Determination 433955

Refusal to pay for removal of concrete slab after fire and slab damage during demolition

FirmFinancial Firm (Unknown - Insurer)
Decided2016-12-06
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$2,000
Amount claimed$20,000
SourceAFCA PDF

Summary

After a house fire, the applicant disputed the FSP's refusal to pay for removal of a concrete slab that the fire did not damage. AFCA found no obligation to pay for the slab removal but ordered the FSP to pay $2,000 for slab damage caused during demolition.

The slab was not damaged by the fire and did not meet building code, so removal was not payable, though demolition damage warranted compensation.

Issues

Subjects and remedies

home or building damagepay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 433955 Determination Page 1 of 6 Case number: 433955 1 December 2016 1 Overview 1.1 Dispute The applicant held a household (home and contents) insurance policy with the financial service provider (FSP). She lodged a claim after fire destroyed her property. The applicant initially complained about the amount of the cash settlement offered by the FSP, and she was also unhappy about the way the FSP had handled the claim. However, she later agreed to limit the issues in dispute to whether the FSP was required to pay for the removal of the concrete slab on the property, and whether it should pay her any compensation. The FSP had declined to pay the part of the claim relating to the slab because it had not been damaged by the fire. However, it did acknowledge that some damage had been caused to the slab in the course of demolition of the fire-damaged house. 1.2 Issues and key findings Is the FSP required to pay for removal of the concrete slab? The FSP is not required to pay for removal of the concrete slab, because it was not damaged by the insured event. In any case, the concrete slab did not comply with the relevant building code, which means the FSP is entitled to reduce the settlement amount on that basis. Is the applicant entitled to compensation? Because the concrete slab was slightly damaged by the FSP during demolition of the building, the FSP offered to pay the applicant $2,000. That is fair under the circumstances, given the additional concern this caused the applicant. 1.3 Determination This determination is partially in favour of the applicant. The FSP is not required to pay for removal of the concrete slab. However, it must pay the applicant $2,000 compensation in relation to the damage caused to the slab. Case No: 433955 Determination Page 2 of 6 2 Reasons for determination I have decided this case on the basis of what I consider fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. This determination deals only with the issues regarding the removal of the concrete slab, and the damage to it. I have taken into account all the material submitted by the parties. I am satisfied that the documentation I have relied on has been provided to both parties. For the purposes of this determination, I will deal with only those points considered relevant. 2.1 The FSP is not required to pay for removal of the concrete slab What does the policy say? The policy covers loss or damage caused by fire. The FSP may choose to rebuild or repair the home, although it is not obliged to pay extra costs which would apply to repair or rebuild to a better condition than it was in before the fire, unless that is needed in order to meet current building standards. The policy, alternatively, gives the FSP the option of making a cash settlement instead of undertaking the rebuilding or repair itself. However, the policy does allow the FSP to reduce the payment if any part of the home did not comply with relevant building laws when it was originally built. What was the condition of the house and slab? In this case, it appears the house had been constructed and the lower level enclosed by the applicant or previous owner, despite the slab being ‘inadequate for usage in a hab itable residential structure’, according to the FSP’s consultant, STA. That means the FSP, in rebuilding/repairing the house (or making an equivalent cash payment), was not obliged to include work needed to put the property into a better condition than it had been – specifically, by replacing the slab to make the lower area habitable - when the evidence indicates the use to which the area was being put was not in compliance with the relevant building codes in the first place. How did the applicant and FSP agree to settle the claim? The FSP made a cash settlement offer, which the applicant initially accepted. However, she said that when the FSP demolished the house, it left behind the concrete slab, which was cracked and had holes in it. (The applicant said it cost her about $20,000 to remove the slab herself.) The FSP explained that the scope of works on which that settlement offer was based did not provide for the removal or replacement of the concrete slab. This is because STA had reported that the slab itself had not been damaged by the insured event, and so did not have to be replaced. The FSP also pointed out that the new house the applicant proposed building on Case No: 433955 Determination Page 3 of 6 the site – a single storey ‘slab -on-the- ground’ home – is substantially different from the one that was there before the loss. This meant the existing slab was unsuitable and had to be removed and replaced before the new building could go up. As STA reported, the original slab was not built to allow habitable areas on the lower level (but was expected to be for car-parking and laundry purposes), and it did not meet the relevant building code to allow habitation. I am satisfied that it is not the FSP’s responsibility to meet the costs for extra work needed to accommodate the applicant’s specific building plans, when the applicant accepted a cash settlement in order to deal with the rebuild herself. That is particularly so when the extra work (namely, removal of the slab) was to a part of the building which had not sustained fire damage in any case. 2.2 The applicant is entitled to accept the FSP’s offer of compensation Under 9.3 of our Terms of Reference (TOR), FOS may award compensation for non- financial loss, but only where:  there has been an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the applicant’s expectation of enjoyment or peace of mind  in the case of a dispute pertaining to an individual’s privacy rights – injury has occurred t o the applicant’s feelings or humiliation has been suffered by the applicant. The maximum for any such award would be $3,000 per claim made in the dispute. In this case, the FSP does concede there was some minor damage to the corner of the original slab, caused while the FSP ’s contractor was demolishing the property. The STA report identified some chipping and a fracture. The FSP said the repair of the damaged section of the slab would have been relatively simple and not expensive. However, it has offered $2,000 in respect of this damage, while pointing out that is far more than the costs that would have been incurred to fix it . I appreciate that the damage to the original slab may well have caused the applicant some additional concern, at what was already a difficult time (and I acknowledge that in her original complaint, she expressed dissatisfaction with other aspects of the FS P’s handling of her claim). However, I also note that the slab was going to be removed and replaced in any case, to accommodate the applicant’s plans for her new home. So, while I consider the FSP’s offer of compensation generous, it is fair in the circumstances as recognition of the damage caused, and the impact of this on the applicant. Case No: 433955 Determination Page 4 of 6 Case No: 433955 Determination Page 5 of 6 3 Supporting information 3.1 Expert’s report Page Wording FSP’s expert (STA) Report 8 February 2016  The front - left corner [of the slab] has been fractured, apparently by the demolition excavator  Our opinion is that there is no indication that the fire event negatively impacted on the integrity of the house slab  The slab is not adequate for residential habitable purposes due to non - compliance with c urrent codes…(AS2870)  It is expected the slab was originally constructed for car parking and laundry purposes and not for habitation  It is recommended that the slab and footings are demolished and removed  Photographs showing chipping and fracture 3.2 Policy terms Page Wording 6 For your home and contents, we pay: Up to your home sum insured… 19 Insured Events Fire A fire causes loss or damage to your home or contents 62 Settling your claim We may choose, at our option, one or more of the following ways to settle your claim: 1. Rebuild or repair your home as new… 2. Pay you the cost to us – that is, pay you what it would cost us to rebuild or repair your home as new up to the ho me sum insured Case No: 433955 Determination Page 6 of 6 63 Reductions we may apply We may reduce your payment in these cases:…  any part of your home did not comply with relevant building laws when it was originally built If only part of your home is affected When only part of your home is damaged or destroyed , then we pay to repair or rebuild only the area that was a ffected by the damage. …

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.