Home / Financial Firm (Unknown - Credit) / Determination 433509
Determination 433509
Conditional loan approval lapsed and application reassessed
Summary
The applicant said the FSP misled him that a lapsed conditional loan approval would be reinstated, failed to warn him of the deadline, and reassessed his application on a lower amount. AFCA found he was not misled, the FSP was entitled to reassess the new application, and no compensation is payable.
Once a conditional approval lapses the arrangement ends, so the lender may lawfully reassess a new application, and the misrepresentation claim could not be established on conflicting uncorroborated recollections.
Issues
- Misleading conduct primary · not upheld
“The Applicant has not established that he was misled by the FSP that the application would be reinstated.”
- Poor communication secondary · upheld
“It appears the FSP did not put the conditional approval in any other written form to the Applicant.”
- Responsible lending failure secondary · not upheld
“The FSP was entitled to conduct a new loan assessment and did not make an error by requesting further information.”
Subjects and remedies
no remedy
Text of the determination
Determination
Case No: 433509 Determination Page 1 of 5
Case number: 433509 2 6 October 2016
1 Overview
1.1 Dispute
The Applicant says that the Financial Services Provider (FSP) misled him about what
would happen if a conditional loan approval he obtained in November 2015 lapsed
after 90 days. He also says the FSP did not keep him properly informed about the
loan or its requirements for approval. The Applicant says that the FSP made him re-
apply for the loan after the conditional loan approval lapsed in February 2016, which
meant that he has suffered financial and non-financial loss.
The Case Manager provided the parties with a recommendation dated 19 September
2016 on the issues in dispute. The recommendation was in favour of the FSP. A copy
of the recommendation is attached to this determination.
The Applicant rejected the recommendation.
1.2 Issues and key findings
Were the findings of the recommendation correct?
The findings contained in the recommendation were correct and are adopted in this
determination . Further submissions provided after the recommendation have been
considered.
Was the Applicant aware that the conditional approval would lapse in 90 days?
Although it appears the time limit on the conditional loan approval of 90 days was
never communicated to the Applicant in writing, it is clear that the Applicant was
aware that it would lapse after 90 days as he discussed this with the FSP in
November 2015.
Did the FSP mislead the Applicant?
The FSP and the Applicant have provided conflicting statements about what was said
about the terms of the conditional approval in November 2015. As there are no
contemporaneous notes of the conversation, there is insufficient information to
establish that the FSP misled the Applicant.
Once the original conditional approval lapsed, was the FSP was entitled to
reassess the construction loan application?
When the conditional approval lapsed, the FSP was entitled to request further
information to assess the new construction loan application.
Case No: 433509 Determination Page 2 of 5
1.3 Determination
This determination is in favour of the FSP.
I agree with the case manager’s reasons for the recommendation and the
recommended outcome. As a result, the FSP is not required to pay compensation to
the Applicant.
Case No: 433509 Determination Page 3 of 5
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
I am satisfied that the case manager’s recommendation contains an accurate
summary of the dispute, the issues to be determined, any applicable paragraphs of
the Terms of Reference and any relevant law.
2.2 Was the Applicant aware that the conditional loan approval would
lapse in 90 days?
The Applicant says he received conditional approval for the loan
The Applicant says that the FSP provided him with an “ approval in writing ” dated 2
November 2015, in relation to the construction loan. However the Applicant has
acknowledged that he did not receive any physical documents from the FSP relating
to the construction loan, including a loan approval, loan offer or loan contract.
The Applicant’s reference is to an email sent on 2 November 2015, from a FSP credit
officer (KS) to the Applicant’s broker. The email is headed “Current Approval Status:
Conditional Approval” and states, “Please provide the following outstanding
requirements to enable me to progress your client’s application further… Please
provide executed Fixed Price Building Contract …”.
I note the email:
does not state that the loan will be approved on the provision of the further
document, but that the application will be progressed further
does not stipulate any time limit for any conditional approval or lapse date and
indicates that a phone call was made at the time, although it is not known what
was discussed.
As neither party has been able to provide any other documents in relation to any
formal conditional approval, it appears that the conditional approval was informal in
nature, but nevertheless presented as a conditional approval based on the email
above and the Applicant’s account of events .
