Denial of storm-related excavation collapse remediation claim

FirmFinancial Firm (Unknown - Insurer)
Decided2017-04-27
ProductGeneral Insurance · Other general
OutcomeFor the complainant
Amount awarded$309,000
Non-financial loss—
Amount claimed$309,786
SourceAFCA PDF

Summary

A company's construction excavation wall collapsed after storm rainwater and the insurer denied its $309,786.08 contract works claim, relying on design, workmanship, geotechnical and betterment exclusions. AFCA found storm water was the proximate cause, the exclusions and betterment were not established, and ordered $309,000 plus Insurance Contracts Act interest and legal costs up to $6,000.

The applicant established a prima facie sudden and unforeseen storm loss, and the insurer did not prove that any exclusion or betterment applied.

Issues

Subjects and remedies

natural disastersmall businesspay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 434179 Determination Page 1 of 8 Case number: 434179 21 April 2017 1 Overview 1.1 Dispute The applicant, a Proprietary Limited Company held an Annual Construction/Liability Insurance Policy with the financial services provider (FSP). On 28 February 2012 the applicant lodged a claim with the FSP after a storm on 9 February 2012 caused the collapse of part of the excavation face of the construction site. The applicant lodged a claim for indemnity of $309,786.08 being the cost to complete relevant remediation work including costs of stabilising the excavation wall and temporary accommodation costs for tenants on the adjoining property. The FSP denied liability and relied on the following exclusions:  loss or damage due to any fault, defect, error or omission in design, plan or specification  the excavation or underpinning work was not carried out in accordance with the plans, specifications, geo-technical reports for such work  the loss or damage arose due to the failure of the applicant to obtain a conditions report prior to commencement of the excavation. In the alternative, the FSP says the works carried out following the collapse does not relate to damage to the contracted works and would result in betterment. The applicant disputes the FSP‟s decision. 1.2 Issues and key findings Has the applicant established a claim under the terms of the policy? The applicant has established a claim under the terms of the policy as the policy provides cover for insured damage which is defined as “sudden and unforeseen physical loss or damage to contract works not otherwise excluded occurring during the period of insurance ” . There is no dispute that part of the excavation face collapsed following the storm/rain overnight on 9 February 2012. Such damage was sudden and unforeseen and therefore falls within the definition of insured damage for the purpose of the policy. Has the FSP established the application of an exclusion? The Panel is not satisfied the FSP has established the application of an exclusion within the terms of the policy. Case No: 434179 Determination Page 2 of 8 Has the FSP established betterment? The Panel is not satisfied the FSP has established betterment as there is no dispute that rectification works were required and the costs incurred were reasonable in the circumstances. 1.3 Determination This determination is in favour of the applicant. The FSP is to pay the applicant $309,000 to cover the cost of the remediation work including the costs of the temporary and permanent solutions to stabilise the evacuation and the temporary accommodation for tenants in the adjoining property. Further, the FSP is to pay interest in accordance with Section 57 of the Insurance Contracts Act 1984 (the Act) from 24 April 2014 being the date of its final decision letter until date of payment of the claim. Insofar as the applicant seeks payment of legal fees, the Panel determines pursuant to paragraph 9.4 of the Terms of Reference that the FSP pay the applicant legal fees up to $6,000 subject to the applicant providing appropriate invoices. Case No: 434179 Determination Page 3 of 8 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. The applicant in this dispute has been assisted by its legal advisor and detailed submissions have been made by the legal advisor on behalf of the applicant. In this determination reference to the applicant will include reference to the submissions made by the applicant‟s legal representative. In view of the complexities in this dispute, it has been referred to a Panel for determination. FOS issued a jurisdictional decision on 21 September 2016 after the FSP disputed the Service‟s jurisdiction to deal with the dispute. It was determined that the dispute is within the jurisdiction. The policy falls within the definition of „small business insu rance product‟ within the Terms of Reference and provided accidental damage cover for the defined event of storm/tempest/rainwater. The Panel has had access to all of the information exchanged and has based this determination on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes or practice and prior determinations where applicable. 2.1 Has the applicant established a claim under the terms of the policy? The applicant has the onus to establish on the balance of probabilities a claim that falls within the terms of the policy. This is commonly called a prima facie claim. Only once the applicant has established such a claim does the onus shift to the FSP to establish the application of any relevant exclusion. The applicant‟s policy, an Annual Construction/Liability Insurance Policy insured the applicant from the period 30 June 2011 to 30 June 2012. The policy provided cover for insured damage defined as: „The sudden and u nforeseen physical loss of or damage to the contract works not otherwise excluded, occurring during the period of insurance. The relevant contract works were the construction of an apartment block in „W‟ . The onus is therefore on the applicant to establish that the insured damage claimed was sudden and unforeseen physical loss or damage to the construction works. Circumstances of the loss There is no dispute that the following events occurred:  9 February 2012 a significant storm event in W  that there was a broken storm water pipe immediately adjacent to the point of failure of the excavation  sometime during the early hours of 10 February 2012 there was a substantial collapse of part of the excavation face along the eastern boundary Case No: 434179 