Home / Financial Firm (Unknown - Insurer) / Determination 435427

Determination 435427

Declined floor tile claim after escape of water and scope of works dispute

FirmFinancial Firm (Unknown - Insurer)
Decided2017-05-09
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss$1,500
Amount claimed—
SourceAFCA PDF

Summary

The applicants claimed for flood damage including floor tiles, which the FSP declined under an exclusion. AFCA found the FSP had not established the exclusion, ordered a fresh scope of works and cash settlement, and awarded $1,500 for non-financial loss.

The insurer bears the onus of establishing an exclusion once the applicant has shown a prima facie claim, and it did not discharge that onus for the tiles; its delay in addressing the wider damage also warranted compensation.

Issues

Subjects and remedies

pay non financial lossreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 435427 Determination Page 1 of 6 Case number: 435427 5 May 2017 1 Overview 1.1 Dispute The applicants held a Home and Contents Insurance Policy with the financial services provider (FSP) in November 2015 they lodged a claim after the house was flooded with water. The FSP accepted liability for the claim and authorised the repairs but declined the applicants‟ claim for damage sustained to floor tiling. The applicants dispute the FSP‟s decision to decline the claim for the f loor tiles and disputes the FSP‟s scope of works. 1.2 Issues and key findings Have the applicants established a claim under the terms of the policy? The applicants have established a claim under the terms of the policy as the policy provides cover for loss or damage arising from insured events including the escape of liquids. There is no dispute that the damage was identified at the property following escape of liquid from the mixer tap pipe. Is the FSP entitled to rely upon an exclusion to refuse payment of the claim for damage to the tiles? The FSP‟s reports confirm it is impossible to say if the drumminess is from the leak or from the pre-existing condition. I am not satisfied the FSP has met its onus to establish the application of an exclusion under the terms of cover. Is the FSP required to increase the cash settlement amount? The FSP is required to increase the cash settlement amount in accordance with section 2.3 of this determination. 1.3 Determination This determination is in favour of the applicants. Within 14 days of acceptance of this determination the FSP is required to arrange for a full scope of works to repair the damage sustained to the applicants‟ property, including the likely costs of any mould remediation required, costs to reinstate the tiling and likely costs of temporary accommodation. FSP is then entitled to settle the applicant‟s claim subject to the conditions as set out under section 2.3 of this determination. Case No: 435427 Determination Page 2 of 6 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. This determination is based on what is fair in the circumstances, having regard to the relevant legal principles, terms of the po licy, good industry practice including codes of practice and prior determinations where applicable. 2.1 Has the applicant established a claim within the terms of the policy ? The applicant has established a claim within the terms of the policy The applicants have the onus to establish on the balance of probabilities a claim that falls within the terms of the policy. This is commonly called a prima facie claim. Only once the applicants have established a prima facie claim does the onus shift to the FSP to establish the application of any exclusion. The applicants‟ policy is a Home and Contents Policy providing cover from 11 December 2014 to 11 December 2015, for specified insured events including loss or damage resulting from the bursting, leaking, discharge or overflow of water or liquid from pipes, etc. The onus is therefore on the applicants to establish the loss or damage sustained to the property resulting from the bursting, leaking, discharge or overflow of water or liquid from pipes. There is no dispute tha t on or about 7 November 2015 the applicants‟ house flooded with water when a flexible pipe connected to the mixer tap in the kitchen burst. According to the information provided water covered the entire interior of the property to approximately 120mm. The FSP accepts that this is an insured event under the terms of the policy. FSP has provided a detailed scope of works Although the FSP initially provided a scope of works limiting the damage to the kitchen, it has since provided a far more detailed scope of works that includes the following:  Damage to bedroom 1 including painting and decorating and carpentry.  Damage to bedroom 2 including painting and decorating and carpentry.  Damage to bedroom 3 including painting and decorating and carpentry.  Damage to bedroom 4 including painting and decorating and carpentry.  Damage to dining room including painting and decorating and carpentry.  Damage to ensuite including painting and decorating and carpentry plus plumbing works required and removal and replacement of splash back and ceramic tiles.  