Determination 432361

Denial of 2015 structural damage claim after cash settlement and undisclosed engineering report

FirmFinancial Firm (Unknown - Insurer)
Decided2018-01-08
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$309,000
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The applicant's 2015 structural damage claim on his home was denied after an earlier cash settlement, and the FSP's representative had directed repairs based on an engineer's report without disclosing a contrary report. AFCA found the FSP responsible for the current damage and ordered, at the FSP's option, either repairs or a $309,000 cash settlement with interest, plus $3,000 non-financial loss.

The FSP breached its obligations by failing to provide a contrary engineering report and by its representative's advice, making it responsible for loss flowing from the applicant's reliance on that advice.

Issues

Subjects and remedies

home or building damagepay compensationpay interestpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 432361 Determination Page 1 of 7 Case number: 432361 20 December 2017 1 Overview 1.1 Dispute This matter involves claims by the applicant under a Home Insurance Policy, held with the financial service provider (FSP), following damage at the insured home. The FSP has denied the applicant’s 2015 claim on the basis that there is no single defined event that has caused the damage to the property, damage is occurring gradually over time due to unstable founding soils and that any problems with the underpinning works have occurred due to the applicant’s failure to engage appropriate experts to carry out earlier work. The policy holder is the applicant’s father but for the sake of brevity any reference to applicant within this determination will be to both the policy holder and the applicant himself. 1.2 Issues and key findings Has the FSP met its obligations in respect to the claims and dispute? The FSP is not entitled to deny the applicant’s 2015 claim and is required to respond to the claim in accordance with the terms of this determination. 1.3 Determination This determination is in favour of the applicant. At the FSP’s discretion, it is to:  meet the costs of all repairs at the insured home arising from the work which was carried out by the applicant following the claim which was accepted in 2008; or  pay the applicant the amount of $309,000, being the jurisdictional limit of the Service. Should the FSP chose the first option, the FSP is to arrange for suitable professionals to attend onsite to prepare a scope of works and quotation for the required repairs. The FSP is to provide the applicant with a copy of the scope of works and the quotations, for review. Case No: 432361 Determination Page 2 of 7 The parties are requested to work together to resolve the dispute on this basis but in the absence of agreement, either party may come back to the Service for further determination to resolve this aspect of the dispute. Should the FSP chose the second option, then the FSP is to pay interest on the $309,000, in accordance with the Insurance Contracts Act 1984 (the Act) from the date the FSP denied the applicant’s 2015 claim, to the date that the cash settlement is paid. The FSP is required to pay a further amount of $3,000, by way of non-financial loss compensation. Case No: 432361 Determination Page 3 of 7 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the material exchanged. The FSP engaged an engineer (SC) to report regarding the circumstances of the claims and the dispute. SC attended onsite on several occasions and has provided reports dated 26 March 2007, 14 March 2008, 30 June 2015, 8 June 2017, 19 June 2017 and 10 November 2017, all of which have been exchanged. The FSP also engaged a civil engineer (RB), who attended onsite on 18 July 2008 and provided a report dated 20 August 2008, which has been exchanged. The Service engaged an independent structural engineer and building surveyor (GC), to provide a report under its Terms of Reference. GC attended onsite on 17 May 2017 and 8 August 2017 and has provided a report dated 16 October 2017, which has been exchanged with the parties. In addition, the panel has had the opportunity to review a number of additional reports which have also been exchanged. Those additional reports include, but are not limited to, a report dated 7 April 2008 from Geotechnical Engineers (FE), a report dated 13 May 2015 from Leak Detection Specialist (IL), together with material in relation to the work conducted by the applicant in respect to repairs completed following acceptance of the claim in 2008, all of which have been exchanged. The panel chair Ombudsman attended onsite on 17 May 2017, with the applicant, a representative of the FSP, SC and GC. Finally, the panel has had the benefit of reviewing a number of helpful photographs which have assisted its deliberations. Whilst all of the information exchanged has been considered, only that information relevant to the final outcome will be referred to in this determination. This determination is made by a panel consisting of the panel chair Ombudsman, a representative with extensive experience in consumer claims and a representative with extensive experience in the insurance industry. 