Flood damage: slab movement declined as structural defect; mould remediation and contents damage

FirmFinancial Firm (Unknown - Insurer)
Decided2017-05-04
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

Owners of a flood-damaged home disputed the insurer's refusal to pay for slab movement and mould damage. AFCA accepted the slab movement was excluded as a structural defect, but found the insurer's failure to dry and remediate the home caused the mould damage, ordering contents and mould works, tile and render costs, and $2,000 non-financial loss.

Where an excluded structural defect and a covered flood are both proximate causes, the exclusion defeats the claim for that damage, while loss flowing from the insurer's failure to complete post-flood works is covered.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 436710 Determination Page 1 of 6 Case number: 436710 28 April 2017 1 Overview 1.1 Dispute The applicants lodged a claim on their Home Building and Contents Policy held with the financial services provider (FSP) after the home was inundated by flood on 26 August 2015. The FSP accepted liability and elected to cash settle the property damage claim for $27,511.77 and contents claim for $28,175. It subsequently offered an additional four weeks accommodation calculated at $360 per night. Dispute now exists as to the extent of damage sustained to the building, in particular the concrete infill slab on the lower level of the property and further mould related damage to contents. 1.2 Issues and key findings Was the damage to the ground floor infill slab caused by the flood event? The FSP is entitled to decline liability for damage arising from the movement of the concrete infill slab. The Panel accepts the flood event caused some further movement in the concrete infill slab, however the proximate cause of the damage is due to a structural defect. Is the ongoing issue with the mould due to the flood event? On the balance of probabilities, the ongoing issue with the mould is related to the flood event and the FSP’s failure to properly dry the concrete infill slab. The FSP is liable to compensate the applicants for the additional damage to contents as set out in section 2.2 of the determination and complete any necessary mould remediation. Are the applicants entitled to compensation for non-financial loss? The applicants are entitled to compensation for non-financial loss of $2,000. 1.3 Determination This determination is partially in favour of the applicants. The FSP is liable to meet the claim for mould remediation and additional damage to contents as per section 2.2 of this determination and pay the applicants $2,000 by way of non-financial compensation pursuant to paragraph 9.3 of the Terms of Reference. The FSP is otherwise entitled to deny liability for damage arising from the movement of the concrete infill slab. Case No: 436710 Determination Page 2 of 6 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. Due to the complexities involved in this dispute, it has been referred to a Panel for determination. The Panel has had access to all information exchanged and has based this determination on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes of practice and prior determinations where applicable. 2.1 Is the FSP liable for damage arising as a result of th e movement of the infill concrete slab? Policy provides flood cover The applicants ’ policy of insurance is an Insured Events Policy that provides cover for both storm and flood damage. Cover under the policy is subject to a number of general exclusions including exclusions relating to:  ‘… subsidence or landslide, rust, corrosion, gradual deterioration, depreciation, wear and tear,  the settling, shrinkage or expansion in buildings, foundation walls or pavements  inherent defects or structural defects.’ Circumstances of loss There is no dispute that the applicants ’ property was inundated by flood waters on or about 26 August 2015. According to the information provided, the property was inundated through the lower level to a peak depth of 480mm and through the upper level of the ground flood to a peak depth of 200m. The applicants deny there was damage to the slab prior to the flood and say that since the flood, there has been movement and cracking of the concrete infill floor slab causing damage to the property. The FSP says that whilst there has been some further movement of the slab following the flood, the proximate or dominant cause of the movement of the concrete infill slab is the inadequate supporting infill material impacting on the structural integrity of the slab. The FSP maintains that this is a structural or inherent defect and therefore excluded from cover. Pre purchase report indicates minor movement. The applicants provided a copy of a pre purchase report dated 28 August 2014 from HC. The sub-floor of the property and slab was not inspected but there was evidence of some minor movement which the applicants say was cosmetic only. Case No: 436710 Determination Page 3 of 6 The report identified evidence of dampness and moisture to the ground floor and considered there was inadequate drainage to the right side of the property. The Panel acknowledges that the applicants completed the drainage repairs in December 2014. Engineering reports identify unsuitable infill material as the cause of the movement TE reported on 14 September 2015 there were wall and skirting cracks and cornice cracking. TE considered a lot of this damage was pre -existing and had been documented in the report from HC. TE concluded that the suitability and compaction of the supporting material under the concrete infill slab was unsuitable. The slab movement was caused by the inadequacy of the floor support fill. TE considered that the settlement had been occurring for some time, but conceded that the situation had been compounded by the flood events. The applicants obtained a report from WP who considered that the inundation of the ground floor slab placed considerable downward load/pressure on the slab which in turn caused the compaction of the fill or natural ground under the slab. WP considered this was the cause of the movement. TE considered this theory as flawed as the flood would have evenly disbursed the pressure across the area over already saturated soil. The applicants also provided a further report from HC. HC concluded in a report dated 14 March 2016 that there was obvious movement and cracking of the concrete infill floor slab that had manifested itself post the flood event. HC considered the possibility of inadequate compaction or suitability of the infill material was plausible but noted the house floor slab had remained static since construction. HC considered it had deviated drastically from its normal location during and after the flood event which has resulted in the settlement and cracking of the property. Further reports were obtained from BH who considered the pre-existing movement prior to the flood and did not believe the movement was due