Storm damage to stormwater pipe and landscaping denied and claim decision delayed
Text of the determination
Determination
Case No: 434733 Determination Page 1 of 9
Case number: 434733 26 July 2017
1 Overview
1.1 Dispute
The applicant is a body corporate for a unit complex located in Brisbane (the
property). The applicant has insured the property under a residential strata insurance
policy (the policy) with the financial services provider (the FSP).
There is no dispute between the parties a severe storm occurred on 27 November
2014.
The applicant made a claim under the policy for damage caused by the storm.
The FSP accepted damage to roof tiles was covered under the policy. However, the
FSP denied damage caused to a storm water pipe and damage to landscaping.
The FSP denied the claim on the basis the concrete thrust block where the storm
water pipe failed was poorly maintained, did not comply with the relevant building
standard and because the damage occurred gradually over time. The FSP also says
the erosion of the river rocks and supporting material and logs and baffles was not
covered u nder the “Landscaping” Additional Benefit in the policy.
The applicant argues the policy responds to the claims and also complains about the
FSP‟s claims handling and the lack of timeliness and provision of certain information.
The case manager provided the parties with a recommendation on the issues in
dispute. The recommendation was substantially in favour of the applicant.
The applicant accepted the recommendation, on certain terms, but as the
recommendation was not accepted by the FSP, the dispute has been referred to me
for determination.
1.2 Issues and key findings
Is the FSP entitled to deny the claim to repair the stormwater pipe?
The material provided establishes on the balance of probabilities a prima facie claim
because the damage to the stormwater pipe was unintended and unexpected and is
therefore covered under the policy which covers accidental damage.
The material provided does not establish on the balance of probabilities the pipe was
damaged because of a building defect. Therefore, the FSP is not entitled to rely on
the policy exclusion to deny the claim.
Case No: 434733 Determination Page 2 of 9
The FSP is not obliged to pay $1,000 for exploratory costs but is to pay to the
applicant $3,500 to repair the stormwater pipe.
Is the FSP entitled to deny the applicant’s claim for the lands caping?
The FSP is not entitled to deny the applicant‟s claim for landscaping as the damage
claimed was accidentally caused. Under an Additional Benefit, the policy provides up
to $10,000 for the reasonable costs necessarily incurred in replacing or repairing
damaged rockwork. The policy also provides an Additional Benefit for the cost of
removal and disposal of debris.
As the material provided establishes there was significant displacement of the
rockwork which was held in place by the wooden structure; the supply and
installation of stones and rocks behind the wooden structure was estimated at
$10,500; and the applicant has not been indemnified pursuant to the Additional
Benefit of removal of debris, it is fair in all the circumstances the FSP pay to the
applicant $10,000 for this part of the applicant‟s claim.
Is the applicant entitled to compensation?
It is fair in the circumstances the FSP pay to the applicant compensation as the FSP
took an unusual amount of time to make a claims decision.
1.3 Determination
This determination is substantially in favour of the applicant.
Should the applicant accept this determination, then within seven days of
acceptance, the FSP is to make the following payments to the applicant:
$3,500 for the claim to repair the storm water pipe
$10,000 being the policy limit for repair or replacement of damaged landscaping
$500 compensation for non-financial loss
The FSP is not otherwise required to take any further action in relation to the claim or
the dispute.
Case No: 434733 Determination Page 3 of 9
2 Reasons for decision
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
recommendation. I am satisfied the documentation I have relied on has been
provided to both parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only
More photographs were provided after the recommendation
After the recommendation was rejected, both parties made further submissions and
the applicant provided photographs. Where appropriate, the submissions are referred
to in the determination.
2.1 Is the FSP is entitled to deny the applicant’s claim to repair the
storm water pipe?
Applicant must establish a prima facie claim
In March 2015, the applicant lodged a claim claiming hail and storm damage as a
result of a storm on 27 November 2014.
The claim relating to the hail damaged roof tiles has been settled by the FSP.