2.1 Has the FSP met its obligations in respect to the claims and dispute? The panel regards it is fair to say that this dispute has had a long and difficult history. As detailed above, numerous reports have been provided along with submissions from both parties. The panel does not propose to summarise all of the information, but simply to refer to those matters relevant to the final outcome. Case No: 432361 Determination Page 4 of 7 The exchanged material confirms that in early 2007, the applicant lodged a claim for cracking that had occurred at the insured property. The FSP accepted that the structural movement and cracking of the building was caused by the listed event of water damage and accepted the claim. SC recommended that the burst pipe be repaired and a suitable period be allowed for the soil at the property to dry out. Following re-attendance at the property, SC provided a further report dated 14 March 2008. The FSP says that because the likely repair cost would exceed the sum insured, it had no other option than to cash settle the claim as a total loss. Significantly, as part of its notice of response, the FSP says that it gave the applicant, ‘… all the information we had at the time of settling the claim.’ It is clear from the exchanged material that the information the FSP gave to the applicant at that time, did not include the report from RB. The FSP says that the report from RB was obtained in order to have a second opinion and the FSP’s current representative says that she can only assume the report was only obtained because the cost of repairs was exceeding the sum insured. The FSP says that the second opinion was taking too long and so a cash settlement was issued to the applicant for the full sum insured at that time. Finally, the FSP says that a copy of the RB report was not provided to the applicant as the initial claim had been finalised by the time the RB report was received. The panel notes that in addition, the FSP says: ‘The 2nd report recommends doing as little as possible to the house structurally. However, imagine if we put to the insured that we have one engineer recommending underpinning and one engineer recommending doing very little and there would have been a dispute because the customer would have pushed for the total loss settlement amount based on having to do underpinning etc. From our perspective, a settlement had been issued on the basis of the property being rendered a total loss because the sum insured was inadequate. We acted in good faith and cash settled the sum insured. We were no longer in control of repairs and it is our position that we cannot be held respons ible for the works carried out.’ In the panel’s view, the report from RB is significant for at least two reasons. First, RB was of the view that the repair method proposed by SC, was ‘fundamentally wrong’. Secondly, the applicant says: ‘(WH, the FSP’s repr esentative) was the only person that I had contact with. No one else. It now seems that his instructions to us were clearly not the instructions that he was given by the consulting engineer. After (WH) chased up the engineer and discussed the issue with h im, WH organised a meeting with my parents and I where he advised that the cost of repairs exceeded the amount that the house was insured for. He strongly advised us to accept the payout for the insurance claims so that the money would go further to cover repairs; especially if I project manage to keep the costs down. Case No: 432361 Determination Page 5 of 7 When I pointed out that I was inexperienced in this area, he assured us that ‘all the hard work had already been done’ by the Consulting engineer in his scope of works. He said that all I had to do was hire professionals who would follow the underpinning plans. He physically handed me the engineer’s plans, drawings and reports and then instructed me not to deviate from them.’ The FSP says that it has provided the applicant and the Service with all of the notes relevant to the claim in the dispute. The FSP says: ‘… This is a claim that was lodged nine years ago. I am not withholding anything – I simply have no access to any notes or reports and WH has not been with the organisation for some years .’ The FSP says that there is no evidence that an FSP assessor had advised that all the paperwork, reports, drawings, plans were finished, approved and ready to go or that it was stated or implied that no further engagement of experts was necessary by the applicant. Further, the FSP says that on the contrary, the applicant has admitted to being in possession of the reports from SC and specifically SC’s report of March 2008, in which the FSP says it is clearly stipulated that the report was not a final repor t and further engineering engagement was necessary before final plans could be drafted. The difference of opinion between the parties raises two questions. First, did the FSP’s representative, WH, represent to the applicant that the applicant simply needed to follow the report from SC? Second, was the report from SC of March 2008, a final report upon which the applicant could proceed with the proposed repairs? In respect to the first question, the panel is satisfied in the absence of specific evidence to the contrary, that WH did represent to the applicant that he could proceed with the repairs by following the report from SC. In respect to the second question, the panel notes that SC is fulsome in his position that the Scope of Rectification Works was proposed on the basis of assumed foundation construction and soil conditions and that further work including soil testing was required before preparation of final designs and work proceeding. Indeed, the document attached to SC’s report of 14 March 2008, is entitled ‘ PROPOSED STAGE 1 SCOPE OF RECTIFICATION WORKS ’. However, having reviewed the exchanged material and in particular the reports from SC dated 26 March 2007 and 14 March 2008, the panel is satisfied that SC’s use of the word ‘proposed’ was not a ref erence to preliminary or to a requirement that further investigation or work was needed before proceeding, but rather a reference to the work which was intended to be completed. The panel is also satisfied that the tone and content of SC’s report of 14 Mar ch 2008, would have led the applicant to believe he was entitled to proceed with the repairs on the basis of that report and the attached scope of