Determination Page 4 of 8  due to instability, there was a danger that the immediately adjacent building would fall into the excavation  the applicant obtained urgent advice from an engineer JN and geo-technical engineers DP as to the make safe and remediation works required  excavated material was back filled against the collapsed excavation face to maintain stability  a temporary steel support framework was designed and installed against the collapsed face to provide longer term support  the temporary measures averted further collapse  within the design, shoring was incorporated to the western face but not the eastern face of the wall  no site specific geo-technical investigation was conducted prior to commencement of the work. Proximate cause of the loss The Panel is satisfied that the proximate cause of the loss was the storm/rainwater that fell overnight on 9 February 2012. DP a geo-technical engineer conducted a site inspection immediately following the collapse and determined that the failure occurred after a period of overnight sustained intense rain (80mm). DP advised that prior to the failure, the surface of the excavation had been shotcreted to control erosion. He considered „ that a buried storm water pipe may have introduced water behind the shotcrete face essentially blow (sic), the shotcrete off the wall of the excavation.’ JN a consulting engineer reported on 2 March 2012 as follows: „The design of the above (excavation) was carried out by this firm. It is structurally adequate, complies with relevant Australian codes, and is suitable for the proposed usage. Computations for the design have been carried out by a practising, qualified structural engineer. Periodic inspections have been carried out, during the construction and at the time of the inspection of the above and was found to be satisfactory subject to the recommendation of the site instructions provided.‟ The FSP ‟s loss adjustor CL in progress report 14, dated 4 July 2013, confirmed given the torrential overnight rain, that it and the engineers believed the pressure from the escape of water into the ground, in particular at a point where there had also been a vertical fissure in the rock was the immediate cause of the failure of the excavation. The FSP has relied on a report from KA, a consulting engineer, dated 26 July 2013. That report was not based on any inspection of the property but based on a review of documentation. KA does not dispute the fact that the heavy rain was a proximate cause of the collapse of the face of the excavation. Case No: 434179 Determination Page 5 of 8 Applicant has established a prima facie claim for insured damage Based on the available information, the Panel is satisfied that the applicant has established a claim within the terms of the policy as the storm/rainwater was the proximate cause of the sudden and unforeseen collapse of the excavation wall. 2.2 Has the FSP established the application of an exclusion? The Panel is not satisfied the FSP has established the application of an exclusion Exclusion (a) under section 1 of the policy which provides: „We will not be liable for insured damage: a) Due to any fault, defect, error or omission in design plan or specification‟ The FSP says and the Panel agrees that the exclusion is not limited to any fault, defect, error or omission of the applicant but applies whether there is a fault, defect, error or omission in design plan or specification irrespective of the party responsible for that. The Panel is not satisfied however that the FSP has established that the insured damage was due to a fault or error in design or that such a fault or error in design, plan or specification was a proximate cause of the loss. The FSP‟s engineer KA reached the following conclusions: 1. some shoring should have been detailed or at least noted on the structural engineering drawings for the eastern side of the site 2. as there was an existing building on shallow foundations in close proximity to the eastern excavation is important to ensure that the excavation remains stable during the works 3. the shotcrete on the eastern side of the excavation should have been specified to at least the extent that it was specified for the western side 4. the shotcreting did little to stabilise the excavation face and in fact was detrimental 5. the shotcrete probably exacerbated the collapse by causing the development of hydrostatic pressure 6. if the shotcrete was not in place it is likely that any escape of water from the buried stormwater line would have only caused localised collapse. The Panel notes however that the engineer JN identified that the design was structurally adequate and complied with relevant codes and was suitable for the proposed usage. There is no suggestion in the report from KA that this was not the case. JN identified that periodic examinations had been carried out during the construction and at the time of inspection was found to be satisfactory. There is no suggestion that this did not occur. CL in the progress report 14 dated 4 July 2013 identified that as a precautionary measure, in November 2011, the applicant had some preliminary geo-technical tests undertaken before proceeding with the work. Case No: 434179 Determination Page 6 of 8 In relation to the design of the excavation wall, CL noted: „whilst it might be possible with the benefit of hindsight to criticise the absence of specific provision for shoring, we would hesitate to suggest that the engineer‟s design fell into the category of f aulty nor was the “omission” of shoring the immediate cause of the collapse. ‟ The Panel is persuaded by the reports provided by the applicant and CL that the collapse was not due to any fault, defect, error or omission in design, plan or specification within the terms of the policy. There is no evidence of any fault, defect, error or omission in material or workmanship The FSP has not identified any evidence of defective workmanship or materials that would fall within the exclusion. The Panel notes that CL in this respect reported as follows: „We have not identified any defective workmanship or materials that might fall within this exclusion.