Home / Financial Firm (Unknown - Insurer) / Determination 441169

Determination 441169

Scope of tree-damage repairs and quality of completed repairs disputed

FirmFinancial Firm (Unknown - Insurer)
Decided2017-03-14
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$850
Amount claimed—
SourceAFCA PDF

Summary

The applicant's home was damaged by a falling tree and repaired by the FSP, but he disputed the quality of the repairs and additional roofing and guttering work. AFCA ordered the FSP to carry out most of the outstanding works, rejected the claim for two ridge capping sections, and awarded $850 non-financial loss.

The insurer must replace damaged parts with a reasonable equivalent where the original gutter could not be repaired, and must complete outstanding works for damage caused by the insured event.

Issues

Subjects and remedies

home or building damagepay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 441169 Determination Page 1 of 5 Case number: 441169 10 February 2017 1 Overview 1.1 Dispute The applicant’s claim for damage following a tree impact was accepted by his insurer, the financial services provider (FSP). The FSP authorised and completed repairs. However, the applicant has raised concerns about the quality of repairs and other aspects which were not addressed. The FSP has not agreed to address all of the outstanding matters raised by the applicant. 1.2 Issues and key findings What is the extent of the FSP’s liability ? The evidence shows the FSP is liable for these additional works that it has not agreed to:  replace the two gutters with “Jasper” continuous guttering  replace the roofing within the areas set out in the app licant’s diagram that he says were associated with the event  replace damaged tin areas the applicant says was caused by the repairer  replace the capping on the left side of the rear part of the roof Is the applicant entitled to compensation? The applicant is entitled to $850 in non- financial loss. This is because the FSP’s claims handling has resulted in him suffering an undue amount of inconvenience and interference. 1.3 Determination This determination is substantially in favour of the applicant. The FSP is liable for the additional works set out in this Determination. The FSP is to pay $850 in non-financial loss. Case No: 441169 Determination Page 2 of 5 2 Reasons for determination 2.1 What is the extent of the FSP’s liability ? Applicant has provided a diagram setting out the additional works The applicant is seeking for additional works to be completed by the FSP as set out in a submission dated 31 July 2016. During the course of the dispute, the FSP has completed or agreed to various items. This is set out in its email dated 2 November 2016. The outstanding issues it has not agreed to are mostly set out in the applicant’s coloured diagram. These include:  continuous guttering along the back and side walls of the house  Colorbond tin parts of the roof damaged by the tree and not replaced – thi s includes the back part of the roof and partially along its side  Colorbond tin parts damaged by the repairer when replacing a valley  replacing capping along the centre length of the home and the right hand side of the rear triangle roof section I will consider each matter. Guttering is payable There is no dispute that:  prior to the damage, the previous guttering on the two sides in question were one piece  both sides suffered damage  one side was repaired by cutting out the damaged area and replacing it with a different gutter that did not match the existing one  the other gutter will likely require similar replacement according to the FSP’s assessor report dated 21 June 2016 I do not accept the policy entitles the FSP to cut out the damaged section of the gutter and replace it with one that does not match for the following reasons. There is no dispute the guttering was one piece and damaged. Whilst the policy says it will not replace undamaged parts, this is not applicable given the continuous guttering was one part. Further, I do not accept the gutter was repairable given the repairer had to remove the damaged section. Instead, when that necessity arose, the FSP was obliged to replace the part with either the same type or one of a similar standard. The appl icant has referred to “Jasper” continuous guttering that is a reasonable equivalent. The FSP has not disputed this is the case. Accordingly, the FSP is liable to replace the two gutters with “Jasper” continuous guttering. Case No: 441169 Determination Page 3 of 5 Damaged tin areas from the tree not repaired The applicant has highlighted parts of the roof he says were damaged by the tree but not replaced by the FSP. The applicant has provided some photographs in support. The FSP had an expert (SRS) inspect the roof on 8 June 2016. SRS identified at least one roof sheet that was found to be damaged and likely associated with the impact. SRS does not comment on other sheets the applicants says require replacement. Neither has the FSP addressed this issue despite having had an opportunity to do so. The