Attached to the claim form were photographs and a quote from EZ:
The quote includes the following costs:
repair to the storm water pipe $3,500
installation of retaining wall baffles $16,600
installation of retaining wall $6,250
The applicant must establish on the balance of probabilities it has suffered a loss
caused by an event to which the policy responds. This is known as a prima facie
claim.
The FSP‟s policy covers accidental loss or damage to the insured building and
common area contents which occurs during the period of insurance.
The FSP‟s assessor inspected the property on 31 March 2015. In his first report, he
says there was a severe storm with associated hail, extreme winds and torrential rain
which passed through Brisbane on 27 November 2014.
At the time of inspection, the assessor says he saw resultant damage to the terraced
landscaping along the western elevation of the property.
He described the work which needed to be done including removal of damaged
timber retaining steps, and rebuilding of the landscape.
Case No: 434733 Determination Page 4 of 9
He engaged a builder to report about whether the storm pipe burst due to the volume
of rain or whether there was a pre-existing defect.
Damage claimed was unintended and unexpected
The policy does not define accidental damage.
Accidental damage has been judicially interpreted to mean damage which is
unintended and unexpected.
Having considered the material provided, i n particular the numerous photographs, I
am satisfied the damage to the claimed items was unintended and unexpected.
In the circumstances, I am satisfied the applicant has established a prima facie claim.
FSP must establish an exclusion applies
Once so established, the onus shifts to the FSP to prove on the balance of
probabilities an exclusion applies if it seeks to deny or limit its liability for the loss.
As for the repair to the storm water pipe, the FSP relies on a policy term which allows
it to limit its indemnity to an insured for exploratory costs and replacement of
defective parts in the amount of $1,000.
Otherwise, it says it is not liable to indemnify an insured any further if the pipe burst,
leaked, discharged or overflowed because of a building defect.
The FSP relies on a builder‟s report. It submits the claimed damage to the thrust
block of the storm water pipe was weathered and non-compliant in both its
installation and design.
The FSP‟s builder inspected and photographed the pipe and provi ded a report in May
2015. The builder reported he saw a cracked section of concrete (which he described
as the thrust block) around the connection to the pipes. The lower pipe had moved
downward and away from the connect point. Upon inspection of the cracked
concrete, the builder said the edges were weathered and discoloured and not
recently damaged. The builder noted the other thrust box and concrete cell surrounds
were intact.
The builder also said the thickness of the concrete installed at the thrust block is
insufficiently thick. He relied on a 2003 Australian Standard.
However, he concedes:
It is possible that due to the nature and volume of hail and water which entered the
pipe at the head (top) of the drain and the force at which the water/hail flowed down
this pipe has caused the two pipes to separate…”
But he doubts if the correct size thrust block had been installed, the join would have
separated.
The applicant contends the volume of the water within the pipe coupled with packed
ice was too stressful at the first join in the pipe so the join split and fractured the
thrust block.
Case No: 434733 Determination Page 5 of 9
Builder’s report insufficiently persuasive to establish an exclusion applies
Although I acknowledge the applicant has provided no expert report, I have carefully
considered the photographs provided and the dramatic description of the storm
event. I note the FSP does not dispute the storm event was severe.
I have also taken into ac count the applicant‟s submission that the insured complex
was built in 1997 pursuant to requisite architectural and engineering plans and
specifications and yet the FSP‟s expert relies on a 2003 Australian Standard.
Furthermore, although the FSP‟s builder notes the concrete appeared to be
weathered and discoloured and not freshly exposed, he photographed and inspected
the property on 20 May 2015, some six months after the storm event.
On the information provided, I am not satisfied the FSP has established o n the
balance of probabilities the damage to the pipe and to the thrust block was caused by
a building defect. I am not satisfied the FSP can rely on a policy exclusion to deny
the claim.
The applicant has provided a quote for the cost to repair the storm water pipe. The
quote says the extent of damage cannot be ascertained without more extensive
evaluation and a PC amount of $3,500 was allowed.