‟ The Panel notes the concern expressed by KA that the shotcrete may have exacerbated the collapse. In this regard, there is a suggestion that the shotcrete did not have any weep holes. The applicant strongly disputes this and maintains there were weep holes along the line of the shotcrete. Neither party has developed this argument further. I n the Panel‟s view, the available information does not support a finding that the insured damage was caused by a fault, defect, error or omission in material or workmanship. The insured damage was not a consequence of the failure to carry out the work in accordance with plans, specification or geo-technical reports. Exclusion “ H ” excludes damage that is a consequence of failure to carry out excavation or underpinning work in accordance with the plans, specifications, geo- technical reports for such work as approved by design, structural or consulting engineer directions. The FSP say that as the design and specifications did not include shotcrete being placed on the eastern wall of the excavation and as in KA‟s view, the shotcrete contributed to the loss, this exclusion should apply. The FSP says the applicant applying shotcrete to the wall was a breach of the plans, specification etc. The applicant says the report from KA is fundamentally flawed as it refers to there being no drainage provided behind and through the shotcrete which is incorrect. The applicant maintains evidence of the drainage and weep holes has been provided. As indicated earlier, the Panel notes that the FSP has not responded to this assertion. The Panel accepts that there is evidence that the application of the shotcrete may have contributed to the extent of the damage. However, there is no evidence that the collapse of the wall was caused by the application of the shotcrete. Case No: 434179 Determination Page 7 of 8 According to the engineer JN, there were regular inspections conducted. It is reasonable to accept that the application of the shotcrete was an additional provision to secure the wall against erosion is consistent with the instructions from the engineer. The Panel is not satisfied the FSP has established the application of the exclusion. The failure to obtain a site specific geo-technical report is not the proximate cause of the loss Exclusion “ L ” and general exclusion “ I ” cover the failure to obtain a conditions report prior to commencing excavation work. The Panel notes from the information exchanged that the applicant did obtain a geo- technical report from DP prior to the commencement of the excavation works. Engineer JN had been involved in the design of a building on the adjoining site in 2004 and based on a geo-technical report provided by DP for that project believed that the site was essentially underlying rock with no significant shoring or piling required. As a precautionary measure in November 2011, DP was requested to undertake a test excavation at each of the four corners of the site to assess the suitability of the site. As a result of those findings, the applicant was reasonably satisfied that the ground conditions from the 2004 report had been validated. The relevant exclusion (general exclusion I) provides as follows: „Insured damage or liability is a consequence of a failure to obtain a conditions report prior to such excavation or underpinning works.‟ There is no information that the absence of a site specific report caused or contributed to the collapse of the wall. There is no requirement under the exclusion to obtain a site specific report. The information provided satisfies the Panel that the applicant did obtain an appropriate conditions report. 2.3 Has the FSP established betterment? The FSP says that much of the works carried out following the collapse of the excavation does not relate to damage to the contract works. Scope of cover is provided under the policy for amongst other things:  the demolition or disposal of damage to undamaged contract works  the removal of debris  architects, engineers, surveyors and consultant fees necessarily incurred  the damage to the existing structure located on or about the contract site  for mitigation expenses including the cost and expenses reasonably incurred in contracting  reducing or preventing further insured damage provided such further loss or damage is not excluded under the policy. Case No: 434179 Determination Page 8 of 8 There is no evidence that the works conducted by the applicant were not reasonable mitigation expenses incurred in containing, reducing, supressing or preventing further insured damage. The architects, engineers, surveyors and consultant expenses incurred are reasonably covered under the policy as is the demolition and disposal work. Whilst the FSP says that shoring was not part of the original design and the redesign was not as a consequence of the damage but to address the deficiencies in design it has not provided any detailed reasoning for this argument. The FSP has not provided any breakdown of the costing which it says constitutes betterment. Based on the information provided the Panel is not satisfied the FSP has established betterment. Conclusions The applicant has claimed the sum of $309,786.08. The applicant is aware that the compensation cap of $309,000 applies to claims before the Financial Ombudsman Service. The applicant has accepted this cap and in the circumstances, the Panel is satisfied that the applicant is entitled to compensation for the insured loss in the sum of $309,000. The Panel is also satisfied the applicant is entitled to interest in accordance with Section 57 of the Act from 24 April 2014 being the date of the FSP‟s final decisi on to reject the claim. The Panel is satisfied that at that time, the FSP had all relevant information and was in a position to make an informed decision to accept liability for the applicant‟s claim. The Panel is also satisfied that the applicant is entitled to be paid legal costs incurred in providing the submissions to FOS. Paragraph 9.4 of the Terms of the Reference provide that FOS may decide that an FSP contribute to legal or other costs but unless exceptional circumstances apply will not require the FSP to contribute more than $6,000 to these costs. The Panel has been assisted by the submissions made on behalf of the applicant by the legal representative. The Panel accepts given the nature of the dispute that exceptional circumstances apply as the applicant could not have adequately represented itself in this dispute. In the circumstances is satisfied that the FSP is required to contribute up to $6 ,000 to the applicant‟s legal costs subject to the applicant providing relevant invoices.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.