Kitchen carpentry including replacement of skirting boards, internal door, electrical, joinery and cabinet making, painting and decorating, plumbing removal and replacement of kitchen splash back. Case No: 435427 Determination Page 3 of 6  Laundry painting and decorating and carpentry.  Bathroom 1 – carpentry and painting and decorating and plumbing.  Hallway – painting and decorating and carpentry.  Living area – painting and decorating and carpentry.  Rumpus area – painting and decorating and carpentry.  Front entry – painting and decorating and carpentry.  Toilet 1 – painting and decorating and carpentry.  Linen cupboard 1 – painting and decorating and carpentry.  Linen cupboard 2 – painting and decorating and carpentry. Whilst the applicant disputes the amount of the settlement offer there is no dispute that damage was sustained to the various areas identified in the scope of works and this is supported by the FSP‟s quote obtained from their builder TB. 2.2 Has the FSP established the application of an exclusion The FSP has the onus if it seeks to limit its liability to establish the application of an exclusion under the terms of the policy. Under the insured event covering the escape of liquids, you are not covered for loss or damage caused by gradual seepage of water, leaking or faulty shower recess or base or an inadequate drainage system. None of these apply in the applicants‟ case. Under the general exclusions contained on page 38 of the policy, cover does not extend to loss or damage resulting from or incurred from or of:  gradual deterioration, including wear and tear, rust, corrosion, depreciation, fading or deterioration from exposure to light;  mould or mildew, wet or dry rot, rising damp or dampness;  inherent defects, structural faults, faulty workmanship or faulty design. The FSP has sought to rely upon inherent defects, structural faults, faulty workmanship or faulty design in the laying of the tiles to exclude cover for the damage sustained to the floor tiling throughout the house. Assessors’ Report The initial assessment report obtained by the FSP followed a site attendance on 9 November 2015. The assessor “ CC ”, noted that damage throughout the applicants‟ property and found the ceramic floor tiles in bathroom 1, the entrance, hallway, kitchen, laundry and toilet were noted to be drummy. According to the report, cleaning and restoration specialists were engaged to remove and dispose of water affected carpets and complete mould remediation/structural drying as required but had not attended at the time of inspection. The mould remediation and structural drying did not occur. The FSP has accepted liability with respect to replacement of the carpets. CC noted in relation to the damages to the floor tiles that: „whilst impossible to confirm, in our opinion it cannot be solely attributed to the flooding that occurred. The tiles have been fixed to the concrete slab substrate using adhesive Case No: 435427 Determination Page 4 of 6 and both the tiles and grout are designed to withstand moisture. Given this advice, the fact that the tiles are drummy suggests the damage is pre-existing or that a pre-existing maintenance/defect issue relating to the glue adhesive having failed prior to the flooding that occurred is a significant contributing factor to the damages that exist.‟ CC estimated the cost to complete the works to repair the floor tiles would be approximately $6,000. CC conducted a reinspection of the property on 14 September 2016. In relation to the causation of the damages to the fl oor tiles. CC‟s recommendation was “unsure”. Engineer’s report from BH BH reported that no dehumidification or other equipment had been used to expedite the building element drying process. He identified abnormally high moisture levels located in the bedrooms, lounge and dining rooms and in the skirtings and xxx locations. Immediate dehumidification was recommended. In relation to the floor tile adhesion failure, BH noted:  adhesive was generally fully spread over the entire back side of the tile and that an approximate equal amount of adhesive was remaining on both the floor tile and the concrete slab floor.  Movement joint did not comply with relevant building requirements and perimeter movement joints should have been inserted.  Floor tile adhesive appeared to be a pre-mixed acrylic and was grey in colour whilst floor tile adhesive recommended for concrete slab substrates use a thin set mortar type adhesive. From his visual assessment, the adhesive did not appear to be the later and therefore was non-compliant. BH considered the floor tile adhesion failure was likely to have been occurring prior to the inundation. I note BH did not have a copy of the pre-purchase inspection report at the time of his assessment. Pre purchase inspection report The applicants‟ deny any issues with the floor tiles prior to the inundation. The applicants provided a copy of a building inspection report and whilst that report did identify an issue with the bathroom sealant and grouting, it did not identify any issues with drumminess in the