Text of the determination
Determination
Case No: 431363 Determination Page 1 of 9
Case number: 431363 7 December 2016
1 Overview
1.1 Dispute
The applicant lodged a claim under her home insurance policy with the financial
services provider (FSP) following a storm in May 2015 that damaged her home.
The FSP accepted the applicant’s claim and cash settled her for a total of
$141,919.21 for the cost of building repairs, replacement of contents items and
temporary accommodation.
The applicant says the cash settlement amount is not sufficient to repair all of the
damage to the building caused by the storm and meet her temporary accommodation
expenses. She also seeks compensation for various financial and non-financial
losses incurred as a result of the FSP’s handling of her claim.
1.2 Issues and key findings
Is the FSP required to increase the settlement amount for building repairs?
The cash settlement amount should be increased by $10,769 to reflect the cost of
replacing the mould-affected air conditioners, as the available information does not
establish that they can be effectively remediated.
Is the applicant entitled to further temporary accommodation costs?
The FSP has paid the applicant her full entitlement under the policy for temporary
accommodation costs and she is not entitled to any additional amounts.
Is the applicant entitled to compensation?
The circumstances of the dispute do not justify the award of compensation.
1.3 Determination
This determination is partly in favour of the applicant.
The FSP is to pay the applicant an additional amount of $11,533.96 (to allow for the
costs of replacing the air conditioners and the microbial spray) in full and final
settlement of her claim .
The FSP is required to pay interest on the additional amount at the rate determined
in accordance with section 57 of the Insurance Contracts Act 1984 (Cth), from 29
February 2016 until the payment date.
Case No: 431363 Determination Page 2 of 9
2 Reasons for determination
2.1 Is the FSP required to increase the cash settlement amount?
Cash settlement amount addresses damage from two separate events
After the applicant lodged her claim, the FSP appointed a building consultant (S) to
inspect the damage to the property caused by the storm in May 2015.
S did not identify any storm damage to the roof of the property. He concluded that the
internal water damage to the property had occurred due to wind driven rain entering
under the side lap of the roof sheets. As S was unable to access all parts of the roof,
he engaged a specialist roofing contractor (PT) to carry out a further inspection.
During his inspection, PT identified a number of pre-existing issues with the roof
which he considered had allowed water to enter during the storm.
These issues are clearly reflected in the photographs included in PT’s report and
include the use of short roof sheets, loose fixings and corrosion to the roof sheets
(which PT noted was more extensive than initially identified, due to the roof having
been repainted).
PT also observed a number of dents in the roof sheeting, the majority of which he
concluded had been caused by foot traffic (due to their size and shape). However, he
also identified a small number of dents which he considered had been caused by
hail.
The applicant has provided reports from her own roofing contractors (PC and MT).
While both PC and MT noted the dents to the roof observed by PT, neither identified
any damage to the roof caused by the storm in May 2015. MT concluded that the hail
damage to the roof had been caused by an earlier storm in November 2014.
Following receipt of the roofing reports, the FSP accepted liability for the cost of
removing and replacing the roof in its entirety, on the basis that some portion of the
damage to the roof had been caused by the hail storm in November 2014. The FSP
did not seek to reduce its liability due to the pre-existing issues with the roof identified
by PT.
The FSP required the applicant to lodge a separate claim for damage arising from
the earlier hail storm and settled her for the roof repairs under this claim. The FSP
imposed a policy excess of $2,000 in respect of this claim, in addition to the excess
of $2,000 which applied to the claim for internal water damage arising from the storm
in May 2015.
The panel is satisfied that the approach taken by the FSP was appropriate in the
circumstances. None of the contractors engaged by the FSP and the applicant
identified any damage to the roof caused by the storm in May 2015.
Accordingly, to the extent that the FSP was liable for replacing the roof, this can only
have been due to the damage caused by the earlier storm in November 2014 (which
was a separate insured event under the policy). In these circumstances, it was
Case No: 431363 Determination Page 3 of 9
appropriate for the roof repairs to be dealt with as a separate claim, subject to an
additional policy excess.