The Applicant was aware of the time limit
Although the Applicant says that the 90 day time limit for the conditional approval
was not communicated to him in writing, it is clear that he was aware of the time limit.
In his letter to FOS dated 3 May 2016, the Applicant says:
“ Once the loan was approved in November 2015, I requested specifically to speak with [KS at
the FSP] who was the credit assessment officer of this case.
The reason for making this contact was that I was given approval with a condition (signed
agreement with a builder) at a time where most builders were unavailable. And I was only given
3 months to satisfy this condition …
Case No: 433509 Determination Page 4 of 5
…the v ery purpose of contacting [KS] was my concern around the timeframe I had been given
to provide the signed document and the fact that the building industry will be mostly unavailable
in that time for me to provide what they were requesting. Basically I was not satisfied that I can
provide the bank with what they need in the time that they need it. Otherwise why else would I
be contacting a credit officer?
I first asked [KS] what it was that they needed to formalise the loan and he said I need to
provide a signed agreement with a licensed builder to the bank that has a contract amount…”
Despite the lack of relevant documents, it is clear that the FSP or his broker made
the Applicant aware of the three month expiry period at the time of the email of 2
November 2015. That was his main motivating factor in contacting the FSP officer,
KS, personally to find out what would happen if he was not able to meet the
timeframe or request an extension of time.
It appears the FSP did not put the conditional approval in any other written form to
the Applicant. Therefore, the FSP did not do all that it could have to meet its
obligations under the Code of Banking Practice to promote better informed decisions
and ensure there was effective disclosure of information, preferably in writing,
including the terms of the conditional approval and lapse period warning.
However, the Applicant was aware of the lapse period of 90 days at the time and was
not able to provide the relevant executed building contract in the time period.
Therefore, nothing further turns on the fact that the information was provided verbally
rather than in writing. I don’t consider that the issue of how notice of the lapse period
of 90 days was communicated to the Applicant caused him any loss.
2.3 Did the FSP mislead the Applicant?
The Applicant has not established that he was misled
The Applicant says that the FSP misled him to believe that the loan application would
be reinstated if he missed the 90 day deadline “… without any further conditions other
than providing the signed fixed price building contract”. The Applicant says that
although he has no record of the discussion, the surrounding circumstances show
that his account is to be preferred, namely that he was calling to seek comfort around
the lapse period and he would have acted otherwise without such a statement.
Although the FSP officer, KS, could not recall the particular telephone call with the
Applicant, he says that he would not have made such a statement as he was aware
that once a conditional approval lapsed, it would need to be re-assessed. He states
that he may have said that the Applicant could apply for an extension, but that it
would need to go back to the credit team for review and was not guaranteed.
I don’t consider the Applicant’s reference to surrounding circumstances persuasive.
The Applicant’s motivation to make the phone call to the FSP officer in November
2015 may have been to obtain information on what would happen if the offer lapsed,
but there is nothing to show that the FSP officer made the statements the Applicant
alleges. The Applicant may have been told there can be an extension request, yet
considered at the time that he could meet the 90 day timeframe and continued on
accordingly. I note that although the Applicant was aware of the timeframe, there is
Case No: 433509 Determination Page 5 of 5
no information to show he contacted the FSP within the 90 day period to request any
extension. The Applicant’s subsequent conduct is equally applicable to both versions
of events.
Neither party had any contemporaneous records of the telephone conversation in
2015. Because of this and because FOS cannot cross examine parties to a dispute,
the case manager found that the Applicant had not established that he had been
misled by the FSP.
I agree with the case manager’s c onclusion that it has not been established that the
FSP misled the Applicant in this regard.
2.4 Once the original conditional approval lapsed, was the FSP was
entitled to reassess the Loan?
The FSP was entitled to conduct a new loan assessment
The Applicant says that upon having to re-apply for the construction loan in 2016, he
had to supply a new series of documents which meant that there was a further delay
of two months in the loan application process. He says the FSP should have told him
this in October 2015 and been clear in its communication, and he should not have to
account for a change of mind by the FSP credit officers betwee n November 2015 and
February 2016.
However, where a conditional approval lapses, any arrangement between the FSP
and the Applicant ceased. Any subsequent loan application would be need to be
considered by the FSP as a new loan application in accordance with its responsible
lending obligations. As a result, the FSP was entitled as a matter of standard industry
practice to:
request further documents or information from the Applicant to assess the new
loan application in 2016 even if that differed from previous requests and
come to an independent lending decision based on the new documents or
information provided.