floor tiles. The building inspection occurred in 2013. An online search relating to adhesives confirms that acrylic based adhesives, whilst suitable for some interior tili ng is not generally regarded as suitable for tiling over concrete or waterproofing membranes. Polymer modified rubber based tile adhesive is suitable and there are some forms of flexible acrylic adhesive that are suitable. The FSP‟s engineer has not commen ted on types of acrylic floor adhesive that may be suitable, nor has the engineer commented on the pre-purchase report. The FSP has not established the exclusion applies As the onus is on the FSP to establish on the balance of probabilities that the exclusion applies. Case No: 435427 Determination Page 5 of 6 I am not satisfied based on the current information provided that the FSP has established on the balance of probabilities that the failure of the floor tile adhesive was due to either gradual deterioration, an inherent defect, faulty workmans hip or faulty design. In the circumstances I am satisfied that the FSP is liable to meet the applicant‟s claim for the damage to the floor tiling. 2.3 Is the FSP’s offer of settlement sufficient? The FSP‟s policy provides the FSP with an option whether to cash settle or repair or rebuild the property. When exercising this such discretion, the discretion must be exercised reasonably and consistent with the principles of utmost good faith and fairness. It is apparent however that the relationship between the FSP and the applicant has irretrievably broken down. The applicants‟ have indicated they would prefer a cash settlement of the dispute and in the circumstances I accept that it is fair and reasonable for the FSP to cash settle the dispute. As indicated under section 2.1 the FSP has offered cash settlement based on damage to the various rooms excluding the tiling. I note the FSP‟s offer does not include replacement of the carpets although the FSP has accepted liability with respect to this. I also note that the offer does not include cost of mould remediation or the dehumidification of the property. It is possible that this is no longer required, however it is fair that this be reassessed. I accept the FSP did make some attempts to attend the applicants‟ prope rty to complete this work although this was sometime after the urgency of the situation was identified by the FSP‟s assessor and engineer. The policy also provides a number of additional benefits including emergency accommodation in the event that you cannot safely reside in the home because of the damage. The FSP offers to pay temporary accommodation whilst the home is being repaired or rebuilt. The FSP has provided no estimate of the likely period that it will take to repair the home nor in its offer of settlement included any offer for temporary accommodation. The policy also includes cover for the cost of contents temporarily removed from the home during repairs. The FSP has not provided any allowance with respect to storage of contents during the relevant repair period. In order to reach a fair and reasonable figure for the cash settlement, the FSP should within 14 days of the applicants‟ acceptance of this determination arrange for to obtain a suitable scope of works to repair all damage identified including the tiling and obtain costings from a relevantly qualified person or persons who would be prepared to do the work in accordance with the scope of works. The FSP should make allowance within the scope of works for the cost of any possible dehumidification or mould remediation, temporary accommodation and contents storage. Case No: 435427 Determination Page 6 of 6 The parties are then asked to work cooperatively together to reach an agreement as to the final cash settlement figure. In the event that the parties are unable to reach agreement then the matter may be returned to the Service for further consideration as to the cash settlement amount. Are the applicants entitled to compensation? Under paragraph 9.3 of the Terms of Reference , the Service may determine that the FSP pay compensation of up to $3,000 for non-financial loss in circumstances where an applicant incurs an unusual degree of physical inconvenience or time taken to resolve the dispute. I accept that there have been substantial issues relating to the assessment of the damage to the floor tiles and that it was reasonable for the FSP to fully investigate this. However, I do not accept the time taken by the FSP to accept the remainder of the damage to the property. The initial scope of works provided by the FSP was limited to damage to the kitchen whilst the FSP did not attend to the dehumidification or mould remediation in a timely manner. By the time it attempted to do so, its relationship with the applicants had broken down. I am satisfied based on the information provided that the applicants have experienced an unusual degree of physical inconvenience and time taken to resolve this dispute. In the circumstances, I determine the FSP should pay the applicants $1,500 compensation for non-financial loss.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.