Applicant says cash settlement underestimates cost of repairs required
The applicants’ policy provides that, where a claim for building damage is cash
settled, the FSP will pay the applicant the costs (to the FSP) of repairing the building
to its condition when new.
The cash settlement amount paid by the FSP included a total of $111,457.47 for the
cost of replacing the roof and repairing the internal damage to the applicant’s
property.
This amount was based on quotations provided by the FSP’s builder (PA) for the
repairs set out in separate scopes of work prepared by the FSP’s building consultant
(S) for the roof replacement and the internal repairs.
The applicant says that the cash settlement amount does not provide for the cost of
repairing all of the internal damage to the property caused by the storm in May 2015.
In particular, she says that this amount does not make sufficient allowance for the
cost of addressing the mould growth at the property, which has continued to worsen
due to ongoing water entry issues following the storm in May 2015.
The applicant has provided an alternative scope of works and quotation for
$215,280.23 prepared by her builder (HA). She says the cash settlement amount for
the building repairs should be increased to reflect the amount quoted by HA.
Cash settlement amount is generally fair and reasonable
As outlined above, the cash settlement amount for the internal repairs was based on
the scope of works prepared by the FSP’s building consultant (S).
Having reviewed the available information, the panel is satisfied that S’s scope of
works generally provides an accurate assessment of the damage to the property
caused by the storm in May 2015 and a detailed breakdown of the works required to
repair that damage.
The repairs included i n S’s scope of works are generally consistent with the claim -
related damage to the property as identified in the various reports provided, and the
photographs taken, by the various contractors who inspected the property.
After the applicant raised concerns about the adequacy of the scope of works, the
FSP arranged for its quality and technical loss adjuster (SB) to reinspect the property
and review S’s scope of works, in conjunction with the alternative scope of works
provided by the applicant’s builder ( HA).
In his reinspection report prepared in January 2016, SB identified the key differences
between the two scopes of work as follows:
HA’s scope of works included the painting of all exterior cladding, doors and
windows, eaves and fascia boards and the front and rear stairs, while S’s scope
of works did not;
Case No: 431363 Determination Page 4 of 9
HA had provided for the replacement of a number of fixtures and fittings
(including lights and electrical fittings, the bathtub and bathroom floor tiles and
the kitchen sink), while S’s scope of work s provided for the reinstatement of the
existing items following the repairs; and
HA’s quotation allowed for the full costs of removing and replacing the asbestos
ceiling and wall linings throughout the entire house, on the basis that this was
required to effectively eradicate mould.
Having carefully reviewed the available information, the panel is not satisfied that the
additional items included in HA’s scope of works are necessary in order to repair the
internal damage to the property arising from the storm in May 2015.
In his report, SB advised that there was no storm damage evident to the exterior of
the property and any need for external painting had arisen as a result of the gradual
deterioration of the paintwork over an extended period of time. The photographs
included in SB’s report support his conclusions in this regard.
The scope of works and quotation provided by HA did not identify the reason why he
considered the exterior of the house was required to be repainted. While the
applicant says the exterior was affected by mould, there is no independent
information to support this.
SB also confirmed that the additional internal fittings and fixtures included in HA’s
scope of works had not been damaged by the storm and therefore could be reused
(rather than being replaced). This is consistent with the approach reflected in S’s
scope of works.
Neither HA’s scope of works (nor any of the other information provided) identifies any
damage to these fixtures and fittings as a result of the storm. Give n these items were
reinspected by SB in January 2016, the panel is satisfied that they do not require
replacement.
In relation to mould remediation, S’s scope of works provides for the removal and
replacement of the asbestos wall and ceiling linings in the affected rooms (as was
also proposed by HA).
However, following his reinspection of the property, SB concluded that the
replacement of the asbestos linings was unnecessary, as the mould could be
eradicated using the “peel away” method.
