The applicant claimed for cracking and movement damage to her home, which she attributed to leaking storm water and sewerage pipes, and said claim delays caused further damage. AFCA found the damage was caused by excluded earth movement and that the FSP handled the claim reasonably, so no order was made.

On the balance of probabilities the proximate cause was excluded earth movement, not the leaking pipes, based on damage pattern, prior underpinning and floor level surveys.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 432339 Determination Page 1 of 8 Case number: 432339 30 March 2017 1 Overview 1.1 Dispute The applicant lodged a claim under her home insurance policy with the financial services provider (FSP) for cracking and movement damage to her property. The applicant considers the damage has been caused by water leaking from cracked storm water and sewerage pipes at her property. The FSP denied the claim on the basis that the damage was not caused by leaking pipes (or by any other event insured against under the policy) but by naturally occurring earth movement over a prolonged period of time, which is excluded from cover under the policy. The applicant disputes the FSP’s denial of her claim. She also says the FSP’s delay in finalising the claim has resulted in additional damage to the property. 1.2 Issues and key findings Is the FSP liable for the damage to the property? The available information establishes that, on the balance of probabilities, the cracking and movement damage to the applica nt’s property was caused by naturally occurring earth movement. The nature and extent of the damage is not consistent with it having been caused by water leaking from the damaged storm water and sewerage pipes at the south eastern corner of the property. Damage caused by naturally occurring earth movement is not covered under the policy. Accordingly, the FSP is not liable for the applicant’s claim . The approach adopted by the FSP to investigating the cause of the damage and assessing the applicant’s claim was reasonable in the circumstances. Accordingly, the FSP is not liable for any additional damage to the property during the claim process. 1.3 Determination This determination is in favour of the FSP. The FSP is not liable for the damage to the applicant’s pr operty. Case No: 432339 Determination Page 2 of 8 2 Reasons for determination 2.1 Is the FSP liable for the damage to the property? Policy provides cover for insured events subject to exclusions The applicant is required to show that, on the balance of probabilities, she has suffered a loss caused by a risk insured against under the policy. This is known as a valid (or prima facie ) claim. If the applicant is able to establish a prima facie claim, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The applicant’s p olicy provides cover for damage caused by the events listed in the policy (including liquid leaking from a fixed pipe, drainage or sewerage system), subject to the conditions and exclusions set out in the policy. Applicant has established a prima facie claim The available information establishes that a cracked sewerage pipe and blocked storm water pipe were identified near the south east corner of the property in May 2014. These pipes were repaired by the applicant in December 2014. The reports prepared by the engineers appointed by the parties (FM and RB) confirm that the property has suffered extensive cracking and movement damage. This damage includes cracking to the external wall on the east side of the property and around the bay window in the front master bedroom (in the vicinity of the leaking pipes). In these circumstances, the panel is satisfied that the applicant has established a prima facie claim under the policy. Accordingly, the FSP bears the onus of establishing that, on the balance of probabilities, it is entitled to rely on a policy exclusion or is otherwise entitled to deny the applicant ’s claim. The FSP says it is not liable for the claimed damage because the leaking sewerage and stormwater pipes did not cause the cracking and movement damage to the applicant’s home. The FSP says the damage was caused by earth movement over an extended period of time, as a result of naturally occurring variations in the moisture content of the surrounding soils. The policy excludes cover for damage caused by subsidence, collapse, shrinkage or any other form of earth movement (unless specifically covered under certain insured events). In order to establish that it is entitled to deny the applicant’s claim, the FSP must show that the proximate cause of the cracking and movement damage (that is, the Case No: 432339 Determination Page 3 of 8 real, effective or dominant cause) was naturally occurring earth movement and/or other factors which are not subject to cover under the policy. Property has experienced long-term movement issues The FSP’s records refle ct that, when the claim was lodged in April 2014, the applicant’s husband advised that the movement at the property appeared to have been going on for around nine years but had worsened in recent months. The applicant has subsequently confirmed that underpinning works to the front of the property were undertaken in early 2007, based on advice provided by an engineer engaged by the applicant at the time. The property was underpinned in five separate locations, following which repairs to the external brickwork were completed. The photographs taken during inspections of the property for the purpose of the current claim indicate that the stepped diagonal cracks to the external brickwork repaired in 2007 were reasonably significant, and affected both the easter n and western wing walls at the front of the property. Both the FSP’s engineer (FM) and the applicant’s engineer (RB) have been highly critical of the underpinning