Home / Financial Firm (Unknown - Insurer) / Determination 438869
Determination 438869
claim_amount_dispute
Summary
The applicant's accepted strata claim for a damaged cooktop disputed the installation cost, with his builder quoting $6,665.01 against the FSP's $1,950 offer. AFCA preferred the builder's uncontested evidence and ordered the FSP to pay the builder's quote plus the new cooktop, less the $250 excess and any payment already issued.
The only builder who inspected the property supplied unrefuted evidence that the installation works were necessary, and the policy pays the cost to replace without betterment deductions.
Subjects and remedies
home or building damagepay claim
Text of the determination
Determination
Case No: 438869 Determination Page 1 of 3
Case number: 438869 18 November 2016
1 Overview
1.1 Dispute
The applicant’s claim for a damaged cooktop was accepted by the strata insurer, the
financial services provider (FSP).
A dispute has arisen regarding the cost of installation. The applicant is seeking
$6,665.01 based on his builder’s quote (OP). The FSP has offered $1,950 for both
the cooktop and cost of installation.
1.2 Issues and key findings
What is the extent of the FSP’s liability ?
Th e extent of the FSP’s liability is to pay OP’s quote plus the cost of the new cooktop
minus the excess and any payment issued because:
the only builder who has inspected the area and provided an opinion about the
cost of installation is OP
OP has explained why the costs are necessary
OP’s evidence is unrefuted by any expert
1.3 Determination
This determination is in favour of the applicant.
The FSP is liable to pay the balance of:
OP’s quote + new cooktop – excess – any payment already issued
Payment is to be made within 14 days of the applicant accepting this decision.
Case No: 438869 Determination Page 2 of 3
2 Reasons for determination
2.1 What is the extent of the FSP’s liability ?
Parties dispute the cost of installation
There is no dispute that:
the applicant’s cooktop requires replacement
the FSP is liable for the cost of replacement and installation.
The parties dispute the cost of installation.
The applicant says the new cooktop does not fit in the current space. Therefore, the
cost of installing the new cooktop will require replacement of the benchtop and sink.
The FSP has relied on a Good Guys quote ($1,623) which is meant to include the
cost of installation. It also has added $560 for the precautionary cost of removing the
existing cooktop ($500) and a call out fee ($60). These amounts were not based on
any builder quote.
Applicant’s builder says works are necessary for installing cooktop
The applicant’s builder (OP) is the only one who has inspected the property. OP
provided a quotation totalling $6,665.01 for the cost of installation. It does not appear
to include the cost of the cooktop itself as item 17 of OP’s quote noted this would be
supplied by the applicant.
The following information was provided by OP to support the quote:
“The new cook top is a smaller size [supplied by the custo mer] which cannot be fitted into
existing aperture. [Opening]
As this section of the bench is connected to the central section, [sink] therefore all three bench
top section have to be custom made and installed accordingly.
In addition, as all the bench tops are fitted against the wall, the tiles are fixed in such a manner
that they sit onto the benches, this in turn makes it difficult to retain the tiles with-out breakage.
All wall tiles, bench to under overhead cupboard, splash back and side wall need to be removed
and replaced.”
OP provided a subsequent report that said:
“As the secured bench top in question is in a position that requires dismantling of the adjacent
top, i.e. the sink area and break fast return portion of the benc hes. In addition, as these benc h
tops are secured with back splash tiles it may be more than likely the tiles could not be saved,
therefore we have allowed the cost for replacing the said tiles.
The replacement of new tapware is subject to the position and replacement of the sink, as this
will be removed and may not be suitable to be replaced in the most convenient position.”
The FSP has not provided any expert opinion to support its position. Neither has it
inspected the area.
The FSP’s submission is based on the fact that OP’s quot e constitutes a renovation
of the kitchen and would result in betterment. It has also referred to a conversation it
had with the Good Guys who indicated that their quote included installation.
Applicant’s position is preferred
Having carefully reviewed the available information, I prefer the applicant’s position
for the following reasons.
Case No: 438869 Determination Page 3 of 3
First, and of most significance, his position is supported by a builder (OP) who has
inspected the area and provided his expert opinion as to the necessary costs to
installing the cooktop.
Second, OP’s evidence is unrefuted. No other expert has inspected the kitchen or
offered an opinion on this substantive issue. Whilst the Good Guys quote includes
the cost of installation, it is not disputed they did not inspect the kitchen. Therefore,
they cannot refute OP’s evidence as to what works are necessary to install the new
cooktop.
Third, there is nothing in the policy that indicates the FSP can reduce the cost of
installation by any factor that constitutes betterment. Instead, if the evidence
establishes that all these works are necessary as part of the cost of replacement of
the cooktop, then the policy responds.
This is consistent with the policy which says that:
“If Your Insured Property is damaged, We may choose to … pay the amount it would cost to
rebuild, replace or repair.”
FSP liable to pay an additional sum
Given the above, I accept the available evidence demonstrates OP’s quote
represents the costs of installing the new cooktop.
OP’s quote does not appear to include the supply of a new cooktop. If this is the
case, then the cost of the cooktop must be added to OP’s quote.
Having viewed the Good Guys quote, it does say the amount of $1,623 includes the
cost of delivery and installation. It is therefore unclear what the amount would be if
the cost of installation was removed.
Accordingly, I accept the extent of the FSP’s liability for this claim is as follows:
OP’s quote ($6,665.01) + new cooktop – excess ($250) – any payment issued
by the FSP
The FSP is to issue payment of the relevant amount within 14 days of the applicant
accepting this decision.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.