to the flood event whilst TE provided a further report confirming the view that the structural integrity of the slab was inadequate. The Panel has considered the various opinions provided. The Panel does not accept WP’s theory and accepts the majority view that the concrete infill slab was structurally flawed. Proximate cause was the structural defect. The Panel is persuaded based on the information provided that there had been movement in the concrete infill slab prior to the flood event and most likely that was due to inadequate infill material being used under the slab. The Panel accepts that this may have been exacerbated in the flood event. The Panel acknowledges the applicants ’ position however is well established at law that in the event that there are two proximate causes of damage, in this case the inherent defect/structural defect of the slab and the flood, and one of those proximate Case No: 436710 Determination Page 4 of 6 causes is excluded from cover whilst the other is included, the exclusion operates to defeat the claim. In this case, the FSP is entitled to rely on the exclusion relating to the inherent defect/structural defect to deny liability for the additional damage arising from the movement of the concrete infill slab. 2.2 Are the applicants entitled to cover for the mould damage? The ongoing issues with mould relate to the flood. The applicants have reported ongoing issues with mould and sought remediation of those issues since March 2016. It is accepted that that grey water entered into the dividing bedroom walls and wall cavities of the bedrooms during the flood event. The FSP’s initial builder AG noted damage to melamine in the building and wardrobes. The FSP arranged for a company S to clean and disinfect the tiles of the house whilst the engineering consultant identified that wall linings had to be removed and treated for mould growth. The Panel notes that the FSP did not attend to this. A report was commissioned by the FSP and in an email dated 13 April 2016, the FSP’s mould consultant R advised that there was no visible mould detected in the home however contents and clothing were not on site at the time of inspection. R found mould in the drawers in the shed. The applicants arranged for RS to complete a report and this was provided on 5 April 2016. RS identified medium to heavy mould contamination with active mould growth in the contents located in the ground floor bedroom and high moisture levels in the slabs and walls. RS considered that there were inadequate dehumidifiers and air movers installed by the previous restorer (S) and that the FSP had failed to pay attention to the structural drying of the concrete slab after the flood. The Panel accepts that there is some information in particular the pre-purchase report that indicates the property had been subject to high moisture levels and that this may have contributed to the moisture within the home. The Panel notes however that there is no evidence of any mould infestation prior to the flood. The Panel also notes that despite clear information from the FSP’s consultants that the wall lining should have been removed, following the flood, they were not removed and mould treatment was not applied to them. In the Panel’s opinio n, the available evidence supports a finding that the current mould related issues and additional damage to the contents is due to the failure of the FSP to properly complete the works following the initial flood. In the Panel’s view, the report from RS is persuasive that the applicants ’ ongoing mould issues are related to the failure to properly dry the property and remediate any mould contamination at that time including the failure to remove and treat the wall linings after the flood. Case No: 436710 Determination Page 5 of 6 Whilst the policy does not provide cover for mould, the proximate cause of the mould infestation was the flood and subsequent failure of the FSP to apply dehumidifiers and air movers. In the Panel’s view, the proximate cause of the damage is therefore an insured event and the FSP is liable to meet the costs associated with the additional damage to contents and additional mould remediation. Whilst the applicants have provided a list of items, the Panel is not persuaded that the number of items claimed can be established as items damaged. The applicants are asked to provide further proof of loss with respect to the items of clothing claimed and damage to the furniture claimed. The FSP is entitled to cash settle the claim for additional damage to the contents. The FSP should attend to the further mould remediation and any necessary repairs resulting from that process unless the applicants otherwise agree to accept a cash settlement for that work. Additional damage The Panel notes the FSP offered to cash settle the applicants for four weeks accommodation at $360 per night ($10,800) on top of the building damage settlement of $27,511.77. The FSP has suggested this is a good will gesture however the policy provides for temporary accommodation where the applicants are required to vacate the premises during the repair period. The Panel accepts that the applicants would be required to vacate the premises during the repair period and mould remediation. The Panel also notes that RS identified that the ceramic tiles should be removed to allow the concrete slab to dry. The Panel accepts that this is reasonable and accepts that the FSP should cover the cost to remove and replace the ceramic tiles to allow the floor to dry. The FSP is entitled to assess this amount and should include it in any cash settlement. The Panel also notes that WP has identified there was a deterioration of rendered steps which may have increased because of the moisture damaging the bond between the render and sub-strait. The FSP must include the cost to replace these tiles in any cash settlement. The parties are asked to work together cooperatively to resolve the quantum for these outstanding matters. If they are unable to do so, then the matter may be returned to the Service for determination. 2.3 Are the applicants entitled to compensation for non-financial loss? Under paragraph 9.3 of the Terms of Reference, the Service can award compensation for non-financial loss in circumstances where an applicant experiences an unusual degree of physical inconvenience or time taken to resolve a dispute. Whilst the Panel accepts the FSP responded to the applicants ’ initial claim promptly, the FSP did not respond promptly to the applicants ’ concerns with respect to the ongoing issues with mould and mould contamination. Case No: 436710 Determination Page 6 of 6 In the Panel’s view, the failure by the FSP to complete the works recommended by its own consultants following the flood has caused an unusual degree of physical inconvenience and time taken to the applicants . In the Panel’s view, the applicant s are entitled to compensation in these circumstances and the FSP should pay the applicants $2,000 by way of non-financial compensation.