works carried out in 2007. The FSP’s engineer (FM) considered that the underpinning w orks had been inadequate and ineffective to address the cracking and movement damage to the property. FM advised that the pins were not installed deeply enough (given the highly reactive clay soils at the property) and the works did not comply with the applicable Australian standard. The applicant’s engineer (RB) described the underpinning works as “a travesty of the first order”. He confirmed that underpins installed at a shallow depth are not effective to stop movement and could in fact have the opposite effect, by locking onto the bluestone foundations and pulling them downwards. Engineers have provided differing opinions Both engineers appointed by the parties confirmed that the applicant’s property was founded on highly reactive clay soils, which were susceptible to volumetric changes as a result of variations in moisture content. However, the engineers have provided differing opinions about what caused the cracking and movement damage which is the subject of the current claim. The FSP’s engineer (FM) concluded that the cracking and movement damage had been caused by differential movement due to naturally occurring changes in the moisture content of the reactive clay foundation soils. Specifically, FM considered that the foundation soils at the property had dried out, resulting in shrinkage and settlement (downwards movement), which was most noticeable in the southern (original) section of the property. Case No: 432339 Determination Page 4 of 8 FM advised that the differential movement at the property had occurred over a long period of time as a result of factors including:  the drying effects of the roots of several medium to large trees located near the front of the property;  an extended period of drought followed by a return to normal rainfall conditions, as well as usual seasonal variations;  relative differences in the moisture content of the foundation soils on each side of the property (due to one side sharing a party wall, while the other did not); and  certain features of the property (including the nature of the footings, the design of the sub-floor area and the lack of adequate drainage) which made it particularly susceptible to differential foundation movement. The applicant’s engineer (RM) agreed with FM that the drying out of the foundation soils had resulted in settlement (downwards movement) of the building, which had contributed to the cracking and movement damage affecting the southern end of the property. In this regard, RM noted that there was “a fair amount of foliage far too close” to the front of the building which he believed was having a drying effect. However, RM also considered that, given the nature of the foundation soils, water leaking from the damaged stormwater and sewerage pipes would have caused the soil to lose its shear strength, rendering it unable to support even light loads and resulting in subsidence of the building. Damage was caused by naturally occurring earth movement Having carefully reviewed the available information, the panel considers that the proximate cause of the damage to the applicant’s property was naturally occurring earth movement over an extended period of time. While damaged storm water and sewerage pipes were identified at the south-east corner of the property, the panel is not satisfied that the nature and location of the cracking and movement damage observed is consistent with it having been caused by water leaking from these pipes. While there is extensive damage to the front of the property on the eastern side, the numerous photographs of the damage provided confirm that there is also significant damage to other parts of the property. This damage includes the substantial rotation of the front western wing wall and cracking damage to the western side of the hallway. The evidence of past underpinning works and previous repairs confirms that the property was experiencing serious movement issues as long ago as 2007, many years before the damaged pipes were discovered. It is clear from the photographs provided that at least some of the current damage has occurred in the areas which were repaired in 2007, as reflected by the opening up of previously filled in cracks. Case No: 432339 Determination Page 5 of 8 The panel accepts the view expressed by FM that the pattern of differential movement at the property (as reflected in the floor level surveys) is not consistent with the damage having been caused by the effects of water from the leaking pipes. The comparative floor level surveys carried in July 2014 and June 2015 (before and after the damaged pipes were repaired) support FM’s conclusion that the leaks did not contribute to the damage observed. The pattern of differential movement at the property (as reflected in the contour patterns derived from the floor level surveys) did not change significantly after the pipes were repaired. While the level surveys conducted by RM in September 2015 reflect different absolute measurements, the contour patterns are generally similar. Where differential movement has been caused by water escaping from underground pipes further movement will usually continue after the pipes have been repaired, as the foundation soils gradually dry out and the moisture content stabilises. In his report, RM has suggested that water escaping from the damaged pipes could have contributed to the settlement observed at the property, together with the drying out of the foundation soils. RM states that the escaping water would have wetted the foundation soils to such an extent that they would have lost shear strength, resulting in subsidence of the building. While RM stated that a loss of bearing strength would have occurred once the soils reached a moisture content of 