The FSP has provided no material about the cost of repairs.
The FSP has paid $1,000 exploratory costs. The applicant is holding the cheque. The
exploratory costs indemnify an insured to locate the source of a burst or leaking pipe.
In this dispute, the applicant has located the source of the burst or leaking pipe.
On the information provided, I consider it is fair in all the circumstances the FSP
cancel the $1,000 cheque and pay to the applicant $3,500 for the applicant‟s claim to
repair the stormwater pipe.
2.2 Is the FSP is entitled to deny the applicant’s claim for landscaping?
The applicant claims for the installa tion of retaining wall baffles
The applicant claims the installation of retaining wall baffles to the steep incline at the
rear of the block in the amount of $16,600.
The applicant also claims the installation of a retaining wall at the head of the incli ne
in the amount of $6,250.
As set out earlier in this determination, it is accepted the applicant has established a
prima facie claim.
The onus shifts to the FSP to establish the claimed damage was caused by lack of
maintenance, wear and tear, gradual deterioration, failure to maintain the property in
good repair, or earth movement or that part of the claim is betterment.
The FSP notes the applicant‟s claim may not necessarily be for a retaining wall but
rather the general landscaping of a steep decline. Having considered the
photographs provided, I accept this interpretation.
Case No: 434733 Determination Page 6 of 9
The FSP argues the policy Additional Benefit does not apply as it includes cover for
replacing trees or rockwork but not timber designed to retain landscaping.
The FSP also relies on comments made by the builder that the landscaping down the
slope was free from vegetation and general landscaping. The builder also said the
sleeper logs were weathered and aged and not well maintained.
After the recommendation, the FSP argued the proximate cause of the damage to
the landscaping was the gradual deterioration and/or erosion caused by a weathered
and non-compliant thrust block and/or drainage pipe.
However, as set out earlier in this determination, it is accepted the applicant has
established a prima facie claim and it is not accepted the cause of damage was a
defect in the pipe.
Assessor confirms resultant damage and removal of debris
The FSP‟s assessor noted the applicant had removed a great deal of debris from the
bottom of the hill and around access to the lower units.
The assessor confirmed the resultant damage to the terraced landscaping. He said
the complex was neat and presentable and had no reason to doubt the explanation
given of the extent of the damage resulting from the event.
The assessor spoke with the contractor who provided the quote. The assessor said
item 1 relates to the rectification of the landscaping and the contractor had confirmed
the cost was to reinstate it as it was prior to the storm event. However in relation to
item 2, the assessor said item 2 is betterment as the retaining wall did not exist at the
time of the storm event.
Additional Benefit 14 provides cover up to $10,000
Taking all matters into account, the assessor recommended the FSP pay $10,000
pursuant to Additional Benefit 14 of the policy.
The FSP‟s policy provides cover for accidental loss and damage to the building and
common area contents.
Building and common area contents do not include:
„plants, hedges, trees, shrubs, gravel, shale, stones, clay or soil on paths or
driveways or tennis courts, soil or bark or mulch in gardens other than as
covered under Special Benefit 14 of policy 1:
Additional Benefit 14 says:
“ 14 Landscaping
We will pay up to $10,000 for the reasonable costs You or a Lot Owner necessarily
incur in replacing or repairing damaged trees, shrubs, plants, lawns or rockwork at
Your Situation lost or damaged by an Event claimable under Policy 1. ”
Case No: 434733 Determination Page 7 of 9
Damage claimed was accidentally caused
Both parties have provided numerous photographs of the damage claimed. In
addition, the applicant described how the damage occurred. However the damage
occurred, it is accepted the damage was accidentally caused.
The material provided establishes it is probable excessive water flowed and
displaced the wooden framework seen in the photographs and washed away river
stones and rockwork which the applicant says was part of landscaping in the area.
The applicant describes the structure. Before the storm event, the applicant says
there were two parallel copper treated logs which were staked in place and then the
logs were joined together by smaller timber batons which were covered by rocks. The
applicant describes the rocks which covered the logs which in turn covered the pipe.