This is a process whereby specialised stick on sheets are applied to mould-affected
linings in order to remove peeling paint and mould, leaving the linings clean and
ready to be sealed and repainted. SB confirmed this process would be effective to
remove the existing mould and prevent it recurring.
The FSP has agreed to increase the cash settlement amount by an additional
$764.96 to allow for a microbial treatment spray to be applied following completion of
the peel away process.
The panel notes that, even if the “peel awa y” process is not effective, the quotation
provided by PA (which was used to determine the cash settlement) was prepared
based on the repairs set out in S’s scope of works. Accordingly, PA’s quotation can
be taken to include the cost of removing and replacing the affected asbestos linings.
Case No: 431363 Determination Page 5 of 9
When S queried whether the amount quoted by PA was sufficient to provide for the
costs of these works, PA confirmed that it was and remained willing to undertake the
repairs on this basis.
For the reasons outlined above, the panel is sa tisfied that S’s scope of works and
PA’s quotation represent a reasonable basis for determining the cash settlement
amount, subject to the specific issue identified below.
Settlement amount should be increased to provide for replacement of air
conditioners
The applicant says the cash settlement should be increased to allow for the
replacement of five air conditioners at the property, which have been contaminated
by mould.
The FSP’s building consultant (S) expressed concern about the air con ditioners in
August 2015, as they had all been kept running in an attempt to keep the house dry
and prevent the further spread of mould.
However, S did not express a concluded view as to whether the air conditioners
could be effectively remediated or whether they would need to be replaced.
The applicant has provided a report from her air conditioner specialist (BR), who
advised that the amount of moisture present at the property far exceeded the
capacity of the air conditioners.
BR confirmed that, whil e he had treated the air conditioners with fungicide “as a
courtesy”, this treatment was not guaranteed to be effective as the mould spores
were difficult to eradicate. Accordingly, BR advised that the units would need to
removed and replaced.
The FSP has not provided any information which refutes BR’s findings.
Based on the information provided, the panel is not satisfied that the mould -affected
air conditioners can be effectively remediated.
Accordingly, the FSP is required to increase the cash settlement amount by $10,769
(being the amount of the quotation provided by the applicant for the replacement of
the air conditioners).
2.2 Is the applicant entitled to further temporary accommodation costs?
Policy provides limited cover for temporary accommodation
The applicant’s policy provides cover for the reasonable costs of temporary
accommodation where she is required to move out of her home because it has
become unfit to live in due to an insured event.
The policy provides for the payment of temporary accommodation costs while the
property is repaired, for a period of up to twelve months from the date of the insured
event.
Case No: 431363 Determination Page 6 of 9
The amount payable is limited to the market rent of the applicant’s property as at the
date of the insured event, capped at 10% of the building sum insured.
Applicant is not entitled to further payments for temporary accommodation
The FSP has cash settled the applicant for a total of $26,180 for temporary
accommodation costs.
This amount reflects the rental costs incurred by the applicant for the period from
1 September 2015 (when she moved out of her home due to mould) to 1 May 2016
(being twelve months after the storm occurred).
The amount paid by the FSP for temporary accommodation costs was based on the
weekly rental of $770 for the property to which the applicant relocated in September
2015.
Based on the information provided, the panel considers that the FSP has paid the
applicant her full entitlement to temporary accommodation costs under the policy.
As outlined above, temporary accommodation benefits are limited to a period of
twelve months following the insured event.
Further, the FSP agreed to calculate temporary accommodation benefits based on
the actual weekly rental paid by the applicant for her alternative accommodation. The
FSP did not reduce the amount paid to reflect the market rent of the applicant’s
property (as it was entitled to do under the terms of the policy).
The applicant seeks payment of an additional five months’ worth of temporary
accommodation costs. She says that the FSP has unreasonably delayed the
settlement of her claim, which has caused her to incur additional costs.
While it has taken an extended period of time to resolve the applicant’s claim, the
FSP has not been primarily responsible for the delays which led to the additional
costs incurred by the applicant.