The FSP did not make an error by requesting further information from the Applicant
in 2016 that it considered reasonably necessary to allow it to assess the new loan
application. It follows that the FSP:
is not liable for any losses claimed by the Applicant and
is not required to pay the Applicant any compensation.
Recommendation
Case No: 433509 Recommendation Page 1 of 6
Case number: 433509 19 September 2016
3 Overview
3.1 Dispute
The Applicant applied for a loan in October 2015. The FSP gave him conditional
approval for a loan of $800,000 on 2 November 2015 (Loan). The Loan approval was
conditional on the Applicant providing the FSP with a fixed price building contract
(Contract) within 90 days.
As the Applicant was unable to obtain the Contract within 90 days, the Loan offer
lapsed on or around 31 January 2016 (the Deadline). As a result, the FSP required
the Applicant to reapply for the Loan and provide additional information. The
Applicant says the FSP:
acted unreasonably by giving him only 90 days to provide a fixed price building
contract as builders do not work over the Christmas period
failed to notify him or his broker that the conditional approval was about to lapse
or had lapsed
misled him to believe that the Loan application would be re-instated if he missed
the Deadline
should either have declined the application for the Loan in the first instance or
approved it without requiring further information in February 2016.
The Applicant says that delay caused by the FSP’s conduct has caused him financial
and non-financial loss.
3.2 Issues and key findings
Was a timeframe of 90 days reasonable?
The approval the FSP gave the Applicant on 2 November 2015 was conditional upon
the provision of the Contract within 90 days . The Applicant was aware of the
Deadline. Because of this, the FSP has not made an error by lapsing the Loan
application after 90 days.
Was the FSP under an obligation to notify the Applicant of the Deadline?
The FSP notified the Applicant of the Deadline when it provided the conditional
approval. The FSP did not have a duty to notify the Applicant again when the
conditional approval was about to lapse.
Did the FSP mislead the Applicant that it would re-instate the application?
The Applicant has not established that the FSP misled him that it would either
Case No: 433509 Recommendation Page 2 of 6
re-instate the Loan application if it lapsed or
approve the Loan without requesting further information if the conditional
approval lapsed.
Did the FSP make an error when it re -assessed the Loan application?
The FSP complied with its policy and good indus try practice when it re-assessed the
Loan application after the conditional approval lapsed.
3.3 Recommendation
This recommendation is in favour of the FSP.
The FSP is not required to compensate the Applicant.
Case No: 433509 Recommendation Page 3 of 6
4 Reasons for recommendation
4.1 Was a timeframe of 90 days reasonable?
The Applicant says the Deadline was unreasonable
The Applicant says that the 90 day time limit to provide the Contract from a builder
was unreasonable. He says the building industry closes down over the Christmas
period and most of January making it very difficult to contact builders and obtain fixed
price building contracts.
The FSP notified the Applicant of the Deadline
The FSP sent the Applicant a conditional Loan approval on 2 November 2015. The
Applicant says that he was aware of the Deadline when the FSP made the
conditional offer.
As the conditional Loan approval was sent to the Applicant on 2 November 2015, the
90 days ended on or around 31January 2016. The Applicant provided the Contract to
the FSP on or around 10 February 2016 – around 10 days after the Deadline.
While the Applicant says the Deadline was unreasonable, the Applicant was aware of
the Deadline. The time limit for conditional approval was in line with the FSP’s policy.
If the Applicant thought the Deadline unreasonable he was free to approach other
lenders for his construction loan.
4.2 Was the FSP under an obligation to notify the Applicant of the
Deadline?
The FSP did not notify the Applicant that the Deadline was approaching
The Applicant says that the FSP should have notified him that the Deadline was
approaching. It is common ground that the FSP did not do so. It is also common
ground that the Applicant was aware of the Deadline when he received the
conditional approval.
As part of the investigation, the dispute was referred to the Ombudsman’s Banking
Adviser. The Banking Adviser is a person with extensive experience in the financial
services industry and well qualified to give advice about the FSP’s obligations to the
Applicant.
