Home / Financial Firm (Unknown - Credit) / Determination 441784
Determination 441784
Delay in loan settlement causing applicants' financial loss
Summary
The applicants said the FSP delayed their home loan settlement and cost them money. AFCA found the FSP partly responsible for the delay and for an incorrect settlement shortfall, reduced direct loss by 20% for the applicants' late contract, and ordered $5,000 in total including $1,500 non-financial loss each.
A lender that knows settlement is near must complete settlement steps promptly, and compensation is reduced for the consumer's contribution to the delay.
Issues
- Delay primary · upheld
“The FSP should have done some things early, rather than at the last minute... The FSP therefore is responsible in part for the delayed settlement.”
- Administrative error secondary · upheld
“It was on the 17th or 18th of March that the FSP incorrectly calculated the amount required to settle.”
Subjects and remedies
pay compensationpay non financial loss
Text of the determination
Determination
Case No: 441784 Determination Page 1 of 4
Case number: 441784 16 November 2016
1 Overview
1.1 Dispute
This dispute is about whether the FSP delayed a settlement causing the applicants to
suffer a loss.
1.2 Issues and key findings
Did the FSP cause a delay in settlement?
While the settlement occurred within three weeks of the FSP granting loan approval,
the FSP should have done some things early, rather than at the last minute. If it had
done so, settlement may not have been delayed. The applicants contributed to the
delay by providing the loan contract to the FSP because they could have given the
sale contract to the FSP earlier.
Are the applicants entitled to compensation?
The applicants are entitled to compensation, but it should be red uced to take into
account the applicants ’ contribution to the delay.
1.3 Determination
This determination is substantially in favour of the applicant.
The FSP should pay to the applicants the sum of $5,000 to an account nominated by
the applicants.
Case No: 441784 Determination Page 2 of 4
2 Reasons for determination
2.1 Did the FSP cause a delay in settlement?
The contract was signed in January and the loan approved on 1 March
The applicants signed a contract of sale for the purchase of a property on 9 January
2016, which was subject to finance approval b y 27 January 2016. The date for loan
approval and the date for settlement were extended several times, before the
purchase finally settled on 22 March 2016.
The applicants provided the sale contract to the FSP on 24 February 2016 and the
FSP approved the loan on 1 March 2016 after Mr Applicant had provided information
about his work history. The applicants attended the FSP branch and signed the
documents on the same day.
The FSP contributed to the delay in settlement
The FSP knew that settlement had been delayed until 17 March 2016. However, the
required documents were not reviewed by the FSP’s settlement agent until 17 March
2016. It was on the 17 th or 18 th of March that the FSP incorrectly calculated the
amount required to settle. The FSP advised the applicants that settlement could not
proceed when re-scheduled to 18 March 2016 because the applicants were $18,110
short. In fact, after further clarification it turned out that the applicants were only
$3,239.96 short. When the applicants were told of this, they borrowed funds from
family members and settlement proceeded on 22 March 2016.
In my view, given that the FSP knew it was working towards an early settlement it
should not have left the assessment of the amount required to the last minute.
Further when that assessment was done, it was wrong. Had the assessment been
done even a few days earlier than the day of the settlement, the applicants could
have clarified the amount required to pay and make that payment without the need to
delay the settlement planned for 18 March 2016.
As the FSP could have referred the required documents to its settlement agent
earlier, or if the settlement agent reviewed the documents earlier than the day of or
just before the date of settlement, then it is more likely than not that settlement could
have proceeded on 18 March 2016. The FSP therefore is responsible in part for the
the delayed settlement.
The applicants should also accept some responsibility for the delay
As noted above, the applicants were in possession of the purchase contract in
January but did not provide it to the FSP until late February. In this case, the
contract was complex. It was around 113 pages long and involved a Head Transfer
from the initial owner to a builder, as well as the Transfer from the builder to the
Applicants. There was a purchaser’s caveat on title lodged by the vendor builder, not
disclosed in the contract.
If the contract had been provided earlier, the FSP would have had more time to
address some of these complexities. I am therefore of the view that the applicants
Case No: 441784 Determination Page 3 of 4
should accept some responsibility for the delay in settlement because they did not
provide the purchase contract to the FSP earlier than 24 February 2016.
2.2 Are the applicants entitled to compensation?
The applicants have claimed a loss of $8,288.34 made up as follows:
Item Amount $
Vendor conveyancer penalty charges 1,889. 07
Purchaser conveyancer penalty charges 1,050
Discrepancies difference occurred by the bank 2,198. 33
University units drop 1,407. 60
Rent charges occurred as a res ult of Settlement delay 8 days 384
Food (Take away ) 640
Unex pected (phone/internet) expenses 74.34
Two days of work hours lost 2 days 560
Petrol use 85
The Statement of Adjustments show that the additional penalties imposed by the
vendor for late settlement total only $1,330.36. The balance of adjustments relate to
matters that would have been adjusted or would have been payable regardless of
when settlement occurred.
As settlement was re-scheduled for 18 March 2016 at no cost to the applicants, I
consider that five days additional rental (a total of $240) is appropriate.
The applicants’ solicitor has confirmed they charged an additional $1,050 as a resul t
of the delay. The applicants had to take time off to see their solicitor to get an
understanding of the incorrect stamp duty calculation. The FSP should therefore pay
two days of lost work of $560.
In my view the applicants are not entitled to compensation for lost work, petrol, phone
and internet, take away food or lost university fees. The petrol, phone and food were
ordinary expenses that were not caused by the delay. Nor was the applicants’
decision to drop out of University.
In relation to the discrepancy claim, I am satisfied that all money provided by the FSP
has been properly accounted for. The applicants have not suffered a loss as a result.
The total amount of direct loss that I think the applicants are entitled to is $3,180.36.
Case No: 441784 Determination Page 4 of 4
The FSP should pay non-financial loss
In my view the FSP should pay the applicants $1,500 each for non-financial loss due
to the stress and inconvenience of having to sort out the incorrect assessment of the
shortfall at the last minute.
The compensation should be reduced by 20%
The total amount of compensation due to the applicants is $6,180.36. In my view it is
fair and reasonable in all the circumstances for this to be reduced by 20% to take into
account that the applicants did not provide a copy of the contract of sale until late
February 2016, thus contributing to the short time frame in which settlement needed
to be achieved.
The FSP should bear the lion’s share because it should be used to dealing with
complex purchase contracts, even in a shortened timeframe.
The FSP should pay $5,000
The total amount of compensation to be paid by the FSP to the applicants is
therefore $4,944.29. I have rounded this up to $5,000 to take into account interest.
If the applicants’ accept this Determination, the FSP is to pay to an account
nominated by the applicants so that they can use the funds to pay the outstanding
solicitors’ fees.