rectification work. This is consistent with the applicant’s position that WH advised him to proceed on the ba sis of SC’s report. Case No: 432361 Determination Page 6 of 7 When combining the advice of WH and the report from SC, the panel is acutely aware that the contents of the report from RB are significant and the FSP’s failure to provide the applicant with a copy of that report, when it ultimately was received, deprived the applicant of the opportunity to consider what were obviously difficult and challenging alternatives. In the panel’s view, the FSP’s commentary regarding the repairs following cash settlement, detailed above, whilst likely formulated from a review of the history of this dispute, confirmed that it was likely that the FSP was indeed aware that the applicant did propose to proceed to repairs following the cash settlement of the initial claim. Given that the proposal suggested by RB was completely at odds with that suggested by SC, the panel is satisfied the FSP should have provided the report from RB as soon as it was received. The panel is of the view that the FSP has breached its obligations to the applicant which were not simply finalised by cash payment of the limit of the policy coverage. Further, the panel is concerned by the steps recommended by SC in his report of 14 March 2008 and the attached Proposed Scope of Rectification Works. SC says that prior to preparation of the report dated 14 March 2008, he was never requested to complete soil testing. Whilst the report of 14 March 2008 and the attached documents refer to obtaining the results of detailed Geotechnical Engineers Soils Investigations at the site, the panel is of the view that the scope of rectification works should not have been prepared in the absence of such soil testing. Further, GC identified that the building was supported by four separate concrete slabs with varying strengths. This does not appear to have been identified by SC. In this regard, the panel does not accept SC’s statement that ‘R egardless of whether this dwelling structure was supported upon a single slab or 4, 5 or 6, makes very little difference from an Engineering point of view …’ In the panel’s view, SC’s failure to identify four slabs raises significant doubt over the proposed scope of rectification works contained within SC’s report of 14 March 2008. The panel’s commentary in respect to the advice provided by SC, needs to be viewed in light of the 20 August 2008 report from RB, which significantly challenges the proposals suggested by SC. Whilst SC maintains that the failings at the site are the result of the failings of the geotechnical-structural engineer who carried out the work on behalf of the applicant, given what the panel views are failings in the approach taken by SC and the commentary from RB and GC , the panel cannot be so satisfied in respect to SC’s comments regarding the applicant’s geotechnical -structural engineer. Further, the panel has had regard to the comments from RB and GC, in regard to SC’s proposed solution. As stated, RB expressed the view that given the limited zone in which the building had lifted and heaved, SC’s suggested solution of underpinning and lifting is fundamentally wrong. Case No: 432361 Determination Page 7 of 7 Further, GC regarded SC’s design as counterintuitive in that it recommended underpinning and resin injection to lift a building that had been raised by soil swell from a ‘busted water pipe’. RB was of the view that resin injection would give a slightly differential means of support to the slab verses the underpins, which in the medium term, being 5 to 10 years, will cause ongoing distress and movement to the building. The panel notes with interest that the new damage noted by the applicant in 2014, occurred within the 5-10 year time frame from the resin injection. GC was of the view that the primary cause of the current damage to the building was the adoption of SC’s design. In particular, the underpinning and resin injection of the whole building when only a small portion may have been lifted by the water influx. It was GC’s view that the resulting damage has left the building in a worse state than it was in terms of its ground slabs being out of level. Having considered all of the exchanged material, the panel is satisfied that:  WH (the FSP’s representative) directed the applicant to proceed on the basis of SC’s report and his recommendations alone  The FSP should have but failed to provide the applicant with the report from RB, which significantly challenged the recommendations of SC  The current failings at the property are the result of work undertaken by the applicant based upon the report provided by SC alone and in the absence of the report from RB. In the circumstances the panel is satisfied that the FSP is responsible for the current damage at the property and the applicant’s loss. The panel is of the view that it is fair in all the circumstances, given the FSP’s and its representative’s failings, that it compensate the applicant for his loss. However, the exchanged material does not include sufficient details regarding the cost to repair the damage. The Terms of Reference of the Service limit the maximum total value of the remedy that may be decided upon by the Service (excluding compensation for costs and interest payments) to $309,000. Given the absence of an accurate quotation in regard to the repairs required, the panel is satisfied that the FSP at its discretion, should have the opportunity to either repair the property or cash settle the applicant to the limit of the Service’s jurisdiction. Given the FSP’s failure to provide the applicant with the report from RB and the resultant delay and inconvenience to the applicant, the FSP should pay the applicant an additional amount of $3,000, for non-financial loss compensation.