Home / Financial Firm (Unknown - Insurer) / Determination 437389
Determination 437389
Home insurance claim for cracking damage denied
Summary
The applicant claimed for cracking damage to her home, which she attributed to 2007 council road repairs. The FSP denied the claim and AFCA found the denial was justified.
The applicant could not prove the damage occurred during the policy period, and the expert evidence attributed the damage to excluded settlement.
Issues
- Claim denial primary · not upheld“The FSP was entitled to deny the claim because the applicant has been unable to establish the damage occurred during the period of cover.”
Subjects and remedies
home or building damageno remedy
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 437389 Determination Page 1 of 6
Case number: 437389 8 March 2017
1 Overview
1.1 Dispute
In June 2015, the applicant lodged a claim under a Home Insurance Policy held with
the financial services provider (FSP) until 2011.
The claim relates to cracks discovered at the property in 2014, (or at some earlier
unidentified time) and which the applicant believes were caused by council road
repairs conducted in 2007. She says the repairs included the use of heavy machinery
causing extreme vibrations throughout the property.
The FSP denied the claim on a number of grounds including:
the applicant has been unable to establish a link between the damage claimed
and any roadworks taking place in 2007
the delay in lodging the claim means it is prevented from verifying whether the
damage occurred during the period of cover which ended in 2011
the available evidence suggests the damage is as a result of settlement which,
if occurring during the period of cover, is specifically excluded from cover.
The applicant maintains the road repairs caused the damage and expects the FSP to
honour the claim.
The case manager provided the parties with a recommendation on the issues in
dispute. The recommendation was in favour of the FSP.
The FSP accepted the recommendation, but it was not accepted by the applicant. In
the circumstances, the dispute has been referred to me for determination . A copy of
the recommendation is attached to this determination.
1.2 Issue and key findings
Were the findings of the recommendation correct?
The findings contained in the recommendation were correct and are adopted in this
determination. Further submissions provided after the recommendation have been
considered but make no difference to the outcome.
Was the FSP entitled to deny the claim?
The FSP was entitled to deny the claim because:
the applicant has been unable to establish the damage occurred during the
period of cover and so a valid claim under the policy which expired in 2011
Case No: 437389 Determination Page 2 of 6
even if the applicant could establish the damage occurred during the period of
cover, the expert evidence establishes the damage is a result of settlement,
which is specifically excluded from cover.
1.3 Determination
This determination is in favour of the FSP.
I agree with the case manager‟s reasons for the recommendation and the
recommended outcome.
The FSP is not required to take any further action in relation to the claim or the
dispute.
Case No: 437389 Determination Page 3 of 6
2 Reasons for decision
2.1 Were the findings in the recommendation correct?
The findings in the recommendation were correct
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties.
I am satisfied the case manager‟s recommendation contains an accurate summary of
the dispute, the issues to be determined and any relevant law.
No new material provided after recommendation
After the recommendation was rejected, the applicant made further submissions in
which she essentially reiterated her position. The applicant provided no new material.
The further submissions did not advance the applicant‟s c ase or affect the outcome.
2.2 Was the FSP entitled to deny the claim?
The FSP was entitled to deny the claim
The material provided establishes cracking damage to the insured property. The
applicant‟s policy with the FSP provided cover for such damage. However, the
applicant has not established, on the balance of probabilities, the damage occurred
in 2007 while th e FSP‟s policy was in force. The policy expired in 2011.
The applicant asserts the cracking damage occurred in 2007 but has provided no
proof that council road repairs were undertaken then, that the repairs caused
vibrations and that the vibrations caused the claimed cracking damage to the house.
Whilst I acknowledge the extenuating circumstances which resulted in the applicant
lodging a claim in 2015 (several years after 2007) I accept the delay has prejudiced
the FSP‟s enquiries into whether the FSP‟s p olicy responded to the claim.
The FSP arranged for an engineer to inspect and photograph the property in August
2015.
The applicant criticises the engineer‟s findings. However, she has provided no expert
independent evidence. In the circumstances, I give greater weight to the only expert
evidence which was presented by the FSP.
The only expert material provided to me is the FSP‟s engineer‟s report and
photographs taken after an inspection of the insured property on 28 August 2015.
I have considered the report carefully. It has been summarised in the
recommendation and I am satisfied the case manager has accurately summarised
the engineer‟s opinion. The engineer‟s opinion is comprehensive and the
photographs support the observations made by the engineer.
Case No: 437389 Determination Page 4 of 6
The engineer reported:
“…there is no evidence of vibrational damage to the structure… In fact, the residence is
an exceptionally good condition, with the levels indicating that the cracking is related to
settlement damage of the footings to the north-east and south-west caused by ground
movements .”
Accordingly, even if the applicant was able to establish an insured event occurred
while the FSP was on risk, the material provided establishes the cracking damage
was caused by ground movement which is excluded from cover under the FSP‟s
policy.
In all the circumstances, on the material provided, I am satisfied the FSP is entitled to
deny the claim.
