Determination 438457

Storm damage claim for farm shed declined under design and construction defects exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2017-01-09
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's storm claim for a collapsed farm shed was declined under the exclusion for defects in design, structure, materials, workmanship or construction. AFCA found the defects were a proximate cause and that section 46 of the Insurance Contracts Act did not assist her.

Where an insured event and an excluded defect jointly cause the loss and the defect is a proximate cause, the insurer may rely on the exclusion, and section 46 does not apply to an exclusion that is not time-based.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 438457 Determination Page 1 of 5 Case number: 438457 9 January 2017 1 Overview 1.1 Dispute The applicant made a claim under her home building and contents insurance policy with the financial services provider (FSP) when a storm at her property resulted in the total loss of a large farm shed. After receiving a report from a structural engineer, the FSP declined the claim for the shed and its contents, on the basis of the policy exclusion for ‘defects in design, structure, materials, workmanship or construction ’. The applicant does not accept th e FSP’s decision . She believes she took appropriate steps in relation to the design, construction and approvals for the shed. 1.2 Issues and key findings Was there storm damage to the property? The parties agree there was damage to the property from a storm. This is an insured event under the policy. Does an exclusion apply? The policy excludes cover for loss or damage arising from ‘ defects in design, structure, materials, workmanship or construction ’ , and the evidence establishes th ere were defects in the design and installation of the shed . Does section 46 of the Insurance Contracts Act 1984 (the Act) assist the applicant? Section 46 of the Act does not assist the applicant in the circumstances. Is the FSP entitled to decline the claim? The FSP is entitled to decline the claim because the policy exclus ion prevails in this case. 1.3 Determination This determination is in favour of the FSP. The FSP is not required to pay the claim. Case No: 438457 Determination Page 2 of 5 2 Reasons for determination I have decided this case on the basis of what I consider fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties. I am satisfied that the documentation I have relied on has been provided to both parties. For the purposes of this determination, I will deal with only those points considered relevant. 2.1 The damage arose from an insured event The policy covers storm damage, and there is no dispute that the damage to the shed and contents arose from the storm and accompanying winds. The FSP appointed a claims assessor, CL, who confirmed the impact of the storm event. CL recommended engaging a structural engineer, FC, to check that the shed satisfied required building regulations and council approvals. FC’s report found, amongst other things, that the shed design had been based on an incorrect terrain category assessment. That effectively meant that it was not designed (or subsequently built) to adequately withstand the relevant wind speeds or wind pressure. The evidence indicates that had the shed footings been designed in accordance with Australian Standards, the structure should have withstood winds of approximately 140km/h. CL did not consider that any damage they had sighted in the region affected by the storm event had been caused by wind speeds exceeding 102 km per hour. FC ’s report concluded that, as designed, the shed footings would have failed at a wind speed of approximately 70km/h. 2.2 The exclusion applies The proximate cause of the loss was defective design of the shed footings and faulty workmanship in the installation of the concrete piers It is well-established law that a proximate cause is not necessarily the first or last or the sole cause of the loss. It is the effective, dominant or operative cause. The courts have said that if one cause would have resulted in the harm in any case, and the other would not have done so in the absence of the first, then the first is the proximate cause. There may also be circumstances where it is reasonable to conclude that there were two causes which were equal or concurrent in their efficiency in bringing about the damage. If one of those causes was an insured event, and the other an excluded event, then the excluded event would prevail. In this case, I am satisfied that the evidence s hows that the storm would not have resulted in the total loss of the shed (and the contents) if not for the defects in its design and construction – and these defects are a proximate cause of the loss. Case No: 438457 Determination Page 3 of 5 The policy excludes cover for defects in design and construction The policy specifically excludes cover for loss or damage arising from the following: Maintenance and building  defects in design, structure, materials, workmans hip or construction. FC ’s comprehensive and detailed report identifies a number of issues in both the design and construction of the shed which satisfies me that the exclusion applies in