Determination 440347
Lengthy unexplained delays in completing repairs after a leaking bath claim
Summary
A landlord's bath leak claim accepted by the FSP had repairs still incomplete 11 months after lodgement, and she sought expenses and compensation. AFCA found the delays unreasonable and unexplained, ordered completion of repairs within 14 days, a $1,500 non-financial loss payment, and assessment of a damaged vacuum cleaner, but refused reimbursement of interstate flights.
Unreasonable and unexplained delay in completing accepted repairs can warrant non-financial loss compensation where it causes significant stress and interference with peace of mind.
Issues
- Delay primary · upheld
“There were lengthy and unexplained delays in completing repairs; the FSP has not provided any explanation as to the cause of such lengthy delays.”
- Claim amount dispute secondary · not upheld
“I am not satisfied the cost of flights was an expense incurred in the applicant's capacity as a landlord.”
- Repairs or contractors secondary · unclear
“The FSP is required to assess the alleged damage to the vacuum cleaner and if it was caused by the repairers, the FSP is liable to repair or replace it.”
Subjects and remedies
home or building damagepay non financial lossrepair or rectify
Text of the determination
Determination
Case No: 440347 Determination Page 1 of 4
Case number: 440347 28 November 2016
1 Overview
1.1 Dispute
In December 2015, the applicant lodged a claim on her Landlord Insurance Policy in
relation to damage to her property caused by a leaking bath waste outlet.
The FSP accepted the claim. However, a dispute arose due to lengthy delays in the
repair process. The repairs had still not been completed 11 months later.
The Applicant is seeking reimbursement of expenses she incurred and compensation
for stress and inconvenience, as a result of the delays in repairing her property.
1.2 Issues and key findings
Is the applicant entitled to compensation?
The Applicant is entitled to compensation for non-financial loss in the amount of
$1500. Lengthy and unexplained delays in completing the repairs caused the
applicant a significant amount of inconvenience, stress and interference with her
peace of mind.
Is the FSP liable for other costs sought by the applicant?
The FSP is required to assess the alleged damage to the vacuum cleaner and if it
was caused by the repairers, the FSP is liable to repair or replace it.
The FSP is not obliged to reimburse the cost of airline tickets for the applicant’s son
(and tenant) as I am not satisfied it was an expense the applicant incurred in her
capacity as a landlord.
1.3 Determination
This Determination is in substantially in favour of the applicant. The FSP is required
to:
Ensure the repairs are fully completed within 14 days of the applicant accepting
this Determination.
Pay the Applicant $1500 in compensation.
A ssess the damage to the applicant’s vacuum cleaner , and if caused by the
repairers then repair or replace it.
Case No: 440347 Determination Page 2 of 4
2 Reasons for determination
2.1 Is the applicant entitled to compensation?
There were lengthy and unexplained delays in completing repairs
The applicant lodged the claim on 12 December 2015 and as at the time this
Determination was prepared (25 November 2016), repairs had still not been
completed.
I have reviewed the FSP's claim notes and the timelines provided by the applicant
(which the FSP has not disputed). Below is a brief chronology of the repair process
during 2016:
Date Action
11 Feb Cleaning and restoration works commence.
17 Feb Clearance certificate provided to FSP and builder appointed.
20 April Builder advised work order had been prepared and the job had an
estimated completion date of 13 May 2016.
8 May Work had not commenced. Applicant asked FSP to follow up.
26 May Work had not commenced. Applicant asked FSP to follow up.
Builder advised repairs would be completed in two weeks.
1 June Work had still not commenced. Applicant says builder told her his
tradesman had got mixed up and started work on a different house.
29 June Repairs started but not completed.
28 Aug Repairs still not completed. The shower, bath and walls had not
been sealed, there were large holes in the wall of the spare
bedroom and joins in the plastering had not been covered.There
was a lot of rubbish in front of the house which the builder had not
yet removed.
25 Nov Repairs still not complete. Mirror and towel rail still to be installed.
The chronology above indicates that a repair job which was estimated to take 3
weeks was still not completed after 11 months. The FSP has not provided any
explanation as to the cause of such lengthy delays in the repair process.
Non-financial loss compensation is warranted
FOS may consider awarding compensation for non-financial loss where there has
been an unusual extent of physical inconvenience, time taken to resolve the situation
or interference with an Applicant’s expectation of enjoyment or peace of mind.
The FSP's claim notes indicate that from an early stage the applicant expressed how
important it was to her that the works be completed as soon as possible. Her son
and his wife and baby had been living in the house and had been forced to relocate
as a result of the repairs.
They had been unable to find temporary accommodation all together and the wife
and baby had to move interstate to stay with relatives whilst the repairs were
Case No: 440347 Determination Page 3 of 4
ongoing. The applicant had incurred the cost of several airline flights for her son to
visit his family interstate.
The applicant called the FSP several times enquiring about when the repairs would
commence and their subsequent delays. The FSP agreed to follow up with the
builder but little or no progress was made. Six months after the claim was lodged the
repairs were finally commenced. Eleven months after the claim was lodged they had
still not been completed.
There has been no attempt by the FSP to explain what caused such lengthy delays
and based on the material provided, little action was taken to address the issue and
ensure that the work was completed promptly. On that basis, I consider the lengthy
delays to be unreasonable and the FSP's handling of the applicant’s claim to be poor.
The applicant (and her family) have clearly suffered a significant amount of stress,
inconvenience and interference with peace of mind as a result of the way in which
the claim has been managed.
I am satisfied the applicant is entitled to an award of $1500 in compensation.
Onus is on the Applicant to ensure suitable insurance cover
The applicant submits that she should have been sold a home insurance policy
rather than a landlord policy as her son was living in the property and acting as a
caretaker.
However, the legal onus is on the applicant to ensure the cover she selects is
suitable for her needs. The Applicant received the Product Disclosure Statement and
chose to maintain the policy. Therefore, she is bound by its terms and conditions.
Dyson vacuum cleaner
The applicant says the repairers damaged her Dyson vacuum cleaner by using it to
vacuum up wet plaster. The FSP is required to assess the alleged damage to the
vacuum cleaner and if it was caused by the repairers, the FSP is liable to repair or
replace it.
Cost of airline flights
The FSP paid the applicant for the loss of rent she incurred during the period of the
repairs. However, that payment was only minimal as the applicant had been leasing
the house to her son and his family at a rate far lower than the market value.
The applicant says the FSP made a significant saving as a result of not having to pay
her loss of rent claim at the market value rate. Accordingly, she submits the FSP
should reimburse her for the cost of airline flights she purchased for her son to visit
his wife and child interstate, during the repair process.
Whilst I accept this was a very unfortunate situation for the applicant and her family, I
am not satisfied the cost of flights was an expense incurred in the applicant’s
capacity as a landlord, but rather, a cost she chose to incur to assist her son during a
difficult time.
Case No: 440347 Determination Page 4 of 4
Accordingly, the FSP is not required to reimburse the applicant for the cost of
interstate flights.