Case No: 437389 Determination Page 5 of 6
3 Supporting information
3.1 FOS Approach
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered for the purposes of this determination.
This dispute has been decided on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
It is an accepted principle of general insurance law that an insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
3.2 Relevant policy extracts
The relevant policy extracts are referred to in the FSP‟s Notice of Response dated
30 August 2016. Both the policy document and the Notice have been exchanged with
the applicant.
3.3 Timeline of key dates
Year Occurrence
April 2007 Council road repairs undertaken proximate to insured property .
After complaint about vibrations, road workers changed to hand held
compactor and vibrations ceased.
Up until June 2011 Applicant caring for husband and mother .
17 November 2011 Cover under the policy ends when the applicant elects to insure with a
different insurer.
Applicant says she noticed the cracking well before 2014 but didn‟t
know what to do about it.
Applicant says the t ree was not removed in 2004 but several years after
the cracking appeared in the house and in the church halls .
2014 - 2015 Applicant identifies the damage in question. She approaches the council
for assistance, but this is declined.
9 June 2015 The applicant lodges a claim with the FSP for cracking damage to
house.
Case No: 437389 Determination Page 6 of 6
Engineer ins pected
premises wit h applicant
28 August 2015
Noted cracking damage.
Dama ge not related to the roadworks.
Damage occurred due to possible tree root drying and the underlying
reactive clay soil .
3.4 Other relevant material considered and relied on
Parties‟ submissions, emails and photographs and all attachments to
submissions.
Correspondence between the parties.
Engineer‟s report and photographs dated 3 September 2015 ( and summarized
in the recommendation).
Recommendation
Case No: 437389 Recommendation Page 1 of 6
Case number: 437389 25 October 2016
4 Overview
4.1 Dispute
In June 2015, the applicant lodged a claim under a home insurance policy held with
the financial services provider (FSP) until 2011.
The claim relates to cracks discovered at the property in 2014, and which the
applicant believes are a result of council road repairs in 2007. She says the repairs
included the use of heavy machinery causing extreme vibrations throughout the
property.
The FSP denied the claim on a number of grounds including:
the applicant has been unable to establish a link between the damage claimed
and any roadworks taking place in 2007
the delay in lodging the claim means it is prevented from verifying whether the
damage occurred during the period of cover which ended in 2011
the available evidence suggests the damage is a result of settlement which, if
occurring during the period of cover, is specifically excluded from cover.
The applicant maintains the road repairs caused the damage and expects the FSP to
honour the claim.
4.2 Issue and key findings
Was the FSP entitled to deny the claim?
The FSP was entitled to deny the claim because:
the applicant has been unable to establish the damage occurred during the
period of cover and so a valid claim under the policy
even if the applicant could establish the damage occurring during the period of
cover, the expert evidence establishes the damage is a result of settlement,
which is specifically excluded from cover.
4.3 Recommendation
This recommendation is in favour of the FSP.
The FSP was entitled to deny the claim and not required to take any further action.
Case No: 437389 Recommendation Page 2 of 6
5 Reasons for recommendation
5.1 Was the FSP entitled to deny the claim?
Initial onus on applicant to establish damage covered under the policy
At insurance law, the initial onus lay with the applicant to establish, on the balance of
probabilities, loss or damage caused by an event covered under the policy.
Further, the onus also lay with the applicant to establish, on the balance of
probabilities, loss or damage occurring whilst the policy was in force, and so prior to
2011.
The applicant‟s policy provided cover for accidental loss or damage, and there is no
dispute the damage now seen is accidental in nature. However, the applicant still
needs to establish this damage occurred during the period of cover.
If the applicant can establish this the onus then passes to the FSP to establish, on
the balance of probabilities, why it may otherwise be entitled to refuse the claim.
Applicant believes the damage occurred in 2007
The applicant believes the damage to the property is a result of the council
undertaking road repairs adjacent to her property in 2007.
She says the repairers used a ride-on compactor which caused extreme vibrations
throughout the property. Having approached the repairers about this, they then
switched to a manual compactor and the vibrations ceased.
There is no dispute a vertical crack approximately 5mm in diameter now extends the
height of one wall, and other smaller cracks throughout the property.
Claim not lodged until 2015
The applicant noticed the internal cracking in or around 2014, but did not think to
approach the FSP until a friend advised her to do so. The applicant says she did not
notice the damage before 2014, as she was focussed on caring for two family
members who have since passed. A timeline of key dates is outlined in section 3.1
of this recommendation.
However, despite the delay in approaching the FSP, it did appoint an engineer to
assess the damage then claimed. Therefore, it becomes necessary to consider the
engineer‟s findings as to whether the damage likely occurred during the period of
cover.
Engineer report concludes damage due to settlement and not vibration
The engineer inspected the property on 28 August 2015. For ease of reference, the
engineering report is summarised in section 3.2.
