Home / Financial Firm (Unknown - Credit) / Determination 441784

Determination 441784

Delay in loan settlement causing applicants' financial loss

FirmFinancial Firm (Unknown - Credit)
Decided2016-11-24
ProductCredit · Other credit
OutcomeFor the complainant in part
Amount awarded$2,544
Non-financial loss$3,000
Amount claimed$8,288
SourceAFCA PDF

Summary

The applicants said the FSP delayed their home loan settlement and cost them money. AFCA found the FSP partly responsible for the delay and for an incorrect settlement shortfall, reduced direct loss by 20% for the applicants' late contract, and ordered $5,000 in total including $1,500 non-financial loss each.

A lender that knows settlement is near must complete settlement steps promptly, and compensation is reduced for the consumer's contribution to the delay.

Issues

Subjects and remedies

pay compensationpay non financial loss

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 441784 Determination Page 1 of 4 Case number: 441784 16 November 2016 1 Overview 1.1 Dispute This dispute is about whether the FSP delayed a settlement causing the applicants to suffer a loss. 1.2 Issues and key findings Did the FSP cause a delay in settlement? While the settlement occurred within three weeks of the FSP granting loan approval, the FSP should have done some things early, rather than at the last minute. If it had done so, settlement may not have been delayed. The applicants contributed to the delay by providing the loan contract to the FSP because they could have given the sale contract to the FSP earlier. Are the applicants entitled to compensation? The applicants are entitled to compensation, but it should be red uced to take into account the applicants ’ contribution to the delay. 1.3 Determination This determination is substantially in favour of the applicant. The FSP should pay to the applicants the sum of $5,000 to an account nominated by the applicants. Case No: 441784 Determination Page 2 of 4 2 Reasons for determination 2.1 Did the FSP cause a delay in settlement? The contract was signed in January and the loan approved on 1 March The applicants signed a contract of sale for the purchase of a property on 9 January 2016, which was subject to finance approval b y 27 January 2016. The date for loan approval and the date for settlement were extended several times, before the purchase finally settled on 22 March 2016. The applicants provided the sale contract to the FSP on 24 February 2016 and the FSP approved the loan on 1 March 2016 after Mr Applicant had provided information about his work history. The applicants attended the FSP branch and signed the documents on the same day. The FSP contributed to the delay in settlement The FSP knew that settlement had been delayed until 17 March 2016. However, the required documents were not reviewed by the FSP’s settlement agent until 17 March 2016. It was on the 17 th or 18 th of March that the FSP incorrectly calculated the amount required to settle. The FSP advised the applicants that settlement could not proceed when re-scheduled to 18 March 2016 because the applicants were $18,110 short. In fact, after further clarification it turned out that the applicants were only $3,239.96 short. When the applicants were told of this, they borrowed funds from family members and settlement proceeded on 22 March 2016. In my view, given that the FSP knew it was working towards an early settlement it should not have left the assessment of the amount required to the last minute. Further when that assessment was done, it was wrong. Had the assessment been done even a few days earlier than the day of the settlement, the applicants could have clarified the amount required to pay and make that payment without the need to delay the settlement planned for 18 March 2016. As the FSP could have referred the required documents to its settlement agent earlier, or if the settlement agent reviewed the documents earlier than the day of or just before the date of settlement, then it is more likely than not that settlement could have proceeded on 18 March 2016. The FSP therefore is responsible in part for the the delayed settlement. The applicants should also accept some responsibility for the delay As noted above, the applicants were in possession of the purchase contract in January but did not provide it to the FSP until late February. In this case, the contract was complex. It was around 113 pages long and involved a Head Transfer from the initial owner to a builder, as well as the Transfer from the builder to the Applicants. There was a purchaser’s caveat on title lodged by the vendor builder, not disclosed in the contract. If the contract had been provided earlier, the FSP would have had more time to address some of these complexities. I am therefore of the view that the applicants Case No: 441784 Determination Page 3 of 4 should accept some responsibility for the delay in settlement because they did not provide the purchase contract to the FSP earlier than 24 February 2016. 2.2 Are the applicants entitled to compensation? The applicants have claimed a loss of $8,288.34 made up as follows: Item Amount $ Vendor conveyancer penalty charges 1,889. 07 Purchaser conveyancer penalty charges 1,050 Discrepancies difference occurred by the bank 2,198. 33 University units drop 1,407. 60 Rent charges occurred as a res ult of Settlement delay 8 days 384 Food (Take away ) 640 Unex pected (phone/internet) expenses 74.34 Two days of work hours lost 2 days 560 Petrol use 85 The Statement of Adjustments show that the additional penalties imposed by the vendor for late settlement total only $1,330.36. The balance of adjustments relate to matters that would have been adjusted or would have been payable regardless of when settlement occurred. As settlement was re-scheduled for 18 March 2016 at no cost to the applicants, I consider that five days additional rental (a total of $240) is appropriate. The applicants’ solicitor has confirmed they charged an additional $1,050 as a resul t of the delay. The applicants had to take time off to see their solicitor to get an understanding of the incorrect stamp duty calculation. The FSP should therefore pay two days of lost work of $560. In my view the applicants are not entitled to compensation for lost work, petrol, phone and internet, take away food or lost university fees. The petrol, phone and food were ordinary expenses that were not caused by the delay. Nor was the applicants’ decision to drop out of University. In relation to the discrepancy claim, I am satisfied that all money provided by the FSP has been properly accounted for. The applicants have not suffered a loss as a result. The total amount of direct loss that I think the applicants are entitled to is $3,180.36. Case No: 441784 Determination Page 4 of 4 The FSP should pay non-financial loss In my view the FSP should pay the applicants $1,500 each for non-financial loss due to the stress and inconvenience of having to sort out the incorrect assessment of the shortfall at the last minute. The compensation should be reduced by 20% The total amount of compensation due to the applicants is $6,180.36. In my view it is fair and reasonable in all the circumstances for this to be reduced by 20% to take into account that the applicants did not provide a copy of the contract of sale until late February 2016, thus contributing to the short time frame in which settlement needed to be achieved. The FSP should bear the lion’s share because it should be used to dealing with complex purchase contracts, even in a shortened timeframe. The FSP should pay $5,000 The total amount of compensation to be paid by the FSP to the applicants is therefore $4,944.29. I have rounded this up to $5,000 to take into account interest. If the applicants’ accept this Determination, the FSP is to pay to an account nominated by the applicants so that they can use the funds to pay the outstanding solicitors’ fees.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.