photographs do not clearly illustrate the dents referred to by the applicant. However, given the extent of damage and repairs undertaken, the applicant’s position is plausible on the face of it and unrefuted. Further, it is partially supported by SRS where one part of the roof was damaged and not addressed. Given this, I consider it is fair in all the circumstances to accept the applicant’s position about the areas of the roof that require replacement. Accordingly, the FSP is liable for this cost. Damaged tin areas caused by the repairer The FSP has not commented on this specific issue in its submission. Neither does SRS’s report or the other experts address this The applicant has provided photographs to support his position. There are areas showing dents. The applicant says these were damaged by the repairer when replacing the valley. Given the applicant’s position is supported by photographs and unrefuted by the FSP, I accept the FSP is liable to replace these damaged sections. Ridge capping The applicant sought replacement of three lengths of capping. According to his diagram, two were at the rear roof that border a triangular section. The third was a centre capping that starts at the point these two capping meet and proceeds towards the front of the house. SRS’s report confirms the capping on the left side of the rear roof was damaged. This supports the applicant’s position and therefore should be replaced. There is no evidence supporting the applicant’s argument about the right or centre capping having damage. No photographs of these sections have been provided to support his position that they were damaged. The FSP’s reports and photographs provide no evidence of these sections of the home being damaged. Given this, I cannot be satisfied the evidence shows they were damaged from the event. Case No: 441169 Determination Page 4 of 5 The extent of the FSP’s liability Accordingly, after careful consideration of all the evidence, I am satisfied the FSP is liable to undertake the works it has agreed to as well as those set out in this decision. The FSP is to undertake these works urgently given the applicant has sold the house and settlement is due shortly. If it is not possible or feasible for the FSP to complete the works within the timeframe, then the dispute should be resolved on the following basis:  the applicant is to obtain a quote for the outstanding works set out in this decision, and  the FSP is to pay the applicant the amount set out in the quote within 14 days of receipt of same unless it can establish the amount sought is unreasonable. By way of clarity, unreasonable does not mean the most economical. In order for the FSP to say the quote is unreasonable, it must establish it is extravagant or excessive. 2.2 Is the applicant entitled to compensation? FOS awards non-financial loss conservatively The applicant has complained about the delay in settling this claim and the effect it has had on him. Under paragraph 9.3(b)(i) of FOS’s Terms of Reference, I can award up to $3,000 for non-financial loss if the applicant suffered an unusual degree or extent of:  physical inconvenience;  time taken to resolve the situation; or  interference with the applicant’s expectation of enjoyment or peace of mind. Such an award can be provided if the FSP’s handling of the claim causes any of the above. Any award of compensation linked to the degree or extent suffered Any amount of compensation awarded by FOS is normally linked to the degree or extent suffered. That is, the more extreme the circumstances experienced by an applicant that is caused by the FSP, the higher the amount to be awarded. For instance, a maximum award may be provided when a person is sustaining severe financial hardship due to:  their home being substantively damaged,  the repairs having been prolonged for years, and  the person having to pay for both alternative accommodation and the mortgage to their home whilst pursuing a dispute. Case No: 441169 Determination Page 5 of 5 Applicant’s situation satisfies the criteria I am satisfied the applicant has suffered an unusual degree of physical inconvenience, time taken to resolve the situation and interference. This is supported by the following:  the claim was lodged on 16 January 2016 and the excess paid the following day  the FSP has accepted that to date, being more than a year later, there are outstanding issues yet to be rectified  evidence shows additional damage was caused by the FSP’s contractor  the extent of damage from the insured event was not completely identified I also note that the applicant is elderly and his health has deteriorated over the course of the claim. Whilst the evidence does not show his deterioration was caused by the FSP’s conduct, I accept the impact of the above factors would have been more extensive to him as a result of his personal situation. In context of all this, and given FOS’s conservative approach, I accept it is fair in all the circumstances that an award of $850 for non-financial loss be allowed.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.