The FSP was ready and willing to commence the roof repairs by early September
2015, and the internal repairs approximately eight weeks later. In late January 2016,
the FSP offered to cash settle the claim for the estimated cost of repairs, as the
parties had been unable to agree on a scope of works.
For the reasons outlined above, the panel is satisfied that the cash settlement offer
made by the FSP in January 2016 was generally appropriate.
Had the applicant accepted the offer made at that time, she would have had sufficient
opportunity to complete the necessary repairs before her entitlement to temporary
accommodation benefits under the policy expired.
Accordingly, the applicant is not entitled to any additional payments for temporary
accommodation.
Case No: 431363 Determination Page 7 of 9
2.3 Is the applicant entitled to any additional amounts?
Applicant seeks compensation for various financial and non-financial losses
The applicant seeks reimbursement for certain additional costs incurred as a result of
having to move out of her property, including the costs of:
telephone and water services at her temporary rental accommodation;
returning her contents to the insured property once the repairs have been
completed; and
relocating her elderly father (who suffered from dementia) to Melbourne in June
2015, due to respiratory issues suffered as a result of water and mould damage
to the house.
The applicant also seeks compensation for stress and inconvenience suffered by
herself and her father, as a result of the manner in which the FSP handled her claim.
Applicant is not entitled to payment for additional expenses
The applicant’s policy provides for the payment of certain additional amounts,
including the cost of removing and returning contents from storage when she is
required to move out of her property, as well as reasonable extra living expenses
following an insured event.
The cash settlement paid by the FSP for damage to the applicant’s contents items
caused by the storm in May 2015 included the cost of transporting her contents to
her temporary rental accommodation. The cash settlement for building repairs
included an additional amount of $3,500 for the removal and return of furniture items.
To the extent that the applicant can be considered to have incurred reasonable extra
living expenses following the insured event (such as water and telephone connection
costs), the panel considers she has been adequately compensated for these
expenses by the amount paid for temporary accommodation costs.
As outlined above, the amount paid exceeded the applicant’s entitlement under the
policy (as it was based on a figure in excess of the estimated market rental for her
property).
The applicant is not entitled to reimbursement for the additional costs incurred in
relocating her elderly father to Melbourne. The FSP’s obligation to fund relocation
costs in these circumstances is limited to the costs of renting an equivalent
alternative property in a comparable location.
Applicant is not entitled to compensation for non-financial loss
The panel acknowledges that the claim process has been difficult for the applicant, in
part because the usual stress and inconvenience associated with an insurance claim
has been exacerbated by her father’s d ementia, which has made relocation from the
insured property more traumatic.
However, having carefully reviewed the claim history, the panel is satisfied that the
FSP managed the claim reasonably overall.
Case No: 431363 Determination Page 8 of 9
The claim process was complicated by the fact that the hail damage to the roof
discovered during assessment of the claim arose from an earlier event and therefore
needed to be addressed under a separate claim.
However, the panel is satisfied that the applicant was not disadvantaged by this
process. As outlined above, the FSP accepted liability for the full cost of replacing the
roof, even though the specialist reports obtained indicated that (at least to some
extent) the need to replace the roof arose from other factors.
While several inspections over a period of some months was required to fully assess
the damage, finalise the scope of works and obtain quotations, this timeframe was
not unreasonable given the nature and extent of the damage claimed.
As noted above, the FSP was ready and willing to commence the repairs in
September 2015, several months after the fire.
The bulk of the delays experienced since that time have been due to the applicant
having disputed the approved scope of works for the repairs, which the panel has
found to be generally reasonable (subject to the single issue identified above).
For the reasons outlined above, the panel does not consider that the circumstances
of this dispute re such as to justify the award of compensation for non-financial loss.
Case No: 431363 Determination Page 9 of 9
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS recommendation. Due to the nature
of the dispute, it has been referred directly to a panel for determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The panel has decided this case based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous Financial Ombudsman Service (FOS) decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, the panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.