The photographs provided show the structure described by the applicant. Some of
the timber work appears to be in place. Some is disturbed. The photographs show a
significant amount of displaced river stones.
The policy provides up to $10,000 for the reasonable costs necessarily inc urred in
replacing or repairing damaged trees or rockwork.
EZ provided a breakdown of the supply and installation of the sleepers and the
supply and installation of stones and rocks behind the sleepers. The breakup
included the stones behind the sleepers in the amount of $10,500.
On the information provided, I do not accept the damage was caused by excluded
events relied on by the FSP. Furthermore, from the material provided, I am not
satisfied the wooden structure described by the applicant is covered under the policy.
However, under additional benefits, the policy provides for the cost of removal and
disposal of debris. It appears the applicant has removed the debris but has not been
indemnified by the FSP.
While the policy does not provide cover for stones, under the Additional Benefit,
cover is provided to replace or repair damaged rockwork lost or damage by an
insured event. Having considered the photographs provided, I accept if there were
trees, shrubs or plants in the vicinity of the area of damage, it is probable they would
have been washed down the slope together with the other debris.
Fair in all the circumstances the FSP pay the applicant $10,000
Having considered the significant displacement of the rockwork which was held in
place by the wooden structure, and the application of the additional benefit which has
not been addressed, I am satisfied it is fair in all the circumstances the FSP pay to
the applicant $10,000 being the reasonable costs to supply and install the rockwork
behind the sleepers.
I am also satisfied it is fair in the circumstances that no policy excess is applied and
no interest is payable on the amounts in the determination.
After the recommendation, the FSP argued the current status of repairs is unknown
and the scope is to be reassessed. However, as the claim was made in March 2015
and is still not resolved, and in view of the material provided by EZ to the FSP‟s
Case No: 434733 Determination Page 8 of 9
assessor, I am satisfied it is fair in the circumstances to make a determination on the
material provided.
After the recommendation, the applicant argued for payment of other benefits
including removal of debris, claim preparation costs, and costs associated with
engineering and building consultancy reports.
This determination has taken into account the additional benefit of removal of debris.
The applicant has not incurred the cost of any consultants‟ reports. Claims
preparation costs must be incurred with the written consent of the FSP. In any event,
I am not satisfied claims preparation costs are applicable to the circumstances of this
claim or dispute.
2.3 Is the applicant entitled to compensation?
Compensation payable in some circumstances
Under its Terms of Reference, FOS may decide the FSP is to compensate the
applicant for non-financial loss (up to a cap of $3,000) but only where there is an
unusual degree or extent of physical inconvenience and time taken to resolve the
situation.
The a pplicant complains about the FSP‟s claims handling. It contends decisions were
not made and material not provided in a timely fashion.
The FSP has not addressed this aspect of the dispute.
The material provided shows the claim was made in March 2015 and assessed by
the FSP‟s assessor and builder in May 2015. A decision to deny the claim was not
made until November 2015.
FOS takes a conservative approach to non-financial loss and considers an insured
should be moderately robust and bear the normal degree o f inconvenience
experienced when a problem arises.
However, in the circumstances of this dispute, I am satisfied the FSP has not acted in
a timely fashion due to the time taken to make a claims decision.
I am satisfied it is fair in the circumstances the FSP pay to the applicant $500
compensation for non-financial loss.
Case No: 434733 Determination Page 9 of 9
3 Supporting information
3.1 FOS Approach
It is an accepted principle of general insurance law that an insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
3.2 Relevant policy extracts
The relevant policy extracts are referred to in the correspondence between the
parties and in the FSP‟s Notice of Response dated 2 6 February 2016. Both the policy
document and the Notice have been exchanged with the applicant.
3.3 Other relevant material considered and relied on
Parties‟ submissions and all attachments to submissions including emails,
quotes, reports, and photographs
Correspondence between the parties
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.