door
Laundry wall
Cash settled $8,360.00 1 March 2016
Front porch
(masonry wall)
Driveway gate
Removal of waste
Cash settlement of $8,360.00 reversed
and work done by FSP repairer
FSP confirms work completed
and builder paid in October 2016
The handling of the claim fell below expected standards
I t is clear from the builder’s reports that the retaining wall was never contemplated in
the scope of works. The report dated 25 June 2015 clearly lists the retaining wall
under the heading of maintenance and defect issues.
It is unclear how the FSP progressed a claim for the retaining wall when its own
builder had never included it in any of the scope of works. Despite this the applicant
was encouraged to lodge an additional claim for accidental damage to cover the
retaining wall in November 2015.
Case No: 443217 Determination Page 6 of 6
The FSP was aware that the applicant and her husband (Mr T) are elderly and Mr T
is in ill health requiring hospitalisation. The stress and inconvenience associated with
the poor handling of this claim was therefore exacerbated by the applicant ’ s
circumstances.
It is therefore fair in all the circumstances that the FSP pay the applicant $2000 in
non-financial loss.
Based on information provided all other aspects of claim have been resolved
The applicant is concerned that not all of the work covered under the Policy has been
cash settled or completed. In particular she does not think that the work to the
masonry wall and gate was worth $8,360. There is no evidence to substantiate this
claim. I am satisfied that the FSP has discharged its duty under the Policy in having
the work completed.
Having considered the claim notes, the expert reports and the list of payments, I am
satisfied that the claims except for the retaining wall have been finalised, and the
FSP need not take any further action in relation to these works.