There is no obligation on the FSP to notify the Applicant
In the Banking Adviser’s opinion, there was no obligation on the FSP to notify the
Applicant that:
the Deadline was approaching or
the conditional approval had lapsed.
I am satisfied that that the Banking Adviser’s opinion is correct.
Case No: 433509 Recommendation Page 4 of 6
4.3 Did the FSP mislead the Applicant that it would re-instate the
application?
Misleading conduct
FOS can investigate a claim that a financial services provider misled an Applicant
and caused them to suffer loss. If we find that the Applicant was misled, we will
assess how much worse off they are as a result of relying on the misrepresentation.
The remedy for misleading conduct is not to make the misrepresentation come true.
The Applicant says the FSP misled him
The Applicant says when he was informed by his broker that the conditional approval
would lapse after 90 days, he telephoned the lender he was dealing with at the time
(the First Lender) to object. The Applicant says that First Lender told him that the
FSP would:
renew the approval without any further conditions other than providing the signed fixed
price building contract.
The Applicant says the First Lender misled him as the FSP did not agree to renew
the application for the Loan when he missed the Deadline.
The First Lender’s recollection is different to the Applicant’s
The First Lender admits that he does not recall the exact conversation he had with
the Applicant. The First Lender does, however, say:
I do not believe that I would have told either a broker or a customer in writing or
verbally [that the FSP] “ is happy to approve the approval without further conditions
other than providing the signed fixed price building contract ” or something to that effect.
This is because I am aware once a loan approval lapses it would need reassessment.
The Applicant has not established that he was misled
FOS is not a court of law. We do not have the power to take or test evidence on oath,
or to require third parties to give evidence.
When we assess disputes, we consider available documents, the recollections of the
parties, and all relevant circumstances. We give more weight to contemporaneous
documentary information.
If there is no relevant documentation, we will decide what is most likely to have
occurred based on the information provided to us. If there are conflicting recollections
and these are evenly weighted, we may find that a claim cannot be established.
In this case, there are opposing statements of what was said during the relevant
telephone call. Although the Applicant says that the timing of the telephone call
should give weight to his recollection, without contemporaneous notes from either
party, it is not possible to reach a conclusion about the contents of the conversation
between the First Lender and the Applicant.
Case No: 433509 Recommendation Page 5 of 6
Because of this, the Applicant has not established that he was misled by the First
Lender.
4.4 Did the FSP make an error when it re-assessed the Loan
application?
The Applicant says the FSP has made an error
The Applicant’s position is that the FSP made an error as it gave him conditional
approval for the Loan in November 2015 and then:
required additional information in February/March 2016 and
approved a lesser amount.
The Applicant says the FSP has come to different lending decisions based on the
same information because his financial position was the same in March 2016 as it
was in November 2015.
The FSP’s policy required the Loan to be reassessed
The FSP’s policy relating to the expiration of loan offers is that once an a pproval
lapses is not to be reinstated. The policy requires an applicant to submit a new loan
application and for the FSP to undertake verification of the information provided.
According to the Ombudsman’s Banking Adviser, this is good industry practice an d
considered to be the actions of a diligent and prudent lender. This is because,
amongst other things:
updated financial information may be available to the FSP and
valuation reports have a limited life, generally agreed to be three months.
Although the Applicant says that his financial position had not changed, additional
information was available to the FSP. This information included:
updated company tax returns and financials for year ending 2015
directors’ individual tax returns for year ending 2015
building tender and
works outside of the building contract.
The FSP also arranged for an updated valuation that took into account “ specific
commentary…around works outside the contract ”. In the Banking Adviser’s opinion the
additional information requested b y the FSP was crucial to a proper assessment of
the Loan application.
The re-assessment led to a lesser offer
The FSP used the updated financial information to assess the Applicant’s loan
application. The FSP’s lending notes contain the following entry on 22 February
2016:
Based on the land value + building tender + works outside the contract, the security value
adopted by the bank at this time is $2,144,561. As such, the maximum new loan amount that
can be considered with the LVR @ 80.00% is $765,648 rounded down to $765,600.
Case No: 433509 Recommendation Page 6 of 6
In the above circumstances, the FSP did not make an error by re -assessing the Loan
application. The FSP’s decision to offer the Applicant a lesser amount is a
commercial decision the FSP is entitled to make and not one that FOS can review.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.