Relevantly, in relation to whether the damage likely resulted from vibrations and so a
possible link to the road repairs, the report states:
Case No: 437389 Recommendation Page 3 of 6
“However, there is no evidence of vibrational damage to the structure, especially in the
bathroom loc ated on the southern perimeter of the building, which would have been
immediat ely adjacent to any vibrating machinery.”
The engineer concludes the more significant damage, which is confined to one area
of the property, is most likely the result of settlement being caused by:
tree root drying; and/or
settlement of the surface dune sand; and/or
drying out of the reactive clay beneath the dune sand.
The FSP relies upon this report to say there is no identifiable link between any road
repairs taking place in 2007 and the damage now claimed. Moreover the FSP says
the engineer concludes the damage was caused by settlement, which is expressly
excluded from cover.
No expert opinion provided by the applicant
The applicant disagrees with the engineering report for a number of reasons
including:
the engineer did not do any soil tests and when her step father dug at the
property in the past he found limestone, not clay
the tree referred to by the engineer was cut down much more recently than the
road repairs and after the damage identified
the bathroom has since been painted and the cracks referred to by the engineer
repaired at the same time.
The applicant also says the church behind her property suffered damage as a result
of the vibrations. Despite the damage being deemed a result of concrete cancer, no-
one had been inside the church at the relevant time to realise what the true cause
was.
In considering these matters, FOS will give greater weight to expert opinion.
Ultimately, the arguments raised by the applicant do not advance her position. This is
primarily because the applicant‟s arguments are not supported by a relevant expert,
such as a builder or engineer.
Applicant unable to establish the damage occurring during the period of cover
I accept the applicant found herself in distressing circumstances during the relevant
period. I also acknowledge the concerns the applicant has with the engineering
report.
However, the onus still lays with the applicant to establish the damage occurring
during the period of cover. In this instance, I am not satisfied the applicant has met
this onus because:
the damage was not sighted internally until in or around 2014, some three years
after the policy ended and some seven years after the road repairs
the available expert evidence suggests the damage is unrelated to vibrations
during any road repairs
the council‟s own insurer reportedly concluded the damage was u nrelated to
any road repairs in 2007.
Case No: 437389 Recommendation Page 4 of 6
I acknowledge the delay in contacting the FSP has significantly impacted the
applicant‟s ability to establish a valid claim. However, the FSP cannot be held liable
for the challenges now faced by the applicant as a res ult of this delay.
For these reasons, the applicant has been unable to establish the damage occurring
during the period of cover and so a valid claim under the policy.
Therefore, the FSP was entitled to deny any associated indemnity.
Policy excludes damage caused by settlement
For the sake of completeness, even if the applicant were able to establish a valid
claim, the available expert evidence suggests the damage is a result of settlement.
In these circumstances, the FSP would still be entitled to deny indemnity because the
policy specifically excludes damage caused by:
“settling, shrinkage or any movement of earth”
Therefore, even in this hypothetical situation, the overall outcome would remain the
same.
Case No: 437389 Recommendation Page 5 of 6
6 Supporting information
6.1 Timeline of key dates
Year Occurrence
2007 Council road repairs undertaken.
2011 Cover under the policy ends when the applicant elects to insure with a different
insurer.
2014 - 2015 Applicant identifies the damage in question. She approaches the council for
assistance, but this is declined.
2015 The applicant lodges a claim with the FSP.
6.2 Engineering report
Observations
The building was constructed in or around 1903. It is a limestone masonry
structure in very good condition.
The building is built on dune sand overlying reactive clay of moderate to high
reactive properties. The dune sand will consolidate on wetting causing
settlement. If the dune sand is dry, there is potential for the underlying clay to
shrink causing settlement.
The bitumen roadway adjacent to the south-west of the building just west of the
vertical wall cracks suggest settlement is occurring both in the roadway and that
section of the building.
There is a 5mm vertical crack in the rear room identified internally around two
years prior. The crack had been noticed prior to this time, but not immediately
after the road repairs took place.
There is minor internal cracking in other areas of the building.
There is evidence of separation of the timber flooring in the south-western
corner of the building suggesting rotation in this area.
Settlement of between 70mm and 90mm is evident in the northeast and
southwest corners of the building, although limited cracking identified is likely
due to limestone footings on dune sand.
Discussion
Only the external and now internal crack to the southwestern corner of the
property constitutes „cracks noticeable but easily repaired‟ in line with the
associated Australian Standard.
The crack may be due to poor construction of the roadway leading to
consolidation of the dune sand beneath the building and adjacent roadway.
Settlement may also be due to the reactive clay soils drying out during drought
and hot dry summers.
A tree removed in 2004 on adjacent property causing damage to a church may
also have contributed to the cracki ng.
Case No: 437389 Recommendation Page 6 of 6
There is no evidence of any vibrational damage, and particularly in the
bathroom which would have been immediately adjacent to the road repairs.
The building is in exceptionally good condition with settlement in the northeast
and southwest areas indicating settlement damage to the footings.
Conclusion
The damage is not related to the roadworks and possibly due to tree root drying
and the underlying reactive clay soil and/or settlement of the surface dune sand.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.