this case:  terrain category assessment error and footing design error by SE  shed footing installation defects  inadequate embedment of the tie bars into the concrete  inadequate concrete coverage on tie bars  conical shape of footings resulting in inadequate resistance with surrounding soil. In summary, FC’s review of SE’s structural design revealed ‘crucial errors in the original wind speed assessment and footing design’ , as well as concluding that ‘the shed structure has not been constructed in accordance with the design initially compiled by SE nor good engineering practice’ , in any case. With regard to the construction, FC stated that the se ‘…installation issues represent critical building construction defects which have dramatically reduced the strength and ability of the shed footing piers to resist wind uplift forces. We believe that these issues are principal contributing factors to the wind event related failure of the…shed.’ On the available evidence, I consider it clear that the exclusion for defects in design and construction applies in this case. 2.3 Section 46 does not assist the applicant The applicant has not disputed the FSP’s evidence nor provided anything to challenge the FC report. Instead, she submits she took appropriate steps to ensure the building was erected in accordance with building regulations , and says she could not reasonably have been aware the contractors had not properly completed the designs/construction. This is particularly so, since the building was certified and approved by the relevant local authority. She believes section 46 of the Act applies to assist her . That section precludes the FSP from declining the claim:  on the basis of an exclusion which operates by reference to a defect in a thing  where the defect existed before the policy was taken out Case No: 438457 Determination Page 4 of 5  in circumstances where the insured was not aware (and a reasonable person in the circumstances could not be expected to have been aware) of the defect at that time. However, the policy exclusion in this case is not temporal or time-based; and the courts have confirmed that section 46 only applies to assist the insured in circumstances where the insurer relies on an exclusion which operates by reference to the time at which the relevant defect arose – that is, where the exclusion expressly refers to the defect having been present before the policy was taken out. The exclusion here applies by reference to the subsequent separate event of loss arising from the defect in workmanship or design. It does not apply explicitly by reference to the condition of the shed at a time before the contract of insurance was entered into. That means section 46 does not operate to assist the applicant. 2.4 The FSP is entitled to decline the claim I am satisfied that the cause of the damage was the combination of an insured event (the storm and accompanying winds), and an exclusion (the defects in design and installation). On the available evidence, it is reasonable to conclude that the storm damage would not have occurred if it had not been for the defects which were identified. In these circumstances, it is established law that the FSP is entitled to rely on the exclusion to decline the claim. The applicant has also not established an entitlement to consequential or non- financial loss in the circumstances. I am satisfied the FSP dealt with the claim reasonably and in a timely manner, having regard to the need to engage the external expert engineer, and broadly by reference to the code of practice timeframes. Case No: 438457 Determination Page 5 of 5 3 Supporting information 3.1 Extract from the Act Section 46 Pre-existing defect or imperfection 46(1) This section applies where a claim under a contract of insurance…is made in respect of a loss that occurred as a result, in whole or in part, of a defect or imperfection in a thing. 46(2) Where, at the time the contract was entered into, the insured was not aware of, and a reasonable person in the circumstances could not be expected to be aware of, the defect or imperfection, the insurer may not rely on a provision included in the contract t hat has the effect of limiting or excluding the ins urer’s liability under the contract by reference to the condition, at the time before the contract was entered into, of the thing. 3.2 Policy terms Page Extract 12 General exclusions Your policy does not cover any loss or damage that is caused by or arises from: Maintenance and building  defects in design, structure, materials, workmans hip or construction 20 Insured events Loss or damage caused by storm… 3.3 Experts’ reports Record Key points FSP’s expert ( FC ) Report 7 December 2015  Footings under - designed to safely resist minimum wind load  C ritical building construction defects : s hed not constructed in accordance with the design, or good engineering practice  ‘Even if the footing installation for the shed had been completed strictly in accordance with the SE design, we still believe that the shed would have failed at a wind speed of approximately 70km/h, which is far less than the wind speed of 148 km/hr which the shed should have been able to safely resist’

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.