40%, FM considered that a moisture content of 70% would have been required to produce this effect. In the present case, the panel is not satisfied that water would have leaked from the damaged pipes in sufficient volume to result in a loss of bearing strength in the surrounding soils. While the investigating plumbers identified a “major fracture” of the stormwater pipe and “two major … misalignments” of the sewerage pipe, the nature of these pipes is such that water flows through them on an intermittent basis only. Further, it is unclear from RM’s report whether he considers that the escape of water from the two damaged pipes discovered in May 2014 would have been sufficient to cause the damage observed. In his report, RM concluded that it was highly likely that there was still one or more additional leaks at the property which had not yet been discovered, and which were contributing to the differential movement observed. However, no further leaks have been identified to date. For the reasons outlined above, the panel is not satisfied that the identified leaks to the storm water and sewerage pipes contributed to the cracking and movement damage at the property to any significant extent. The panel considers the proximate cause of the damage was naturally occurring earth movement which had affected the property over an extended period of time. Case No: 432339 Determination Page 6 of 8 FSP is not responsible for further damage to the property The applicant says further damage to her property has occurred due to the delays experienced during the claim process. She also says the FSP provided conflicting advice about whether repairs should be deferred while it carried out further investigations. Having carefully reviewed the claim history, the panel is satisfied that the FSP managed the claim reasonably in the circumstances. After the applicant lodged her claim, the FSP appointed a builder (JP) to assess the damage to the property. After attending the property, JP recommended that an engineer be appointed to determine the cause of the damage. Given the nature of the damage, the FSP’s engineer (FM) advised that leak detection testing should be carried out to identify whether there were any issues with the pipes at the property. Extensive leak detection tests were carried out between May and July 2014, during which the issues with the storm water and sewerage pipes were identified. An investigation of the large council stormwater drain running underneath the property was also conducted. F ollowing completion of the leak detection testing, the FSP’s engineer (FM) completed her report which concluded that the claimed damage had been caused by naturally occurring earth movement. In early August 2014, the FSP advised the applicant that the claim would be denied based on the findings in FM’s report that the leaking pipes had not caused or contributed to the damage. The FSP also sent the applicant a copy of FM’s report and the leak detection test results and confirmed that she would be responsible for repairing the damaged pipes. However, the FSP also arranged for FM to re -attend the property six months after the repairs to the pipes had been completed. As outlined in FM’s report, the purpose of the proposed re -inspection was to confirm whether F SP’s initial findings as to the cause of damage were correct, based on the extent of further movement at the property once the pipes were no longer leaking and any remaining moisture in the soils had dried out. By scheduling a reinspection in a furthe r six months’ time, the FSP was attempting to ensure that all possible avenues were explored, in circumstances where the claim would otherwise have been immediately denied. Accordingly, the further reinspection could only benefit the applicant. It was not possible for the FSP to reinspect the property any earlier, as it is usually at least six months after pipe repairs are completed before the surrounding soils dry out sufficiently to allow a comparative assessment to occur. Having carefully reviewed the claim records, the panel is satisfied that the FSP clearly advised the applicant of its preliminary decision regarding the outcome of her claim, and the rationale for the further inspection. Case No: 432339 Determination Page 7 of 8 The FSP also provided the applicant with a copy of the leak detection reports in August 2014, which recommended that the pipe repairs be carried out as soon as possible (although the applicant did not complete these repairs until several months later). In addition, the FSP sent the applicant a copy of FM’s initial re port, which recommended that she urgently engage a structural engineer to undertake make safe works to the front of the house, which had been compromised by foundation settlement and the previous underpinning works. While the final repairs could not be carried out until the further movement (if any) resulting from the drying out of the soils had ended (and FM’s reinspection had been completed), it is possible that interim make safe works could have been carried out in order to minimise further damage. For the reasons outlined above, the panel considers the FSP managed the claim appropriately. Accordingly, the FSP is not liable for any additional damage to the property during the claim process. Case No: 432339 Determination Page 8 of 8 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS recommendation. Due to the nature of the dispute, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the FOS Terms of Reference. The panel consists of an Ombudsman and two representatives with consumer and insurance experience. The panel has decided this dispute based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, the panel has restricted its commentary to those issues that it considers directly relevant to the outcome only.